Got Unwanted PR after MRP run

Hi,
Can sombody give me some tips?
The following is my perplexed thing:
Material Strategy group is 10.
Today is 2010-05-19, the stock is zero.
The material's planned delivery time is 30 work days .There is a LSF requirment 500 pc on 2010-05-19.
And also There is a 500 pc PO whose Delivery Date is 2010-07-20.
When MRP run,we find we get a PR whose purposed quantity is also 500 pc and Delivery Date is  2010-06-18.
However since there is a PO whose Delivery Date is 2010-07-20,we only need an Exception message number for the PO,not a PR after MRP run. In another client we can get what outcome we antcipate. But in this client we can not find where the problem is.Can somebody tell me where the problem is ?
Regards
chunhui

Hi,
Is there no exception message for the existing purchase order??
As i u/s there would be exception message for the purchase order exception message might be 20(cancel process).
If it is so then check the settings for reschdeuling (OMDW)  with the existing client & in the client where you are getting the result correctly.
Check n revert.
Regards
Mithun

Similar Messages

  • Creation of Purchase Order automatically via PR after mrp run.

    Hi Experts,
    I want  to know that , after MRP run  i got the no of PR'S. As i know , through MD04  i can create purchase order from particular pr but is their any option from which purchase order  get generated automatically from pr's which are generated afrer MRP run.
    Thanks n Regards
    Anupam

    Hi,
    You can maintain source list Tcode ME-01 and make it MRP relevant by selecting Sorce list MRP relevant. In sorce list you can maintain vendor and material data valid for particular period and make it MRP relevant.
    With this you can automatically generate purchase order from Purchase requisitions after MRP Run.
    Regards,
    Tushar Patankar

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Schedule lines are not coming after MRP run for HALB material

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Dear All,
    I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
    Thanks for all the reply.
    Thanks & Regards'
    Kundan Kumar

  • How system will generate schedule line for PO after  MRP run.

    Dear Experts,
                                 i have updated  MPS in MD61, the period indicator was  M (monthly),  after  MRP run, system  generating schedule  lines  on daily basis for Scheduling Agreement(ME38), i want  schedule lines   on mpnthly basis, how to achive this,
    thanks in advance.
    regards
    rajakarthik

    Hi
    1. Are you maintaining any Planning time fence period for MPS- No 
    2. What is the PIR qty you maintained in MD61:
                                                                                    i.) FG01 is having BOM  child part RM01.
                              To  produce 1 nos of  FG01 , I need 1 nos of  RM01                                                                               
    ii.) i maintained  FG01 in MD61  with PIR  Qty 5000. in MD61,Planning period is M  and planning hirizon1- jan10To 31-Jan10
           ii.)  i maintained lot size:Monthly lot size for RM01.
           iii.)  there is  no stock  available for  both RM01 and FG01.                                                                               
    3. After MRP how much qty is get planned on what date-     
         i)   planned order created for FG01 in co41 with qty-5000 nos.
         ii)  in ME38, schedule  line created for RM01,  on 01-01-2010, with 5000 nos,  currently Category of Delivery Date
    field is D and delivery date is   01-01-2010, but i want Category of Delivery Date should  be M and delivery date should be 01.2010.
    thanks
    raja

  • Automatic creation of Schedule line after MRP RUN

    Hi,
    Till now we are  using only PO for placing orders to vendor, now we want to use the functionality of scheduling agrement,  so that after MRP run,  we can get automatic schedule line creation,  for this ,  what are settings required, how system create the automatic schedule lines based on which criteria, second thing while creating on eschedule agrement i found that the conditon which i can add for a vednor in ME21N  that all condition are not coming while creating schedule agrement  even my vendor is same for PO and Schedule agrement,  so what are  the setting required for this.
      regards,
       zafar

    Hi
    1.In material master purchasing view data auto PO is to be flagged.If scheduling agreemet with release documentation.
    Then flag JIT indicator 1.
    2.maintain MRP views in material master
    3.In source list for fix vendor,source list usage 2 is to be maintained.
    4.Vendor master purchasing data auto PO indicator is to be flagged.
    5.Then when you run MRP automatically schedule lines are generated.
    For JIT and forecasting maintain creaton profile in OMUP transction.
    Assign the creation profile in scheduling agreement.

  • PR created after MRP run, instead of schedule line

    Dear all,
    I want to create schedule lines automatically from the planning run, for raw material. I have maintained info record, scheduling agreement, quota arrangements and also the source list.
    For the raw material, safety stock of 1000 nos. has been maintained. The current stock of the material is 0.
    After MRP run, based on the upper level PIRs, schedule lines are generated properly. But, against the safety stock of 1000, a PR is generated.
    I donot want a PR to be generated.
    Please suggest a solution.
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 8, 2008 4:17 PM

    Dear all,
    I checked an found that the schedule agreement date does not have any effect. Even if the requirement date falls outside the date range, i am able to create schedule lines.
    I also found that if i maintained GR processing time, then always a PR is created. If GR processing time is 0, then only schedule line is created. Moreover, planned delivery time does not have any effect on the calculations, even if it is 10 days, 20 days or 900 days.
    Can someone please clarify all these? How are these times taken into account?
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 9, 2008 3:04 PM

  • Automatic creation of PR after MRP run

    Hi,
    can anyone please tell me what all fields are picked up in a Purchase Requisition(PR) in the scenario of automatic creation of PR after MRP run.
    If we are using more than 1 PR type in the system how is it determined during the MRP run that the PR will be created for which type.I understand that source list will have to be created and maintained but how is the PR type determined
    Thanks in advance

    In PR the system checks for the material and vendor. See the steps below.
    Step1:Auto PO tick in material master Purchasing view (mandatory)
    Step2:Auto PO tick in vendor master Purchasing view
    Step3:Maintain Source list for vendor and material (If u r not using source list for auto PO creation, the assign the Source of supply to a PR in ME56)
    Step4:Maintain Pur. Inforecord
    Step5:ME59n : execute for PR and Vendor In ME59n, you can also select the PR document type. If you want to select different document types, go for multiple entries and enter the doc types.
    When u execute, the system will give the appropriate PRs. Select the required and convert to PO.
    But through MRP you cannot create PO directly only Planned orders can be created.
    Reward if helpful..
    Thanks,
    Srib

  • Planned order created after mrp run instead of purchase req

    Hi All,
    I am facing a strange problem about planned order being created after mrp run jobs runs in background instead of purchase req. This is happening randomly. In the material master MRP view 2 procurement type is F and in the varient for the MRP job the in Purchase requisition control parmater 1 is marked that is purchase requisition. Also planning file is having the entry once there is shortage and hence MRP run is there always if there is shortage of material.
    With Regards
    Tarun

    Hi Tarun,
    Please maintain the control parameters as
    Processing Key                                       NETCH
    Create Purchase Requisition                          1
    Sched. Agreement Schedule Line                   3
    Create MRP List                                            1
    Planning Mode                                               1
    Scheduling                                                     1
    Please let me know the results.
    Regards,
    satyajit

  • Purchase req type after MRP Run

    Ca we control the type of Purchase req after MRP Run.
    Now for every material it is creating "NB" type purchase req.
    Can we control it material type or by mat number.
    We have 2-3 purchase req types in system for Material.
    Amit Shah

    Dear ,
    Goto -OPPR-Enter Plant Code and Maintain MRP Group -0000( as SAP Standrad for External Procurement ) -Select Scheduling /Doc Type tab -Here you can assing the PR type as per your requirement so the while MRP run , it will selct the PR documents types based on OPPR .At the same time , assing this MRP group in MRP1 view of the material .
    Try and come back
    Regards
    JH

  • Track Changes the qnantity change of PR after MRP run

    Hi Experts
    Please suggest as i am unable to find any solution of following problem.
    My CLient wants to keep track the changes made to PR's after MRP run. When running MRP, already existing requirements (PRs) are automatically changed. These changes are not taken into account by BW extractors since no change document is generated.
    for e.g ,if we check stock requirememt list (MD04), PR of qty 20 exists. Now if i create a manual reservation of qty 20 and then run MRP, the the PR qty will change to 40. But i am unable to track this in CDPOS or CDHDR tables.
    Please suggest.
    Pradeep Bansal

    There are 2 ways to track the PR changes
    1.Goto PR display ME53N  --> Environment ---> item changes
    2.Goto CDHDR Table ,input doc object - BANF ,object value as PR no and get the docuemtn no .Pass this doc no to CDPOS and get the change details
    Hope it helps

  • Vendor in PR after MRP run

    hi all,
    is it possible to adopt vendor details in PR directly after MRP run ?
    thanks in advance

    thanks tejas for the reply.
    yes i want vendor to be adopt in PR after MRP run.
    if i maintain Info record or source of supply for the material w r t vendor.
    and if i run mrp then in PR vendor should adopt directly. is it possible ?

  • How system calculate the required qty. after MRP RUN

    Hi,
    I want to know if we are using MRP Type as PD and also we are calculating automatic saftey stock and re order point qty. after MRP RUN according to which rule formula system calculate the safty stock, reorder point qty. and the required qty. as a PR.
    and if we are not using calculate safety stock automatically and if we set safety stock qty. manually in this case how system will calculate the required qty.
    regards,
    zafar

    please check the below links.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/b441a9a1b011d3a82d0000e82a3c24/content.htm\
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d256344af11d182b40000e829fbfe/content.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm
    please check the above links may get some idea.
    Regards,

  • PR after MRP run

    Hi,
    After MRP run we want the valuation type system should pick up automatic in generated Purchase requisition. Can you please confirm how it is possible ?

    Hi Sun Riser,
    If purchase requisitions for materials subject to split valuation are generated within materials planning (Transactions MD01, MD02, MD03), the system does not supply a default value for the valuation type. The header record is generally used (without valuation type). This is standard behaviour please look at note  15297 Materials planning: No valuation type defaulted. Workaround is when you enter the valuation type during conversion PReq -> purchase order, an account determination is performed with the corresponding valuation type automatically
    Regards,
    R.Brahmankar

  • Defalut Document Type assignment for PR after MRP RUN

    Hi,
    I want to know we have 6 types  of different document types , i want to know after MRP RUN i want to assign a document type how to do setting for this  like for each plant i want to assign diffrent document  type after MRP RUN, also if we have not made  which will be the defalut doc. type after MRP RUN for PR
    regards,
      zafar

    Dear Zafar,
    Go to
    Spro-Materials Management-Consumption-Based Planning-Planning-Procurement proposals-Define External Procurement-MRP Group-Under Doc Type SPO you can maintain your default doc types in front of your plant.
    Now run MRP.
    It will work.
    Regards
    Utsav

Maybe you are looking for

  • Dual boot windows 7+archlinux on separate disks; grub errors. [solved]

    Hello, I am very excited to try arch linux, but am having trouble with the installation.  My situation is as follows:  I have 3 hard drives: windows 7 lives on sda and sdb.  I am installing arch on sdc, which is 500GB. I partitioned the hard drive as

  • Ipod not recognised by car cd player

    I just installed a brand new Alpine CDA-105 and have the high speed connection cable hooked up to it. When I hook the iPod up to it, the stereo doesnt recognise it and the iPod doesnt seem to think it is connected. I have tried to hook up my 5th gen

  • How to set up e-mail account on IPad

    Just got my IPad, how do I set up my e-mail account, so I can send & get mail?

  • Flash causing hangs in safari 4

    Hi, I've been having issues with safari 4 intermittently beachballing, and I've come to notice it's generally occurring as a flash ad/video is loading. The system log also reads... 21/09/2009 20:24:11 com.apple.WebKit.PluginAgent[270] Debugger() was

  • MacBook Pro Won't Boot Beyond Grey Apple Screen - Mystery Partition Found

    My MacBook Pro, which suffers from appalling overheating (94 degrees C in each core last week) won't boot beyond the grey apple splash screen. I booted from a Developer's disk and ran Repair Disk/Disk Permissions. Both verified AND said the repairs f