GR in case of MTO scenario

Hello All
        In case of MTO (Planning strategy 20) when we run the MRP we have  planned order agianst sales order & we convert planned order to Production order, I want to know that in case of MTO if we look at the GR tab page of the production order the GR Non-Valuated checkbox is ticked, & if we see the help of the same field it says:
Goods Receipt, Non-Valuated
Specifies that the goods receipt for this item is not to be valuated.
Dependencies
This indicator is only relevant to production orders, projects and and configurable materials with account assignment to a sales order.
      I want to know why this checkbox is checked in case of MTO.
      I want that this shall not be checkmarked in case of MTO scenario I want that if GR is done against a production order which is of MTO scenario, then GR shall be of valuated.  Kindly suggest what all settings have to be done for the same.
Regards,
J K Tharwani

Thanks R Brahmankar for your valuable inputs,
         I did some changes in customizing under CO node of which the path is as under:
         SPRO>Controlling>Product cost controlling>Product cost by Sales Order>Control of Sales Order related Production-->Check requirement class.
        I made the changes in the following fields:
   Field                      Default Value               Changes
   Valuation               Blank                           M (Separate valuation with ref. to sales document/project)
   Settlement Profile   SD1                            PP01
  Result analysis key  000004                       Blank
      After doing the above changes I created a sales order & did the MRP run I converted the planned order to production order & then I got under GR tab page of production order the check box  for "GR Non-valuated" as unckecked. I want to cross check if the changes I have made are OK as per the requirement. Waiting for your valuable inputs.
Regards,
J K Tharwani

Similar Messages

  • No Accounting Document generated for goods issue in case of MTO scenario

    Hi all,
    I have MTO scenario & the industry is trading. So I have all trading goods. In SPRO - Sales & Distribution - Availability Check and Transfer of Requirements - Transfer of Requirements - Determination Of Requirement Types Using Transaction I have determined requirement type as KE.
    In material master I have used strategy group as 20 for Make to order scenario. In the settings "Determination Of Requirement Types Using Transaction" I have determined the requirement type as "KE".
    The requirement type "KE" determines a requirement class "040 - MkToOrdNoValW/o cons". Here the account assignment category is "E-Ind. cust. w. KD-CO".
    Now I created a sales order, the system determined the requirement type as "KE". I saved the sales order, assigned the stock to the sales order  & created a delivery.
    I did the PGI also. But when I check in the document flow, for the material document the system has not generated any FI document where we see the accounting document for the "cost of goods sold" & "inventory" G/L accounts. The system gives a message "Material document 4900000023 does not include an accounting document".
    Note:
    1. When I create the sales order with normal MTS scenario, the system creates an accounting document for the material document at the time of goods issue.
    2. The valuation class in the material is 3100 for trading goods.
    3. The following settings have been made in OBYC.
    for GBB, the G/L accounts have been assigned for general modifier "BSA", "VAX", "VAY" & "VKA".
    Please suggest me as to where i am missing any settings.
    With best regards,
    Niyaz Sayyed.

    Dear Niyaz Sayyed
    You need to check in the following areas:-
    -  check whether the material is defined as non-valuated stock
    -  go to OME9, select your Account Assignment and see whether you have checked the box "GR non-valuated".   It should not  have been checked
    thanks
    G. Lakshmipathi

  • How can we assign a different scope of planning in MTO scenario?

    Hi,
    We are using MTO scenario. In this case, during sales order creation checking control AE is getting triggered. We want to use a different scenario during rescheduling transaction. But as per my analysis, V_V2 is also calling the same AE checking control eventhough we assigned a different checking control for Back order processing.
    In this case, can we assign a different checking control (scope of check) for back order processing?
    Regards.

    Let me explain my requirement here....
    This is a kind of trading or sub-contracting. Initially we will give the forecast to vendor...but Vendor will start the finished product production only after getting the confirmed order from us. Hence we thought to use strategy 50. So we will create a PO to Vendor only after getting a confirmed sales order from customer.
    But in strategy 50 ATP confirmation is based on PIR. Hence we created a new requirement class (copy of 45 with ATP active). So in this new strategy ATP is against actual receipts instead of PIRs.
    But sometimes Vendor may not be able to supply as per lead-time...and he may postpone the delivery date. In this case we are getting exception message 10 for the PO...even though PO is specific to a sales order. Still rescheduling job (V_V2) is not populating the new confirmation date as it is referring to the TRLT.
    Hence we want to use ATP based on TRLT during sales order creation. And during rescheduling we want to use a different scope of check ('without TRLT' and with 'No storage location check'). Hence we created a new checking rule for rescheduling and this we assigned for that specific plant.
    As per my observation, rescheduling job is not picking the scope of check that is assigned for rescheduling....it is calling the same checking rule AE during rescheduling also.
    So my question here is... can we call a different scope of check during rescheduling run while using make to order strategy?
    Regards.

  • Costing in case of ETO Scenario

    Hi Experts,
    We have ETO scenario. There is sales order with reference to project  and absed on that production for In House Produced materials ( FG, HALB) and procurement for  some HALB, Raw Material will happen.PS<  moduel alongwith SD and PP are involevd in scenaio along with FICO and MM.
    I am new to this area. I was looking for details of Costing of the project. How the production cost will be assigned to project?
    How the execution of production happens..I mean whether we create production order or is there something else coming in picture in case of ETO ( Strategy -21) .
    Thanks in advance.

    Hi,
    Presuming that your production is client order based. You have to use Sale order Costing and make sale order as cost object in the current scenario. As the Pipes are in different dimensions even Variant configuration will come into picture from Sales and Production Planning module.
    When VC is used, there is a concept of Super BOM and Super routing in which all the relevant material and process required will be listed.
    Specific coding will be written and assigned to the Master data in PP. When a specific requirement Sale order is create the required parameters are written on the Sale order VC screen.
    In nut shell, from costing perspective you have to go with MTO scenario with Sale order costing. Then costing differs from Sale order to Sale order wherein there is not SCE updation to the FG material code.
    Hope this trows some light on your doubts.
    Thanks & Regards,
    Ravi Kumar

  • How to Copy Cost Estimate from Quotation to Sales Order in MTO Scenario

    Hi,
    We are working on a MTO scenario- Sales order Costing with Valuated Stock.
    And our case we are creating the Cost Estimate at the time of Quotation using PP qty structure. Now we wan to transfer the cost estimate to Sales Order as we don't want to recost the sales order.
    Currenty it's transferring only the EK01 condition as total planned costs in Sales order but we want to see the itemization also.
    Please suggest is there any way to transfer this cost estimate with itemization from Quotation to Sales Order.
    Regards
    venkat

    Hi
    As far as I know the CO esimate does not get copied from Quotation to Sales Order
    You need to recost the SO again.. If your Qty Structure has not changed between Quotation to SO and your valuation variant is also the same - it would give the same result
    br, Ajay M

  • Change in Sales Order Qty in a MTO scenario

    Hi,
    We had confirmed 5 Qty for the Production Order created with reference to Sales ORder(MTO scenario), now after confirmation of 5 qty, sales order qty is reduced to 3., then in this situation, what we need to do for the already confirmed extra Quantity 2 for this sales order. I think we need to cancel the confirmation for the extra qty 2?. Please clarify and explain what we need to do this for this extra Qty 2 in detail.
    Case 2) If the Sales Order qty is changed to 7, then we will be creating a new Production Order for this new quantity 2 with reference to the same sales order.  Am i correct?.IF wrong, please suggest how should we balance the extra requirement of 2 EA.
    Thanks in advance.

    Is your query being posted even before you actually tried the 2 cases which you refer to in your system?
    If so, then first do the simulation in your sandbox, check how system behaves when you do that. Also check by clicking on ATP check for the material within SO.
    Once you do the above your query will be self answered, if you still face any issue then revert with the specific details.

  • Steps for execution of valuated and unvaluated for MTO scenario

    Hi,
    Can any one provide the steps for execution of valuated and unvaluated for MTO scenario.
    regards,
    RAM

    Hi,
    Please find below the details about Valuated and non-valuated Sale Order scenarios:
    SAP Scenario 1 - Valuated Sale Order Stock u2013 with Sale Order Controlling u2013 (MTO, ATO and ETO with VC)
    1     Enquiry     
    2     Opportunity     
    3     Quotation (Creation and Approval). In case of ETO u2013 BPO is created and updated in quotation (condition type)     
    4     Creation of Sale Order     
    5     MRP Run u2013 Creation of Planned Order u2013 Creation of Production Order and Purchase Order     
    6     External Procurement u2013 Goods Receipt     ROH Inventory A/c Dr (BS)
         To GR/IR A/c Cr (P&L)
    7     Material Consumption to Production Order     In FI:
    ROH con. A/c Dr (P&L)
        To ROH Inventory A/c Cr (BS)
    Same is the case with HALB
    In CO:
    Cost of Material is debited to Production Order
    8     Activity Consumption to Production Order     No FI Posting
    In CO:
    Production Order is debited and cost center is credited with activity cost
    9     Goods Receipt from Production Order     FG Inventory A/c Dr (BS)
       To COGM A/c Cr (P&L)
    10     Delivery to customer     In-Transit A/c   Dr. (BS)
       To FG Inventory A/c Cr (BS)
    11     Invoicing to customer     In FI:
    Customer A/c Dr (BS)
       To Revenue A/c Cr (P&L)
    COGS A/c   Dr (P&L)
        To In-Transit A/c Cr (BS)
    In CO:
    COGS and Revenue are posted to COPA
         Period end closing u2013 Production Order     
    12     Revaluation of activity prices     Production Order and Cost Center will be debited or credited as the case may be
    13     Calculation of WIP     In FI:
    WIP A/c  Dr. (BS)
      To Change in WIP A/c Cr (P&L)
    If the Order is completed:
    In FI:
    Change in WIP A/c   Dr(P&L)
       To WIP A/c Cr (BS)
    14     Calculation of Variances     Variances are Calculated on the Production Order. No FI or CO entries
    15     Settlement to Sale Order     Production Order and Sales Order will get debited/credited depending on whether they are positive or negative variances
    Period end closing u2013 Sale Order
    16     Result analysis at Sale Order     Result Analysis run will identify the status of the sale order and will enable the postings to COPA at the time of settlement
    17     Settlement of Sale Order     
    In FI:
    Variances A/c Dr (P&L)
      To COGS Account Cr (P&L)
    (It would be otherwise if variances are positive)
    In CO:     
    COGS, Revenue and Variances are settled to COPA
    SAP Scenario 2 u2013 Non-valuated Sale Order Stock u2013 with Sale Order Controlling
    Process Step     Business Process Flow     Value Flow u2013 FI/CO
    1     Enquiry     
    2     Opportunity     
    3     Quotation (Creation and Approval)     
    4     Creation of Sale Order     
    5     MRP Run u2013 Creation of Planned Order u2013 Creation of Production Order and Purchase Order     
    6     External Procurement u2013 Goods Receipt     In FI:
    Consumption A/c   Dr (P&L)
       To GR/IR A/c  Cr (P&L)
    In CO:
    Material costs will directly get posted to Sale Order
    7     Material Consumption to Production Order     Not applicable
    8     Activity Consumption to Production Order     In FI:
    No Entry
    In CO:
    Activity Costs are posted to Production Order
    9     Goods Receipt from Production Order     Only Material Document for movement of goods will be there.  The stock is neither valuated in CO nor in FI
    10     Delivery to customer     Just goods movement from sale order stock to customer. No value postings in FI and CO
    11     Invoicing to customer     In FI:
    Customer A/c Dr (BS)
       To Revenue Cr (P&L)
    In CO:
    COGS and Revenue get posted to Sale Order
         Period end closing u2013 Production Order
    12     Revaluation of activity prices     Prodn Order and Cost Center will be debited or credited as the case may be
    13     Calculation of WIP     No WIP
    14     Calculation of Variances     No Variances
    15     Settlement of costs to Sale Order     All the costs accumulated in Production Order gets collected to Sale Order
    16     Settlement of Variances     No Variances in Production Order
         Period end closing u2013 Sale Order     
    17     Result analysis at Sale Order     In FI
    WIP A/c  Dr. (BS)
      To Change in WIP A/c Cr (P&L)
    If the Order is completed:
    Change in WIP A/c   Dr (P&L)
       To WIP A/c Cr (BS)
    No CO postings will happen
    18     Settlement of Sale Order     COGS, Revenue and other direct sale order related values will get posed to PA.
    Best Regards
    Surya

  • Subcontracting in MTO scenario.

    Hi,
    We have an MTO sales order against which we are raising a subcontracting PO. At the time of goods receipt, movement type 101 'E' and 543 'O' has triggered. 3 controlling entries have taken place:-
    1. Cost for Goods issue to subcontractor is debited to PSG. (543 'O')
    2. Credit for goods receipt from subcontractor is credited to SDI.  (101 'E')
    3. Service charge for subcontractor is debited to SDI.
    The above entry has happened only once and is leading to excess credit on the sales order.
    When we replicated the case in test environment, we found that all the costs have gone to PSG (as per OKB9). The movement types are the same as before.
    We replicated a case where we triggered 543 'E' instead of 'O' and the costs are still going to PSG for all the entries. This was done by changing the 'individual/collective' indicator in material master. I believe this is the recommended SAP setting for subcontracting in MTO scenario as per following link.
    Subcontracting for Sales Order Stock and Project Stock - Managing Special Stocks (MM-IM) - SAP Library
    Can anyone explain when does system overrule OKB9 and take sales order as cost object?
    What can be the probable reason that system is behaving differently for only one occassion?
    Is there any other indicator in material master that I should look for?
    Can I look at OMJJ for possible causes?
    I know this has been asked several times on the forums before but I have not been able to explain above situation. So thanks in advance.

    OKB9 is only functional in the case where a "cost object" has not been assigned to a P&L transactions. That's why it is called "Default Account assignment". In the Case of your MTO, the sales order is really considered as the cost object and hence would take precedence over other default...once a cost object is determined, any further assignment of a cost collecting object becomes statistical depending on the type of cost objects. Basically cost objects have precedencies: I believe Sales order, internal orders, Cost center, etc in that order. Meaning, when 2 are assigned, the one in the lower order become statistical. In any of these cases, OKB9 takes a back seat. OKB9 only comes to play when the internally generated accounting entries will result in no cost object assignment, then SAP looks to see if you have a reference maintained in OKB9.
    Basically, for your MTO, the sales order (an maybe the cost center, etc assigned the to sales order) becomes the cost holder. OKB9 will not feature.
    OMJJ will help you simulate the goods movement and see how the accounts are derived/cost assigned. If OKB9 features, you will also see it referenced. But I don't think it will, unless your goods movement results in an accounting entries that internally does not reference the sales order, then OKB9 kicks in.

  • CTM Order Selection MTO scenario

    Hi,
    I  have cfreated a Sales Order in ECC with Requirement Strategy as Made To Order and CIFed the order to APO.
    The order is getting CIFed and is reflecting in APO.
    The issue is that when I try to do Demand Simulation using CTM the order is not getting recognised.
    Is their some setting that needs to be done in case Sales Order for MTO scenario.
    Please help me in this regards.
    Thanks,
    Sanjog

    Hi Sanjog,
    can you see the sales order in APO (/sapapo/rrp3).
    please maintain in the demand prioritization profile the category for this sales order and then try simulating the demands.
    let me know if it works.
    Thanks
    Binod

  • Credit Note in case of return scenario

    Hi,
    In case of return scenario, credit note is issued with reference to return order or return delivery?
    I am unable to see the copy control setting in IDES for RE(Return Order) to G2(Credit Memo).
    Could any one please let me know the setting for the same (Header and item).
    Regards
    Suman

    Hi Suman,
                 As for the standard in the IDES,the Credit memo will be created with reference to the Creditmemeo request because of that RE to G2 copy control setting may not avail.
    You copy the settings same as Creditmemo request(CR) to Credit memo (G2), You just change the name CR in to RE it will work.
    -->Other wise you can use Credit for returns RE document type to create credit memo for return order RE for this copy control avail in the IDES t.code VTFA.
    I hope it will help you
    Regards,
    Murali.
    Edited by: Murali Mohan.T on Feb 27, 2008 11:07 AM

  • Re: Error while making a Process order in MTO scenario

    Hi All,
    I am having a secnario, where I am using MTO scenario. I want that the sales order should trigger the process order.The components in the BOM for the FG material .
    1. Raw material: procured from outside: Stock & value relevent.
    2. This one is non valuated one :procured from outside: Stock &  Non-value relevent.
    Now when I create a sales order, I can see a plan order in the MD04 scree for this FG . But on drilling down this plan order I can only create the PR for the 1st component only ,for the second component I cant create anything.
    The second item should be non valuated & stock relevent.
    Please help me in this regards,
    Vivek

    I have taken help from some other threads to resolve this issue.

  • Error While doing settlement for Sale Order in MTO scenario

    Hi,
    In MTO Scenario - when i try to settle Sales Order i am getting the below error. Even i have maintained the settlement cost element for PSG in allocation structure A1.
    Kindly help me
    Define a settlement cost element for receiver type PSG
    Message no. KD506
    Diagnosis
    In allocation structure A1 (controlling area BP01), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type PSG.
    Procedure
    Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure A1.
    Thanks
    Kishore

    Hi
    Please check your allocation structure , it looks that settlement cost element that you have assigned in the allocation strcuture is not having correct cost element category.
    Go to Allocation structure configuration (OKO6) and check your allocation structure A1.
    check settlement cost elements is it by cost element or you have assigned separate cost element for settlement.
    if you wants to settle with same cost element select By cost element.
    if you wants to settle with different cost element create a cost element and assign settlement cost element.
    http://help.sap.com/saphelp_di46c2/helpdata/EN/9d/1f4b6e5733d1118b3f0060b03ca329/frameset.htm
    hope this helps you.
    Regards

  • Block production order creation in MTO scenario when sales order is blocked

    Hello Experts,
    We are using the MTO scenario and creating production orders with refernce to sales order using CO08.
    The requirement is to not allow the creation of production order when the sales order has a block. It can be an overall block or a credit block.
    Right now the systme allows me to create the production order with refernce to the sales order even when the sales order is blocked.
    Is there any way by which this check can be activated.
    Thanks
    Ritesh

    Hi!,
    Please try follow:
    Go to path IMG > Plant Maintenance and Customer Service > Master Data in Plant Maintenance and Customer Service > Technical Objects > Serial Number Management > Define Serial Number Profiles. There enter "2" in Stkck column for your serial profile.
    Regards,
    Uday

  • In MTO   scenario i want to have some materials with out account assignment

    Hi,
        In MTO scenario i want to have some components in my BOM  to not to get planned with respect to sales order stock / account assignment of specifice sales order( say "C" class items). if i use Consumption based planning" VB" for those
    materials it works with manual reorder point planning.but i cannot estimate my correct reorder point for that material.because it is not constant requirement .It varies basing on customer sales order for that period.
       My question is how to plan  these components in MTO scenario with out having idea of correct manual reorder point for those materials.
    thanks in advance
    regards
    madan

    Madan,
    Automatic Reorder Point Planning
    In automatic reorder point planning, both the reorder level and the safety stock level are determined by the integrated forecasting program.
    The system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified by the MRP controller, and the material's replenishment lead time into account, and transfers them to the material master.
    Since the forecast is carried out at regular intervals, the reorder level and the safety stock level are continually adapted to the current consumption and delivery situation. This means that a contribution is made towards keeping stock levels low.
    So you need to maintain the forecast view for the material. The forecast values comes from consumption data. If the system in place for some time then consuption data will be automatically by the system based on the material issues. I am not sure if you can enter the consumption manually.
    Regards
    Ram

  • For  MTO scenario,multi level bom is not working sap afs pp

    Hi Experts,
                  We are implementing MTO scenario for our client. I have maintained  strategy group for FERT is 40 and strategy group for HALB and ROH are 20.
                   For single level BOM , requirements is not getting generates properly.
                  I would like to know What are all the settings is required to create AFS BOM.(single and multi level)
                   Please suggest me.
    Thanks & Regards,
    Deepika.

    Hello Deepika,
    As we know AFS materials are planned at SKU level (Grid and stock categories)  you can use AFS MRP (/N/AFS/MD02) only.
    Please refer OSS note Note 981747 - FAQ - AFS Production Planning
    Question 5 Made-To-Order Planning -Multi-Level (MD50) does not work for AFS Materials and Sales Orders containing AFS materials.
    Answer: Made to Order Multi level planning functionality was never enhanced for AFS and hence transaction MD50 is not supported.
    Steps are as,
    1. Create a MTO/PTO sales order for an AFS material.
    2. Run AFS MRP using transaction code /AFS/MD02.
    3. Convert the planned order to production order.
    Best Regards,
    R.Brahmankar

Maybe you are looking for

  • Iphone 6 videos can't be viewed on ipad photostream

    I have an iPhone 6 running iOS8.1.2. I have an iPad4 running iOS8.1.3. I extracted my iPhone 6 video to my PC and tried to sync it into iPad4. However I can't seem to find the video in the iPad 4 photostream. Do anyone have a similar problem?

  • Slow Access to NSS326 by Mac

    We have two brand new iMac with Mac OS X (10.6.8). They have 4GB and 8GB RAM for each. When they access to  the folders on the NSS3226, finder responds very slowly. Displaying files in a folder, expecially, if it has a lot of photos, takes very long.

  • Using MXO2 for monitoring fcp

    I'm looking to monitor HD out of a MacPro with one video card, and wondering if the MXO2 mini will allow me to have 2 computer monitors hooked up to my video card, and export HDMI to a LCD/TV (3 screens). From what I'm seeing, it looks like I'm going

  • What is this agent in remote server

    Hello I am really not able to understand when experts are talking 1. "you need to create agent in remote server" What I understand: creating standalone agent in remote means, we need to install ODI there 1st. then we will configure the standalone age

  • Rooms: Find out in which Room a User is?

    Hello Friends, I want to extend the Rooms by contructing a seperate Component and iView. (So I don't have to manipulate the standard application) Does anyone know how I can find out, which Room the actually entered one is? Means: The User Navigates t