GR qty less than the SL qty.

Hi Experts,
I have 2 schedule lines scheduled for earlier dates.
say, SL-1 -> 100, SL-2 -> 200
If i do a GR (MIGO) against the SA today then it should prompt me the qty as 300.
But the system is prompting a lesser qty (say 50). Why??
What all do i need to check to resolve this...
This is very urgent.. please advise...
Thanks,
Manju

Hi,
Since the SL dates are in the past, if i do a GR at the present date then it must allow me to receive the entire qty (i.e. 300 in this case).
But, it is not allowing me to receive qty more than what it has proposed.
I need to receive the entire qty that is due.
Please advise.
Thanks,
Manju

Similar Messages

  • Header qty is less than the operation qty.

    To certain production order header qty is less than the operation qty. Please advise me.

    Dear,
    Base Quantity - Quantity of the material to be produced to which the standard values of the operation refer.
    Operation Quantity - Quantity planned for this operation.
    Base quantity and operation quantity may not always be the same, if we have partial lots delivered during the sequence of operations, the operation quantity will be equal to the lot delivered during the operation.
    Base quantity is dependent on the BOM, where it signifies the total quantity of output after using the components of certain quantity.
    In routing, you neeed maintained there operation quantity, and unit of measure of operation quantity accordingly with base quantity unit of measure.
    Check up the Processing formula used in the Scheduling tab of Work center (Use SAP002 = Machine * Oprn qty / Base qty / No. of splits)
    Hope clear to you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Oct 7, 2008 11:37 AM

  • Service PR qty reduced than the PO qty

    Hi,
    For material PR, if the qty is reduced than the PO qty we can activate
    06 648-Requisition quantity already ordered in full (see follow-on docs.)
    but what is the message no for service PR line item control.(if the service PR qty is reduced than the Service PO qty)- for service line item.
    we are not using the service master for for creation of service PR/PO

    dear indranil,
    thank you.
    06 076 is applicable for material PO, it is not working for service PO.
    as header line qty and not the service line qty
    we have already checked the same.

  • Invoice qty greater than the PO qty

    Hi All,
    I have created material  PO with 100 qty Value 5000 and freight cost 1000 rs for the same Qty.
    Issue: at the time Freight Invoicing with PO/bill of landing
    Material: GR & IR Done for 100 qty -- No issue
    Freight: when am doing invoice (MIRO) i have given Purchase Order no and paid the freight rs 1000 for whole 100 qty
    Issue: If i do invoice (MIRO) by for the same PO and given bill of landing, system still proposing some qty 40 Qty and proposing some cost.. and able to save .
    but it should not propose the Qty... Plz let me know how to restrict it... In case freight Invoice
    Thanks

    Hi,
    not some qty... if i select the Bill of loading in MIRO, then system is proposing the whole qty for the particular item of PO.
    PO:123  100 qty  Fright cost 10  value 10000  Bill of Loafing:XYZ
    MIRO-Delivery plan: Done With PO whole Qty 100  freight cost 10rs value=1000 rs
    If i select :Bill of loading XYZ (Same PO and same item).. system is proposing same Qty 100 and value 10000..
    Thanks

  • Qty received less than Purchase UoM Qty

    Forum,
    Anyone ever run into an issue when a Vendor sends a quantity of a product that is less than the purchase UoM Quantity?
    Example:
    Purchase UoM = Case
    Qty per Unit = 720
    We created a Po for Qty = 1 (720 units)
    The Vendor only shipped 300 units.
    How can the users easily create a GRPO for only 300 units.
    Tried setting Qty to 300/720 = .416667
    But this causes a decimal issue and an issue with having partial quantities in the system.
    Anyone experience this before and have a solution?
    Thanks in advance,
    Brad Windecker

    Brad,
    One thing you could do....
    On the PO..Enable Base Units column using the Form Settings.....The Base Units column is a drop down..change it to Yes
    This will ignore the UoM setting in the Item Master and changes your PO quantity setting to eaches (1) and price for 1 quantity.
    Now change the quantity to 300.  Duplicate the row and change the quantity of the second row to 420.
    This way you can receive the first row when copying to GRPO while keeping the PO balance quantity of 420 intact
    Suda

  • Message-4F181 :Credit Quantity less than Excise invoice Qty

    HI,
    I have done migo with part 1 entery,WHLE DOING J1IEX .I AM GETTING A WARNNING MESSAGE 4F181 :Credit Quantity less than Excise invoice Qty
    Please suggest
    Regards
    SAM

    Hii,
    Did u reduce the Quantity of the Excise Invoice??
    Regards,
    Kumar

  • Issud  qty is  greter  than  the   Reservation  qty

    Dears,
    I   Have  creted the   Resevation  100 qty  for  cost center 1.
    While  i  am    issuing  the   qty    to   cost  center system  is  allowing  more qty  than  the  reserved   qty100.
    Even  if  i  given  the  200  qty  system  is  posting the  Document .
    How  Avoid  this  Posting  and  where  i  ahve   to    cofigure  the    System   setting  please  Guide   Me.
    If  i  am   issuing the   More  qty  than  the   Reserved  qty  systemm  should  give  the   Error  message.
    Like issued qty  is  more  than  the   Reserved    qty .

    This can be controlled by setting the messages to Error in the Relevant application area.
    Go to SPRO-MM-Inv Mgmt & Phy Inv-Define attributes for System messages / use trxn code OMCQ and find the Relevant message number and set to Error and Save.
    Also Check in SPRO-MM-Purchasing-Environment-Define attributes for System messages / use trxn code OMC0 (trxn code may not work) and find the Relevant message number and set to Error and Save.
    Eg : 06 078 Target quantity exceeded by  & & etc

  • Increased Qty in sales order than the Billed qty..  urgent

    Hi folks,
    When I am creating a return sales doc. with reference to a Billing doc,
    everything is getting copied on to the return sales doc.
    The Qty of the item is also getting copied on to the sales doc.
    But when i increase the qty of the item , it is giving me a warning message  saying " Qty is more than the billed qty." and thus allowing me to take it.
    The client want that this should be an error message and hence shouldnot allowed to take the increased qty.
    Can anyone tell how to make it an error message.
    thanx
    sourav

    Hi Sourav,
                  Check copy control settings in the transaction VTAF.
    In that you go to item level copy control check the field Pos./neg.quantity whether this field set as '-' or not.
    If not set enter - (Minus) then try
    If already enter you need to go for the User exits to cahnge the warning message to error message.
    I hope it will help you
    Regards,
    Murali.

  • Excise invoice quantity cannot be less than the quantity received

    Hi,
    I have done MIGO with part 1 entry but while doing J1IEX, I am getting an error message 4F109 : Excise invoice quantity cannot be less than the quantity received.
    Please note that we have done MIGO with 5000 qty. and doing J1IEX with short 3000 qty.
    Regards.

    Hi,
    For this case of "Part I" selected during GR, you need to create Excise invoice thro J1IEX ->  Capture Excise Invoice -> Good receipt (use the material document number), which will complete the part II posting. Then you can proceed with MIRO.
    With regards,
    Jeeva.

  • Create TO for a quantity less than the delivery quantity

    If we have created an inbound delivery in MB1C, 561 movement to post an initial entry of stocks, and then packed the HU in Vl32N. Now, we want to create a TO for a quantity less than the delivery quantity.
    In LT03 I cant see any option to change the TO quantity. How can we actually change the TO quantity to be less than the Delivery quantity.
    Thanks
    -Mike

    Mike,
    I dont think that's going to be possible.  The TO gets data from the del qty which is in your embedded HU since you have packed the qty in the del in the HU,
    so if you are trying to create a TO with less qty means that you want a qty less that the HU in the del and this is not possible.
    Alternatively : 
    1) You can receive it in your warehouse.
    2) Move it in a re-packaging area
    3) break the HU and re-create a new HU.
    4) Pack the desired qty
    5) Move the 2 HU's back to their desired bins.
    Hope this helps and works!
    thanks'

  • Stop new planned order when process order GR qty less then sales order qty

    Hi All,
    How should SAP be configured so that when a process order is GRu2019ed, the sales order requirement is fulfilled regardless of the quantity difference between the sales order and process order?
    The system behavior we are currently experiencing is MRP will generate another planned order for the fixed lot size if the GRu2019ed quantity is less than the sales order quantity.
    Additional background information:
                    Make to order scenario
                    Process industries
                    Batch control
                    Warehouse management
                    Fixed lot size
    Any comments or suggestion are welcome.
    Thanks.

    Brahmaji,
    Thanks for the reply.
    I agree that changing from FX to EX will produce a planned order for the quantity difference (SO qty less the GR qty).  So this would be an improvement to our present situation, but not quite what we are looking for.
    The system behavior we want is MRP to ignore the requirement for the difference, in other words, when the GR is done for the entire batch quantity, we won't be producing any addition product.  The sales order would be considered complete.

  • The amount of down payment must be less than the invoice amount

    Hi all,
    Our customers are using SAP 2007-PL15 and SAP 2007-PL41.
    When we want to create a down payment for a sales order, and we want to pay the entire amount of the sales order, including tax, we have to put an amount inthe TOTAL field of the Down Payment window since by default, the down payment amount is the total of the invoice before applying tax.  The DPM is
    higher than 100% (strange but I think it's normal since the down payment is not planned to take the tax in consideration).
    Then, we create an incoming payment for this down payment. It's ok.
    Then, we create an invoice based on the sales order we have paid with the down payment. It's impossible to use the down payment for the invoice... why that ? We receive the error 'The amount of down payment must be less than the invoice amount'. This causes big headaches to our customers !!
    Could you explain us what to do please ?
    thanks,
    Luce

    I'm very sorry, I have a similar question in dealing with AP Down Payment Request Linked to AP Invoice,  my case like this:
    1. I created 3 AP DPRs,their amount are each 100,000 RMB(for example, their document number are 10,11,12). then do the outgoing payment fully paided.
    2. I created a AP Invoice with the amount 150,000 RMB(for example, this AR Invoice document number is 5). I use the buttom"Total Down Payment",and selecet AP DRP No.10 and 11. When I click the buttom"Add",an error shows:
    The amount of down payment must be less than the invoice amount
    and I don't know how to continue.....
    Many Thanks
    Kam
    (PS:My English is poor,forgive me please. Shall I Speak in Chinese? then I can describe this question more clearly.)

  • Messages in Xi is less than the messages in R/3 server after processing.

    Hi Experts
    I have a scenario file - Idoc.
    XI picks up the file from FTP process it and sends to the R/3 server.
    Now I have a problem is when I check the Data in XI using IDX5 or SXMB_MONI the no of messages in xi is less than the messages in R/3 server.
    I am checking the data of the last day like 8th May from 00:00:00 to 23:59:59 in both the cases.
    In R/3 I check using BD87 t code.
    Thanx

    Hi Divyesh
    Thanks for your prompt reply.
    Ya I am also doing exactly the same . But the problem is that I am checking for yesterday datas.
    In idx5 I get total of 2625 messages for  orders.
    When I check the same on BD87 i get 2636 messages with status 53 & 1 message with status 51.
    Difference is of 11.
    Now the question in how is it possible that it is picking 2625 data from FTP and after processing its sending 2637 data on R/3 server.
    Thanx

  • I am debating between the 13in 2.9ghz mac book pro or the 13in 2.5 ghz mac book pro with all the same specs bbut for me i am trying to see which one for the money is better becuase the 2.5 will run me 100-200 dollars less than the other

    I am debating between the 13in 2.9ghz mac book pro or the 13in 2.5 ghz mac book pro with all the same specs bbut for me i am trying to see which one for the money is better becuase the 2.5 will run me 100-200 dollars less than the other

    Only you can make that determination. All things being equal the 2.5 GHz model is slower.

  • PO is getting released even if the total amount is less than the last PO am

    Purchase Order is getting released even if the total amount is less than the last PO amount. The release strategy is only working for the first Purchase Order and if the PO amount is greater than the last PO amount.
    Please let me know how to correct this scenario (release strategy).
    Regards,
    Prishu

    Hi,
    Release strategy has nothing do with the previous PO amount. May be, Co-incidently the amount in previous PO which you are referring and the characteristics value maintained in the release strategy is same.
    1) Please go in release strategy by the path mentioned below
    IMG u2013 Material Management u2013 Purchasing u2013 Purchase Requisition u2013 Release Procedure u2013 Procedure with Classification u2013 Set Up Procedure with Classification
    2) Then go to release strategy. Here the total available release strategies would be displayed. Double click the strategy which is getting reflected in the PO you want and go the classifiction tab. There you will get the PO value. Based on this characteristic value the respective release streategy gets refelected.
    I hope this clarifies.
    Regards
    sachin