GR slip printing for Byproducts during Prodn order confirmation
Hi,
We are in 3.1I version and my problem is to a print a GR slip similar to the one I print for finished product. I could not print the GR slip for Byproduct and I do not see how the standard program works in this case or any customization is needed specifically for this.
Any suggestions not limiting to the version mentioned is welcome.
Thanks & Regards
Anji
Hi Stuti<
Refer the below links it will solve the issue.
[Batch Determination - help|http://help.sap.com/saphelp_45b/helpdata/en/25/283cb44f7811d18a150000e816ae6e/frameset.htm]
[SDN Thread-1|Re: Batch Determination issue -reg]
[SDN Thread-2|Batch Determination;
Regards,
Shyamal
Similar Messages
-
Serial Nos entry for FG during Production order confirmation in CO11N
Hi all,
Can anybody explain me how can we confirm the assemblies serial no wise for FG in CO11N. this is a stringent requirement for my client.
Withthis they can track which assembly n upto which operation was that confirmed.
Thank youHi,
In OIS2 define a profile and assign procedure PPAU and configure PPAU as
usage = 03,
EQ re = 01.
Assign this profile to assembly as well as product, that profile u have to assign it in material master work scheduling screen.
Now when you go for confirmation in co11n system will ask you the serial no.
Now you do the confirmation...you can get what you described.
This is a standard Sap functionality.First do confirmation and then do goods receipt in MB31 where you assign serial numbers.
OR.
An other way is go to COIB here u have to enter the the serial number and material then it will display the this serial number generated against which production order.and if ur generating number of serial number against single production order then it will dispaly all serial number.
COIB -
> enter material number and serial number -
> click on list<>tree--
>again enter the serial number and material -
>click on explode it will display the production order and if number of serial numbers are their then it will display at the bottom
Please check it and refer to below link
http://help.sap.com/saphelp_470/helpdata/en/dd/f8c817b3f911d1896e0000e8284931/frameset.htm
Hope will work for you.
Regards,
R.Brahmankar -
Change Work Center during production order confirmation
Dear All,
I must to modeling this situation:
I created an production order. In routing I used an work center A.
After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
Thank you for your answer!
Regards,
Marianonce a Order is released, the Process order detaisl for that order is frozen.
however if you want to do it, change the order status to CRTD after reversing the Movements done.
Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
if the change is long term.
or
Just manually add the new work center and do the processing. if the change is temporary. -
Problem during Process Order Confirmation - COR6N
Dear All,
We are into process industries
Till now we are creating different BOM for each section and different process orders for each BOM.
For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.
Now we have created new BOM for FG - showing all input/output of RM, SFGs. In Recipe, define operation for each section. and assign operation to material. I have attached screenshot of Recipe Operation.
During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.
I have checked in Recipe, control key is ok i.e. Automatic GR, in OPK4 setup is also correct.
We have created new BOM and Recipe. There is no change in other configuration parameter.
Thanks and Regards,
NiravHi Nirav
The automatic goods receipt is defined by the operation/phase control key.
Control key PI03 has the automatic goods receipt setting by defaul.
Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.
For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.
BR
Caetano -
Error during Production Order Confirmation
I get a real wierd error during production Order confirmation. The error message is
"Additional items are not allowed
Message no. ZOAL010"
Can anyone throw some light on this?
Regards
Rajit is not std SAP message.
you can check the user exit for confirmation.
check in transaction code CMOD/SMOD for CONF* -
Serial nos entry during production order confirmation in CO15 - User Exits
Hi all,
Is there any user exit existing for a serial nos screen pop-up during production order confirmation.
Regards,
Sravan Kumar VHi,
For serial numbers at the time of goods receipt, u have to activate sr. no. mgt for that particular finished product. This can be done by assigning sr. no. profile in the material master record of that material in work scheduling view. once this is done , system will automatically prompt for sr. nos at the time of goods receipt. I am not aware about any user exit.
Thanks & Regards,
Vijay Patil -
Equipment as PRT's during Production Order Confirmation
Hi Gurus,
During Production Order confirmation I cannot see whether I have consumed equipments as PRT which are attached to operation.
The operation is showing CNF status as well the Order.
How can I see whether which Equipment was used for each operation since there can be more than one equipment as a PRT's for a single operation.
Regards
NileshI use Production Order confirmation hence saw it in CO14 and checked that PRT's are in PRT REL status..I guess this is what you mean to say right??
Thank you so much for your response.
Regards
Nilesh -
Recording shift during Production order confirmation
Hi All,
Is there a way I can record the shift during production order confirmations using CO15, CO11 or CO11N? I do not see the shift field in the confirmation screen.
Thanks & Regards
Subbu SPDear,
If you don't want to use the standard functionality of SAP or you are on lower version then you can go ahead with enhancement.
CONFPP07 Single Screen Entry: Inclusion of User-Defined Subscreens by using this you can define shift in confirmation.
For more details refer this link,
Re: Shift usage in confimation.
<< Moderator message - Point begging removed
Points unassigned >>
Regards,
R.Brahmankar
Edited by: Rob Burbank on Oct 20, 2010 4:28 PM -
Scraps during PP Order confirmations
Hi Gurus
I need to un-connect movement 261 from Scrap declaration during PP Order confirmation.
This becuase my PP Department produces little plastic components and scraps are only a lettle part of row materials consumed during PP Operation. We want to declare the scrap during confirmation only for statistic purpose, but we don't want that this declaration will post automatically 261 movements. Is it possible ???
Thanks for your help
ClaudioHi TQ
Thanks for your reply.
I'll try to explain better my needs.
We use the backflashing mode for post autopmatically consumptions (M.Type 261) during PP Order confirmations (CO11N).
During the production (we mould little plastic components) we have:
a) Fine Products (Yelds using AFRUD-LMNGA)
b) Bad Products (Scraps using AFRUD-XMNGA)
c) Other residues of plastic material
Now we're confirming a) and b) quantities, and the system post automatically 261 movements for Backflushing consumptions.
We wolud like to post:
a) Fine products (and reletive 261 consumptions)
b) Scraps (WITHOUIT 261 consuptions)
c) Residues + Weight of Scraps (manually at the end of production with MIGO and 261 movement).
Therefore I'd like to declare scraps during confirmation, without posting (automatycally) the correspondent consumptions (261).
There's a way to solve my issue ???
Thank for your help
Claudio -
Restriction during process order confirmation
Hi,
I want one validation during process order confirmation (mile stone) through t code COR6N if resource capacity & shift intervals not maintained ( t code CRC2) then process order should not confirmed & there should be error message. Plz advice how it is possible through customization.
regards,
sps.Dear shukla,
Check with this User Exit,
CONFPI02 Process order confirmation: Customer spec. input checks 1
CONFPI03 Process order conf.: Cust. spec. check after op. selection
CONFPI04 Process order conf.: Customer specific input checks 2
CONFPI05 Process order conf.: Cust. spec. enhancements when saving
If the above is not working then check with this BADI
WORKORDER_CONFIRM at the time of saving,
Regards
S Mangalraj -
Error during Production Order Confirmation mfbf ( backflush)
in my company in sap when i using mfbf for production Order confirmation of tractor then during backflush using mfbf tcode order confirm but in my store dept no metiral cunsume so please regards this problem
with warm regards
pritpal singhDear Pritpal,
sorry dear,today i cant check my inbox immediately. Anyway my mail id is [email protected]
have checked as per my previous post.
regards
pradeep -
Exit/Badi for to Stop PM Order Confirmation using IW41
Hi,
My Requirement is while doing PM Order Confirmation based on Order and Operation in IW41, system needs to check WBS element status.
If WBS element status is closed, It has to stop the Order Confirmation.
Kindly suggest any Exit or Badi for this.
Thanks in advance.
Regards,
Kumarcheck below thread it has all the badis and exits summed up for iw41:
http://scn.sap.com/thread/1121303 -
Output determination failed for a single customer(order confirm thru mail)
Hi,
i n sales order while we save a confirmation mail goes to cutomer.but in case of one customer it failed in output in edit option it is showing yellow signal and email id also maintained in cutomer master .for all other customer its ok.i m new to this could you plz suggest me and provide me the settings .
Reagrds,
DebeshHi Debesh,
Please go to NACE t-code in order to configure output determination, if customer master is ok for output control . in that screen, Firstly you should select V1 output control for order confirmation ,and go in your output condition records for your output control adn create a condition record for your access sequence (ıthink there is no condition record or correct condition records for your specific customer.)
When creating condition records, you should define customer number+ SP- partner function +message trn. medium-5, dispatch time- periodic job, immediate, or etx...
I hope you will solve this proble after output condition records for your spesific customer correctly.
Regards, -
How to create ship to party and sold to party for DC10 during sales order ?
Hello all:
When creating sales order for a material in VA01 with sales Org 1000,
distribution channel 10, division 00
The system does not give me any Ship to Party and Sold to Party with the above combination
How to create ship to party and sold to party with the above combination (Plant 1000,
sales org 1000, distribution channel 10, during creation of a sales order
Ironically, when creating material master for a material with a material type KMAT, plant 1000
sales org 1000, the only distribution channel is populating in the input help (F4) is 10
For which no ship to party neither sold to party is maintained in sales order creation
Thanks in Advance!!Dear Eshwer
It is bcoz, the said account groups (Sold To Party and Ship To Party) are not created in the sales area 1000 / 10 / 00.
To create a customer master, you have to go to XD01, select the Account Group, Company Code and the respective Sales Area and execute. In the Customer Master, you have three tabs, viz.General Data where you have give address details of the customer, then in Control Data, you have to assign the respective Recon Account and in Sales Area Data, you have to maintain the customer's sales related details. Once you give all these datas and save the data, a customer code will be displayed at the bottom.
Now go to VA01, input the sale order type and the sales area and execute.
thanks
G. Lakshmipathi -
GR Doc & GR Slip Printing for materials without master data
We need to print the GR document, GR Slip for materials which doesn't have the master data ( Ex: Materials with long text, material group maintained).
Kindly let me know the requirements for executing this task.For printing GR slips we need to maintain a few fields in the master data for the material. In case of materials without master data, these fields will not be maintained. So, in this case, how to print the GR Slips is the clarification whcih I would like to have.
Maybe you are looking for
-
How can I dynamically assign prompt and URI to a button in a table?
I've got a VO returning document name, link and a status flag. My resultsTable for this VO is currently displaying 3 fields: 2 messageStyledText fields for the document name and link text, and a switcher that shows a checkbox image or red X image dep
-
My MacBook Air is at 10.6.8 and I would like to upgrade the OS to Yosemite 10.10.1. How can I accomplish this and is it safe to do?
-
I can't turn off picture frame on the lock screen. The button accessed through settings won't let me turn it off. How do I do this? Thanks.
-
MR11 Number range not found.
Hi Guys, When I am executing MR11 , I am getting the error message that For object RE_BLEG the Number Range 04 does not exist. Why does it occur and can anyone tell me where I can adjust this. Thanks Srikanth
-