GR with MIGO against Scheduling Agreement

Hi,
Please advise what are the (sequence of) steps involved in doing a GR (with MIGO) against a Scheduling Agreement.
i.e.
Step 1- I have created a Scheduling Agreement (ME31L) for a particular material.
Step 2- I have defined the Schedule Line (ME38) for this scheduling agreement.
Step 3- ??
Step 4- GR (MIGO)..
Please advise on the sequence of steps for GR against a Scheduling Agreement. This is urgent please.
Thanks,
Manju

Hi,
Once the Scheduling agreement is created in ME31L and if you have maintained the Schedule lines in ME38,
If the Scheduling agreement is subjected to Release strategy first release the SA in ME35L
If the Vendor supplies the material as per your schedule lines then do the goods receipt in MIGO.
Enter the Scheduling agreement number in the place where you enter the PO number in MIGO, then system will copy the qty from the Schedule lines to MIGO then proceed same as like that PO
Post the stock to storage location.
System will consider Scheduling agreement same as PO in MIGO.
If you find any issue let me know and reply on the same.
rgds
Chidanand

Similar Messages

  • In MIGO against Scheduling agreement for Consignment error

    Dear SAP Gurus,
    I m getting abn error in MIGO for SA
    "Maintain pricing conditions for the material for the excise invoice date"
    vinod

    >
    GSMY Volvo wrote:
    > Hello,
    >
    > We want to receive material against delivery schedules of Scheduling agreement.
    >
    > Our setting are.
    > No MRP
    > Delivery schedules are created manually.
    > No confirmatin control.
    >
    > Issue is, delivery schedules are future date but i want to make MIGO today without changing the delivery schedules in ME38.
    > Is it standard SAP setting that we will not be able to receive the material for future dates ? or is there some setting in background ?
    >
    > Sundar
    Its standard SAP setting that migo cannot be done with delivery in future dates. To do migo, change the delivery schedule to today's date and then do the GR against the SA.

  • MIGO against Scheduling agreement.

    Hello,
    We want to receive material against delivery schedules of Scheduling agreement.
    Our setting are.
    No MRP
    Delivery schedules are created manually.
    No confirmatin control.
    Issue is, delivery schedules are future date but i want to make MIGO today without changing the delivery schedules in ME38.
    Is it standard SAP setting that we will not be able to receive the material for future dates ? or is there some setting in background ?
    Sundar

    >
    GSMY Volvo wrote:
    > Hello,
    >
    > We want to receive material against delivery schedules of Scheduling agreement.
    >
    > Our setting are.
    > No MRP
    > Delivery schedules are created manually.
    > No confirmatin control.
    >
    > Issue is, delivery schedules are future date but i want to make MIGO today without changing the delivery schedules in ME38.
    > Is it standard SAP setting that we will not be able to receive the material for future dates ? or is there some setting in background ?
    >
    > Sundar
    Its standard SAP setting that migo cannot be done with delivery in future dates. To do migo, change the delivery schedule to today's date and then do the GR against the SA.

  • Perform Post Goods Receipt Against Scheduling Agreement

    Dear all,
    I've weird problem here. This is concering GR against Scheduling Agreement. I've a "LPA" type Scheduling Agreement and all the delivery schedule maintained and schedule line released successfully in ME38.
    When I do GR via MIGO by entering the Scheduling Agreement #, a prompt was given with no items selected. Note: My schedule line delivery date = GR posting date.
    What I did was, inside MIGO I go to Settings | Default Values and check on "Propose All Items". Finally, the affected line item appears but with "blank" quantity. So, I key in the actual quantity per the released schedule line and complete the GR posting successfully.
    Question 1: Why do I need to perform the MIGO propose all items setting? Normal PGR against PO doesn't require this.
    Question 2: Is this a standard SAP behavior or I'm doing PGR - scheduling agreement process the wrong way?
    Appreciate any expert clarification.
    Thanks in advance.
    Steven

    Hi Jurgen,
    I've read Notes 493404 and I'm facing Question 10
    10. Question:
    For the goods receipt for the scheduling agreement the system displays error M7 064: "Document xx does not contain any selectable items".
    Answer:
    A possible reason is that the document is subject to a release strategy and has yet to be released. You can check this using transaction ME33 and release it subsequently if necessary.
    Another reason can be that although a confirmation control key that contains a confirmation category with GR assignment has been maintained for the scheduling agreement item, this category has yet to be confirmed. You can check this using transactions ME33 and OMGZ. If necessary, create the relevant confirmation.
    Another reason may be that no undelivered schedule line exists up to the posting date. If nevertheless you want to post the GR, you can use transaction ME38 to bring the next schedule line date forward, or in transaction MB01 you can select the "Suggest Zero Lines" field or in transaction MIGO the "Propose All Items" field under Settings - Default values.
    From the snapshot of the notes 493404 above:
    1. I don't have a release strategy for the scheduling agreement. Have checked via ME33L
    2. I didn't implement any confirmation control in the scheduling agreement. Have checked via ME33L
    3. I've a delivery schedule line up to the posting date. In my scenario, schedule line date = GR posting date
    Therefore, I'm still truly puzzle with the system behavior. Any further help will be most appreciated.
    Thanks.
    Steven

  • Error generating release against scheduling agreement  (cause 6) in ME38

    Hello Experts,
    Need your inputs on the the below error getting generated in ME38
    Error generating release against scheduling agreement  (cause 6)
    Message no. 06857
    Diagnosis
    The function module for generating a scheduling agreement release (forecast delivery schedule or JIT delivery schedule) has run up against an error, causing processing to be terminated.
    In this case the cause of the error is 6.
    System Response
    The error may involve one of the following situations:
    1: The nature of the error cannot be specified precisely.
    2: The forecast delivery schedule or the JIT delivery schedule was generated but no message record could be generated.
    3: A document type for which the functions "Generate forecast delivery schedule" or "Generate JIT delivery schedule" are not defined may be involved.
    4: A material for which the function "Generate JIT delivery schedule" is not defined may be involved.
    5: A scheduling agreement that has not yet been released by all persons responsible may be involved.
    6: The factory calendar has not been maintained correctly.
    Procedure
    Error source 1:
    Check whether the vendor and plant shown in the PO actually exist in the system.
    Error source 2:
    Check the Customizing facility for message determination with respect to delivery schedules created under scheduling agreements (print operation '9').
    Error source 3:
    In Customizing, maintain the document types accordingly ( Define document types for scheduling agreement). Then create a new scheduling agreement with a document type for which release documentation is defined.
    Error source 4:
    Maintain the JIT delivery schedule indicator in the material master record.
    Error source 5:
    Have the scheduling agreement released by the person(s) responsible.
    Error source 6:
    If you are using a release creation profile without aggregation, you must maintain the factory calendar for the next 999 days
    Regards,
    Santosh

    Hello Mallinath,
    I referred the note and following are the observarion in the system.
    Step1:Run T-code SE16 (table T001W) to check the calendar ID of the plant.
    -----Referred the Calendor ID
    Step2: Check the JIT/Forecast delivery schedule of release creation profile in customizing. (T-code OLME -> Scheduling Agreement -> Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu.)
    Run T-code SCAL to adjust the period of the calendar ID which checked in STEP 1 according to the JIT/Forecast delivery schedule of the release creation profile which checked in STEP 2.
    (For example, if the JIT/Forecast delivery schedule of the release creation profile is "999" days, then the calendar should be extended for the next 999 days at least)
    ---------In this case factory calendor is valid till 2015 and according to note needs to change the factory calendor till 2018( or for 999 days) ?
    Waiting for your inputs.
    Thanking you,
    Santosh

  • Error generating release against scheduling agreement

    Need help in resolving the below error msg for Scheduling Agreement.
    ERROR message:
    "Error generating release against scheduling agreement  (cause 2)"
    "2: The forecast delivery schedule or the JIT delivery schedule was generated but no message record could be generated."

    Yes.. its solved now...
    problem areas:
    1: delivery date not matching GR date.
        solution: chng delvry date to GR date in ME38 and thn do GR.
    2: Release not hapnd properly incase if u hav used doc typ LPA for JIT/Forcasting.
        solution: in ME84, chk if the indicator for 'create release' is 'green' for ur SA#. In ME38, select the line and click on 'Release" icon. Select ur relevant delivery schudle line and click on JIT release or Forcast Release icon. See if the indicator is 'Green". If not, the issue is wit message output for the perticular delivry date. (use msg typ LPET process for output) MAKE SURE U SAVE THIS CHNG. Chk againg for the Release indicator for delivry line. If green thn.. its done..
    Let me know if it was hlpful... or need clarity

  • I faile to create outbound delivery with reference to scheduling agreement by using BAPI_OUTB_DELIVERY_CREATE_SLS.

    Dear Team,
    Can you please help me by providing the BAPI name for creating the outbound delivery for Scheduling Agreement in SAP SD .
    I faile to create outbound delivery with reference to scheduling agreement by using BAPI_OUTB_DELIVERY_CREATE_SLS.
    The system says "missing data in the BAPI interface: VBAK VBTYP E". It seems another FM should be used for scheduling agreement only.
    Thank you for your help in this regard .

    Hi Raghu.
    As much as I don't want to do this but just to resolve this error I created an enhancement implementation in include LV50R_CREACSV form routine dcs_check_so_vs_interface and modified VBTYP to blank to avoid that error message.
    Got the tip from this thread http://scn.sap.com/thread/1972059
    Unless... anybody has a brighter idea (without modifying the standards)?

  • Movement Type 351 against scheduling agreement for future dates

    Dear Gurus,
    For stock transfer orders(Inter Plant Transfers), if the schedules in receiving plants are available only in future(say after 15 days), the sending plant is able to make 351 against such scheduling agreements today itself.
    Is there any way to control 351 movements against these scheduling agreements.
    Please reply.
    Points would be awarded.
    Regards
    Shankar

    Hi,
    we are taking multiple GR against Scheduling Agreement hence for Parking Invoice we are using "Delivery Note" as reference.
    but when we maintain delivery note system is not showing multiple GRs against Scheduling Agreement
    Invoice Parking is not done against these Invoice
    Please advce

  • Error generating release against Scheduling agreement (Cause 2)

    dear Sap Experts,
    Please advise me that Error generating release against Scheduling agreement (Cause 2)
    As i have already used transaction code OMQP  and click print operation 9 for LPH1 & LPJI A,
    How can i sort this problem.
    Thanks
    mohit

    Hi,
    pls find below thread
    SA delivery schedule release problem
    you have to Maintain condition records for LPJ1 and LPF1 in NACE
    maintain condition record in transaction MN10 for schedule release. And Generally in the condition records will be maintained for LPH1 & LPJ1in MN10.
    Once you maintain that, you can go to ME84 and ME38 release the schedule
    the JIT indicator in MMR for your material.
    Check that and also you can maintain a release creation profile in VMR or ME31L.
    Regards
    Raj.

  • Good Receipt against Scheduling Agreement

    Hi,
    I have created Scheduling Agreement and maintained delivery Schedule.
    No while making Good Receipt against scheduling agreement, system give message that no item exist.
    I have given date in delivery schedule for e.g 27.06.2008 and I am entering good receipt on 26.06.2008. But it is not possible.
    Once I change the date to 26.06.2008 in delivery schedule, then system allow to post a good receipt.
    Why, Is there any setting to remove this?
    Waiting for your reply.
    Thanks,
    Samir Bhatt

    Hi,
    Definition of Scheduling Agreement: - A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.
    This means schedule lines are fixed and you can only do Goods Receipt on the prodefined schedules. If you do not want this function then better create Contracts and then PO w.r.t. Contract.

  • Sap Error generating release against scheduling agreement  (cause 2)

    Hi,
    Please help me on this issue
    Error generating release against scheduling agreement  (cause 2)
    Message no. 06857
    Regards
    Amey

    Hi,
    For EDI you might be missing settings in:
    1) Matrl Mng -> Purchasing -> Messages -> Output control -> Output types -> Define Message Types for Scheduling Agreement Release/Expediter -> Fine-Tuned Control: Forecast Delivery Schedule/Expediter (check one of the outputs for 9 and for A )
    2) WE20  - EDI settings for partner that is a vendor who should receive your release information  DELFOR / DELJIT (if you do not manage other EDI settings then also other WEDI setings should be maintained)
    Best Regards,
    Tomek

  • Pending DO list against Scheduling Agreement

    Hi All,
    Could someone tell me how to extraxt list for pending DO list against Scheduling Agreement?
    Please reply me.
    Thanks,
    Sangeetha

    Use t.code ME3L report select selection perameters according to your requirement.
    Material wise ME3M - By material
    Material group wise ME3C - By material group .

  • DO List against Scheduling Agreement

    Hi All,
    Could someone tell me how to extraxt list for pending DO list against Scheduling Agreement?
    Please reply me.
    Thanks,
    Sangeetha

    Hi,
    Check if  ME91E(Scheduling Agreement Schedules: Urging/Reminders) can be used.
    Regards

  • Using a JIT call with stock transport scheduling agreement

    Hi,
    I have a requirement to send forecast schedules for a stock transport scheduling agreement from procuring plant to producing plant. Production would be done in producing plant against these forecast schedules. Producing plant would only ship against a JIT call (pull trigger) from procuring plant and not against a forecast schedule line. Is there a way in standard SAP to achieve this?
    Thanks,
    Krishna

    I don't think so.
    You need to transfer the production forecast as demand plan in the production plant. Have a MTS planning strategy (like 10), then manufacturing is triggered by this demand plan, and goods are stocked in the production plant, waiting for the pull call from the sales plant.
    Don't forget to take care of the consumption of demand with STO (I think there's a note on this).

  • Error in MIGO for Scheduling Agreement

    Dear All,
    I have created a Scheduling agreement in LP document type and saved with Net price.
    When i do the MIGO the error appears as below.
    Transaction cannot be posted due to errors in price determination
    Message no. ME573
    Diagnosis
    The error marked with 'X' occurred during the price determination process for purchasing document 5500000087 00010:
    [X] Net price is 0.
    [ ] Net price is negative.
    and/or there are no valid conditions or the duration of the
    contract has ended.
    [ ] Effective value is negative.
    [ ] Mandatory condition missing.
    [ ] Negative delivery costs.
    [ ] Delivery costs have been recorded although invoice
    receipts are not defined for the item.
    [ ] Error during quantity conversion
    [ ] Error during currency translation
    [ ] Field overflow
    [ ] A condition involving delivery costs exists without a
    transaction/event key.
    [ ]Error during maint. of delivery costs in master conditions
                  Delivery cost conditions in different validity  periods not identical
    System Response
    The transaction cannot be posted without successful price determination.
    Procedure
    Check the purchasing document and the associated conditions:
    Display purchase order
    Display scheduling agreement
    If the problem cannot be resolved in this way, contact your system administrator.
    The latter can check the Customizing settings for price determination in Purchasing under Conditions -> Define Price Determination Process
    When the foregoing steps have been carried out, try posting the transaction again.
    Kindly advice how to avoid this error.
    Regards

    Hi
    What type of document type are you using for Scheduling agreement? I think you are using time dependent conditions. (see it in document type definition config). If the tick mark is done for time dependent condition then in additional data of scheduling agreement line item pr.date category will be 5-GR date. So Your validity period for condition is not valid for today thats why you are getting error. You need to change validity period for your conditions. Then you will not get error.
    Regards
    Antony

Maybe you are looking for

  • How to remove icon from desktop

    I have added an external hard drive (for back up.)   It has a USB connection.  Its icon appears on my desktop.  It is only so much clutter, and I would like to make it disappear, as I have done with the icon of the internal HD.  Can that be done?  If

  • Lost my calendars after upgrading to mountain lion

    Please help! I just upgraded to Mountain Lion, clicked into my calendar and there is nothing. It's like a blank slate, except for what it comes with; 'work' 'home' US Holidays'. I had really important birthdays, meetings, work things, bills, etc. sch

  • Bug report - OOB site column ArticleStartDate is crawled according to GMT0 not user/server timezone

    This issue can be reproduced easily on any SP2013 farm (on-premise) and I heard Sharepoint online do not have this problem. Issue: Site column "Article Date" with fieldname "ArticleStartDate" is crawled as GMT 0 regardless what timezone your web appl

  • Multiplex Redo Logs and Control File

    I am wanting to setup an existing Oracle Express 10g instance to multiplex the redo log files and the control file. Instance is using Oracle-Managed Files and the Flash Recovery Area. With these options being used what are the steps required to setup

  • How do I apply any changes?

    I have an audio file I've fixed in STP but when I save it, it sounds like the original. Is there something I'm missing to lock in the changes I've made and export a new version?