Grey out Project/WBS number

Hi,
The Project definition/WBSE number in Project Systems is greyed out once the
project/WBSE is released. In that case, you could use activity type 45 for authorization objects C_PRPS* or C_PROJ* to provide authorization to change these numbers.
But, how do I grey out the PD/WBSE number immediately after the PD/WBSE is created? Can I do it through authorizations or a user status? I tried looking through the field selection for PD and WBS, but the PD and/or WBSE number are not part of the selections there. Any suggestion would be greatly helpful and rewarded through points.
Thanks!
Venkat.

Hi Satish,
With the validations you cannot get your requeriment only you can get this field cannot be editable ( but not greyed), due to valiations works after you are in the screen.
I am not sure how to get this, check WBS BAdi there is a method 'before save' I don't know if you can develop here to grey the field.
Regards,
Sara

Similar Messages

  • How to Grey out the field "tracking number" during change mode in the order

    HI Expert,
    How to grey out the Tracking number (AFVGD-BEDNR) at Order -> Operation tab -> external tab ->tracking number.
    during creation IW31 = not grey out and allow entry.
    for change mode IW32 = grey out
    if i set grey out at config OIOPD, it will grey out even during creation mode.
    Please advise
    Thanks
    Regards

    Hi
    I think Using field selection it is not possible to make as display ,kindly check with screen or transaction variant -SHD0
    regards
    thyagarajan

  • Iphone 4s greyed out caller id

    Please can someone help. I set up my new Iphone 4s via itunes from a previous backup all went well except when I go into settings/phone caller id is greyed out and says Number unknown instead of my mobile number.every thing else works fine.  I have contacted my service provider and they say its apples problem. Does anyone know how to resolve this matter

    Suddenly, my iPhone4s after switching fron BB with Verizon staying with Verizon.  Then one day the contacts were not associated with the caller ID even though they were in the contacts, including a special ringtone and sounds.  I also remember some minor glitches with bluetooth on my car(some names wouldnt be found or siri wouldnt work through the speakers). 
    When I activated the phone, they did it over the phone with me talking to them not using *228 like older phones.  I was later told to do that.  Dial *228, press 1, wait for confirmation that will say or show to some effect- your phone is now fully programmed.  Then you go to home.  Press home(tap) twice.  This brings up the bottom row alone and shows all apps currently still running in the background from before.  Touch and hold an icon until it giggles w a red dash.  Close all of them out (this will not terminate your ability to see them, use them, or receive texts and calls...it just closes them completely so they don't drain juice.).  close all the icons that are jiggling including especially phone and contacts.
    This should do it.  Last option was to do a reset/restore.  Some said through the phone for reset and through itunes for restore depending on what handles your contacts.  Have a backup ready though before doing that.

  • SAP PS: Changing the WBS number for a released project

    Hi Gurus,
    I am wondering if anyone here knows how to change the WBS number under a project that is released (REL). Until the project is partially released (PREL), the WBS number can be changed, but once it's released, the number is greyed out. Is there a special authorization that could be used to achieve this? I do have authorization to C_PRPS_VNR activity 45, but I believe it's the business transaction (for status REL) that's blocking this number from being changed. A quick answer will be highly appreciated and rewarded.
    Regards,
    Venkata.

    The WBS number cannot be changed after it has been released.

  • Project pane greys out after adding either HD movie footage or a photo'

    Project pane greys out after adding either HD movie footage or a photo' into iMovie '08. Since using a HD camcorder, quite often, after adding either HD movie footage or a photo', the project pane greys out. I have to exit the project and re-enter to continue viewing the project; this is tiresome. Any thoughts or is this yet another iMovie '08 bug?

    blackcomb greens wrote:
    PS ~ what is the plist?
    every app as a preference list, which can get corrupted.
    quit iM
    look in user/Library/Preferences for a file called com.apple.iMovie(x).plist (x stands for any number) ....
    trash that.
    restart iMovie..
    it doesn't hurt your projects nor does it touch any files.. it just 'resets' an app.. => slapp on backhead.. as I like to call it..
    yes, hardware is nice, as long as you don't dare to handle AVCHD .. that is on Intel Mac only..
    all Folders (Project/Events) is on local harddrive?
    no plug-ins installed (DivX etc)?

  • Has anyone experience a problem with not being able to add a drumbeat loop to a prerecorded project?  When I open the loop browser, there are only a few options available.  The rest are greyed out.  I can only choose individual drum sounds, not full beats

    I have created a project and recorded 2 tracks, one with a guitar and the other vocals.  I would like to add a drum loop, but when I pull up the loop browser, all of the normal selections aren't available.  Some are greyed out, including "Beats".  "All Drums" is available, but when I click on it it pulls up some cymbal sounds only.  I've opened some old recordings in GB to see if this is a consistent issue, but it's not.  Only this one project won't allow me to use drum loops.  Which leads me to believe there is something I have selected or not selected within the project that's not allowing me to see all the loops.  Any help would be much appreciated.
    Thanks,
    G Clef

    g_clef wrote:
    Only this one project won't allow me to use drum loops.
    http://www.bulletsandbones.com/GB/GBFAQ.html#missingloops ?
    (Let the page FULLY load. The link to your answer is at the top of your screen)

  • Project Server 2010 - Build Team from Enterprise Greyed out

    I am trying to find out why the Enterprise Resources are greyed out when I try to build an Enterprise Team for a project?
    Starting from Project Server, I open a project in Project Pro.  Then go to Resource..Add Resources..Build Enterprise Team.  In the Build Team window, the Enterprise Resources are greyed out and I am unable to add them to be Project Resources.
    Any ideas?

    David --
    To add to the excellent replies from Guillaume, if you are a member of the Project Managers group, you should be able to add resources to your project team (the resources should not be grayed out in the Build Team dialog).  This is assuming, however,
    that your Project Server administrator has not edited the default permissions in the Project Managers group or in the My Organization and My Projects categories that are part of the Project Managers group.
    Assuming that your Project Server administrator has NOT modified the permissions in the default Project Managers group, the other action that can cause your problem is if you are members of MULTIPLE security Groups, and in at least one of those Groups, your
    Project Server administrator has set a Denied value on one, two, or all three of the permissions that Guillaume references in his first post.
    So, to echo what Guillaume has told you, your situation is most likely caused by a permissions issue.  That being the cause, your Project Server administrator would need to track down and resolve the source of this issue.  Hope this helps.
    Dale A. Howard [MVP]

  • How do I import an existing finalised imovie into a new project either in part or full. The movie I want to import is filed under "movies" but greyed out when I go through the procedure in imovie 11

    How do I import an existing finalised movie clip into  a new developing project ? I go through the imovie 11 procedure for importing and the list of clips (finalised and un-finalised) appears, but always "greyed out" which makes it impossible to create anything. I have tried placing it on the desk top and dragging but this doesn't work either.

    AppleMan  Thanks very much for the information, however I could't make it work. I followed your instructions to the letter, in fact I tried every which-way. I created a dedicated file into which I copied and pasted the project from "package contents"  but it was still greyed out when I went to retrieve it. I also found that the file size was reduced to only a few Kb.  Any further step-by-step instructions would be appreciated as I am obviously doing something wrong.  Babowa  It appears that in imovie everything has to be "finalised" before it can be used or shared elsewhere in the same way as a disk has to be to be played elsewhere. Funnily enough an MOV file I converted to Mp4 was not greyed out and I was able to import it.... an exercise I am not keen on because of resolution loss during conversion

  • Why is Import Video greyed out for a new Flash project?

    I have been trying unsuccessfully to load any MP4 (H.264 encoding), FLV, or F4V files into a brand new project. I've tried importing FLV and F4V files via the Import to Library and Import to Stage menu choices but all result in "One or more files were not imported because there were problems reading them" error message. I just downloaded Flash CC today (Feb 23, 2014) and cannot even get started on my project since I cannot seem to load a video into the library or stage. I've looked at the tutorials, but they assume that I can choose the greyed out Import Video... menu choice. Searching the discussion didn't help me as most of the discussions are off-topic or from 2 or more years back.
    Thanks,
    Xtraspatial

    Thank you sinious. I had QT 7.5.5 installed. The problem was unrelated. Like a bufoon, I created a new HTML5 canvas, which is unable to import videos. When I switched to a AS3 canvas all was as it should be. And there was rejoicing throughout the land! Case closed.

  • How do I share a new project on imovie if the export option is greyed out and not an option?

    how do I share a new project on imovie if the export option is greyed out and not an option?

    nicoleking wrote:
    ... I heard that if you bring in your old iPhone, they will give you a new one with some kind of fee, but I don't know how that works.
    https://discussions.apple.com/message/22920500

  • All of a sudden this morning my iphone will not send imessages from my phone number but only from my email address. When I go to the settings for my imessages to choose where they are coming from my phone number is greyed out....Is there a way to fix this

    All of a sudden this morning my iphone will not send imessages from my phone....

    Hi Chas869,
    Hmm, that is strange that your phone number is greyed out. There are a few things that we can try. First would be to turn iMessages off, then back on. See if you are able to select your phone number. Then if that doesn't work, turn iMessages back off, then reset the network settings....settings>general>reset>reset network settings, this will reboot the phone. Don't worry, it won't delete anything from the phone, it simulates a battery pull. Once the device comes back on, then turn iMessages back on. Keep us posted if that works!
    ErinW_VZW
    Follow us on Twitter @VZWSupport

  • I would like to use GarageBand to remaster downloaded music files that are in iTunes.  Poorly mastered files keep clipping and damaging my speakers.  When I try to use an iTunes file as a new project, it greys out the iTunes songs so I can't select them.

    I would like to use GarageBand to remaster downloaded music files that are in iTunes.  Poorly mastered files keep clipping and damaging my speakers.  When I try to use an iTunes file as a new project, it greys out the iTunes songs so I can't select them.  Any ideas?

    As I said - look whether your original file is damaged or not. If not, I wouldn't change it and find out what in your system makes it sound like it's clipping.
    Good sound file, with volume maxed out. No need to change anything.
    The same song clipped - no chance to repair.

  • PA30 - Personnel Number field greyed out - No input help available.

    Hi Experts,
    In our System in DEV, & Quality  in PA30, we are unable to select employees either by directly giving the number (greyed out) or by selecting through F4 (No input help is available).
    But in Production System we can directly give Pernr or select through F4.
    Any body tell me what is the reason behind this.
    Thanks in advance.
    Samanvita.

    Hi Hariprasath,
    It is not the issue with NUMKR, The number Ranges are already maintained, and are defaulted in NUMKR feature.
    This is showing same in DEV / QA/ Prod.
    Issue is in DEV / QA,  The Personnel Number Field is Greyed out, and not able to select any number.
    For that we are going to PA20, open the personnel number first, and open PA30 in another window, then we are changing the data of the employee.
    But we want to give Personnel Number in PA30 itself as per SAP Standard.
    Any Idea, why it is like this.
    Thanks,
    Samanvita

  • My number is greyed out in iMessage, I can only use my email, help me!

    I've just updated my iPhone 5 to iOS 7 and now when I iMessage people it comes up with my email address and i went into messages in settings and my number is greyed out with my email address under it ticked, I've tried everything such as turning it off and back on, adding my number to my Apple ID etc. please someone help me!

    And now I can't even log into iMessage with my Apple ID!!

  • EPT on New project option at project center are all Greyed out

    Hello, 
    We have a problem with only 2 users within the PWA. They can not create new projects. When they click the New button on the project center, all EPTs are gray. 
    We think it was a issue with the permissions. So, we removed all the groups from the users and assign again, but the problem persisted. For other users with the same permission there are no problems. 
    Furthermore, we tested with the same user on other computers, and the problem persists. We believe it's tied to the user. 
    We are using Project Server 2010. 
    If more information is needed, please let me know.
    Tks!

    Hi Alessandro,
    If it was an issue about the permissions, the "new" button would be greyed out preventing users to click on it and seeing the EPT list. If they can click on "new" but only the EPTs are greyed out, then it is another issue..
    Are the users part of a department? Have you associated EPT with departments?
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

Maybe you are looking for

  • Dunning letters run automatically on a weekly basis

    Hi Expert, Is it possible to make the dunning letters run automatically on a weekly basis? If the answer is yes, then what config do we need to run the report on wekkly basis or what are the steps. Please let me know in very details, because, I am no

  • Printing Date in Spanish language

    Post Author: amumahajan CA Forum: General I'm using Crystal Reports XI Professional. I'm printing the report generation date on top of the report. I want that date to be in Spanish. Does anyone know how to translate a date from English to another lan

  • Installation of Adobe Acrobat XI Standard

    How do I install if the program is on CD and my computer does not have a CD drive?

  • Can someone tell me where in numbers 3.0 the formula bar is, or how I can make it visible?

    Hi, I've updated to the new numbers (3.0) and acutally it looks not back. But there is one point that really annoys me. I cannot find the formula bar and also I could not find in the menu where I can make it visible. Any hints from the community? Tha

  • IPhone 4 in recovery mode

    Hi there Firstly I'm not the most techno sharp person so I apologise for needing an idiots guide in advance. I woke up the other morning to find my phone not working and showing the connect to iTunes logo. After searching in various places I download