Help me to guide create schedule lines in MRP
hi
This is my MRP initial screen
Processing key NETCH Net change for total horizon
Create purchase req. 1 Purchase requisitions
Delivery schedules 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning data
Scheduling 1 Basic
I already Maintain the Source list in ME01 with Vendor & Plant then input the Scheduling agreement number and the MRP as 2.
but i counld,t get schedule lines why
thanks
jai
Edited by: Jai on Sep 30, 2008 12:55 PM
Edited by: Jai on Sep 30, 2008 12:55 PM
hi friends,
once i run the MRP MD03 it creates only PR
there is no schedule lines
thats also my problem
please expalin and solve my problem
thanks
jai
Similar Messages
-
Auto Email Throgh SAP After Creating Schedule Line Through MRP Run
Hello experts,
is it possible to have email generation when scheduling lines are created through MRP run ? if yes kindly let me know the procedure.
Regards,
DurgeshHello Raghavendra,
For same requirement i did what you suggested but Can you please guide us what Business object needs to be used as start event for WF3100020 which we are activating. Because We are not able to activate the standard workflow.
It will be better if you help us with steps.
Thanks in advance.
Regards,
Yuvraj -
Provide -- the steps involve (in detail) to create schedule lines from MRP
Dear All
Please provide me with the steps (in details) involved to create the schedule lines automatically from MRP.
Early help would be appreciated.
Regards
Rahul BhardwajHi,
1. In Material Master --> Purchasing View --> maintain the Tick for Scource list.
2. Create th Scheduling Agreement. (valid)
3. Maintain the Source list with the Scheduling Agreement and MRP indicator as 2.
4. MRP Control Parameters - Delivery Schedules - 3 (Schedule Lines).
After MRP Run, system will create the Sched. Lines for you..
For your earlier questions also please check these points..
Regards,
Siva -
Error in creating schedule line aggrement through BAPI
Hi All ,
I want to create schedule line aggrement (VA31) by using BAPI / FM .
I am using " SD_SALESDOCUMENT_CREATE" FM .
Here i am getting error in output when i enter shchedle line data in input .
Error is given below .
E V1 434 No schedule line category could be determined during quantity adjustment
Error only come when i want to create new schedule line ....in Changing any schedule line aggrement there is no error .
I am able to create schedule line aggrement manually .
please help .Use BAPI_SAG_CREATE
-
Unable to create Schedule line(Maintain sch.agreement)
Hi experts,
After running MRP i got Planned order for a certain material and for that material procurement type maintained as "Both internal and external" in material master. After completing the process planned order to purchase requisition, i separately created schedule agreement . Now here i am facing one problem that if i create schedule line with reference to purchase requsition i am getting the error Requisition doc. type NB not allowed with doc.type LP.
pls anybody suggest is there any prob made in the above process
Regs,
SR
Edited by: SP Ramesh on Jan 1, 2010 8:22 AMgo to tcode OLME> schedule agreement> select the line of document type LP and then slecte the folled item category and then selce each item category one by one and then click on the second folders link document type and there give source document type NB
cause of the issue is : the source document type NB is not set with LP document type of schedule agreement -
Any function module available for creating new schedule line specifying schedule line type along with other schedule line related entries
HI,
you can user FM : ME_CREATE_SCHEDULE_DOC to create schedule line agreements.
Thansks,
Nelson -
Hi All
please guide me what is setting for create scheduling line in MD04 automatically?
we created scheduling agreement and when we run MD03 system doesn't create scheduling line and not show in MD04
best regards
R.THi,
MD04 is for List out the stock requirement.
Goto MD04, enter your material & MRP area, execute.
Check the material is already available.
If you don't have any requirement, then Goto MD61 and create a planned oreder.
Now you check MD04.
If requirement is there, you can create schedule line now.
Check the folows:
- procurement type F
- in me01 schedule line item number mentioned in source list or not ?
- me01 MRP column update with 2 in me01
- valid from valid to check in me01.
- source list tick activated in mm02 or not ?
- if more than 2 vendor for same item - check quota arrangement in mm02 should be 3 and maintain quota arrangement in meq1 for all vendors which are mentioned in me01
- once again delete all planned order and re run MRP , md01 parameter for schedule line should be 3 , create PR = 1 , planning mode = 2 , scheduling = 2 -
Generate schedule lines via MRP
Hi,
Unable to generate schedule lines via MRP.
Settings:
Mat master - External proc , no spl proc
OA - Maintained
Source list - Maintained MRP Relevant - Indicator 2
Quota arrangement- Exist with only 1 vendor(same as of OA) 100%
MD03 - Planning data - Create PR (indicator-1), Create Sl(indicator 3)
Please let me know whether there is anything else which influence SL generation.Hi,
hi,
1. Mark checkbox source list in material master.
2. purchase info record for the vendor & material combination
3. source list for the material - mention the scheduling agreement and mark as mrp relevant, schedule lines generated
4. Use MD03, choosing 1 for purchase requisition, 3 for schedule lines and planning mode, prerequisites requirement exists for material. If requirement does not exists it will not create scheduling agreement line.
I hope you got all your answers. so kindly close this thread.
YB -
Schedule line in MRP........
Hi there,
When running the MRP we have the option to create either the Purchase requistion or the Schedule line........
I am aware that the an outline agreement is maintained against which materials are procured at a series of predefined points in time over a certain period.........
what is the advatage we have over creating schedule lines over the Purchase Requistion during the MRP run......
Please enlighten me .......!!!
Thanks
KaushikHi,
If the MRP run determines the Scheduling agreement as the source it can create the delivery schedules (i.e. each call off against this agreement) automatically and so no effort is required by the purchasing department.
If you choose to have P reqs, then these will have to be converted by someone into the schedules before the vendor is made aware of the requirement.
So creating the schedules automatically in MRP is very efficient, but if you want extra control (i.e. by someone in the purchasing department viewing each requirement) then set it to P reqs instead (not ideal)
Steve B -
Hi Friends,
I have a scenario where in After running MRP, new schedule lines are being generated for an ROH inspite of having sufficient stock(in unrestricted use) & also some open schedule lines to fulfill the requirements. Kindly suggest as to how can i control the generation of schedule lines through MRP.
Regards,
SKHi Bala
The MRP type maintained is PD.
Rgds,
SK -
MRP - Problem in scheduling of MRP created schedule lines
Hi,
I am working with single level BOM of FG and trying to generate Schedule lines for RM as per requirement coming from FG - BOM explosion during MRP run -
Material master setting of RM is as below -
MRP type - PD,
Lot Size - Ex,
Procurement type - F,
Planned dlv time - 14 days
i am getting dependent requirement as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
And schedule lines are generated as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
The date of schedule line should be after taking calculation of planned del time of the RM, which is not happening. I can't understand why?
The planned dlv time is same in all 1) Material Master 2) Scheduling agreement and 3) Pur info record
Please help.
Regards,
AmolDear Amol,
the date shown is the ultimate reciet date and not start date.
Since you have already converted PR into schedule lines you will not be able to see the actual start date.
If it was still a PR you can see the release date as planed delivery time days early.
If the requirements date was say 31/05/2009 and you were taking planning run today then the recieved date would come as 05/06/2009.that is 14 days from today.
if requirement well beyond planned delivery time then the planned delivery time will not reflect in recipt date. -
Creating Schedule lines in Scheduling agreement using LSMW
Hi,
I want to upload multiple schedule lines in scheduling agreement using LSMW. I have done the recording and maintained multiple lines in input file. However during execution LSMW creates only one line and keeps on ovewritting the same line. Please let me know how can I create multiple schedule lines.
RegardsFirst you should search for existing standard LSMW migration objects that possibly cover your scenario. These normally take care of complex header / multiple items / multiple subitems relations.
With a recording you can only load flat structures. Sometimes a "create new lines" / "enter first line" / "save transaction" logic can be constructed to load multiple items to a header (or even subitems to an item?) with a recording, but this can be pretty awkward.
Thomas -
BADI / user-exit for MD02 while creating Schedule Lines
Hi experts,
I have a problem with implementation that I'm designing.
Current situation:
While MRP run (MD02 or background) new Schedule Lines are being created in reference to MM Scheduling Agreement.
Example:
04.08.2014
SchLne
5500000415/00010
200
04.08.2014
IndReq
VSFB
200-
05.08.2014
SchLne
5500000415/00010
300
05.08.2014
IndReq
VSFB
300-
2 Schedule Lines where created - for wuantity 200 and 300.
Target:
There is a need to create more than one Schedule Line per day during MRP run. According to example there should be for example 2 Schedule Lines in 04/08 and 3 Schedule Lines in 05/08 all for quantity = 100. There is possibility to change Schedule Lines in ME38, but there is a need to make a change during creatin while MRP run.
04.08.2014
IndReq
VSFB
200-
04.08.2014
SchLne
5500000415/00010 *
100
04.08.2014
SchLne
5500000415/00010 *
100
05.08.2014
IndReq
VSFB
300-
06.08.2014
SchLne
5500000415/00010 *
100
06.08.2014
SchLne
5500000415/00010 *
100
06.08.2014
SchLne
5500000415/00010 *
100
So instead of creating only 2 Schedule Lines, MRP should create 5.
I'm looking for a BADI/user-exit to edit Schedule Lines which are to be created by MRP and change it tn reference to the needs.
I found only one BADI:
BADI: MD_CHANGE_MRP_DATA
method: CHANGE_MDPSX_MDBS
The priblem is that this method is only being executed when there are Schedule Lines which already exist.
Maybe some of you have done some extension similar to mine? Please give me advice where I should put extension.
Thanks in advance!Dear Saravaran,
Thanks for the reply.
This will not suits to us. The provided BADI will works upto Posting the material document in transaction MIGO and it will not considered for the FI level entries.
Hope you could have understand mine requirement.
The requirement of mine is:
While doing the GR with ref to PO the material documnet will be posted and subsequently FI documnet will be generated in Background. While generating the FI document i need to manipulate the values for the G/L. So that the manipulated values will be flow into BKPF and BSEG tables.
Thanks.
Regards
Swamy -
MRP in third party scenario. System not creating schedule lines
HI
I am using third party subcontracting scenario. As i am purchasing material but i am not taking material in under my company. I am paying to my vendor but the delivery is going to my subcontractor.
Here i am able to create planned order or purchase requisition. But MRP is not generating schedule lines for that vendor.
Regards,
Anand.Hello,
Check the following settings.
1. Source list active in Material master.
2. Valididy of the source list.
3. Any quota arrangement
4. Purchase infor record.
Note: all are OK, but still PR's only created, then check for the requirement date, if the requirement date lies before the validity of the source list then also system will create only purchase requisitions.
for this calculation you have to check the lead time for procurement cycle you have to check. Based on this no. of days only system will try to create the procurement proposals.
If the lead time is very high and this is going beyond the sourcelist validity, then also PR's only created.
So there are so many possibilities. check for the above said things and revert back.
regards,
<Manick> -
Converting contract to sales order does not auto create schedule lines
Hi
When I convert quotation to sales order, then schedule lines get auto created.
But when I convert contract to sales order, then schedule lines don't be auto created. Instead, a confirmation screen for proposal delivery date pops up for every line item in the sales order.
Is there any suggestion how can I solve my problem ?
Thanks..Hi,
In standard SD module, system checks availability for each line item, gives you popup screen of confirmation.
If you don't want availability or popuscreen of confirmation,then
Go to VOV6 >>> Select schedule line which you are using in sales order for line item >>> Remove tick mark of availability check.
Else
Remove availability check rule from material master >>> Under tab Sales : ganral/plant
kapil
Maybe you are looking for
-
How to get !--$HttpRelativeWebRoot-- in css file?
Hi, the ucm does not execute the idocs script in css file. How can I get the information in css file? .header{ background:url(<!--$HttpRelativeWebRoot-->groups/webfiles/documents/webfiles/wcm_001871.jpg) no-repeat left 0px; height:104px;
-
An answer regarding language and TOC
I am writing this little post because I know how frustrated you can become about small, small things. Things that make your book not entirely into your own language. I have posted questions in many threads - and finally got a solution for us who are
-
Change default applications in Nokia 5530 XM
Hi there, I have a question about setting the default applications under Menu -> Settings -> Phone -> Application sett. -> Default apps. As I understand this, I can change the default application here. But I can't. I want to change the default webbro
-
How to restore Photoshop albums
Adobe Photoshop 8 Previously Windows XP, now Windows 7 A friend's PC became unusable due to a defective motherboard. She was able do copy all her pictures to the new PC. She now needs to know how copy her album catalogs from the old disk (which is pe
-
Get output messages in invoice creation
Hi all, in invoice creation, how can i get all the output messages for that invoice? In the NAST table there is no record because the invoice is not yet created. Regards Roberto