Actually, we have SAS Server running on Windows 7. Till the day one of the developer is manually running the jobs.
Now client want to use Tidal Enterprise Scheduler for all Servers(including SAS) for executing jobs, which is present in another windows 7. We are working on SAS with Tidal.
We have created a .bat file on SAS server which is having below line.
“C:\Program Files\SAS\SAS 9.1\SAS.EXE" -SYSIN "\\uscol2k3sas02\SASBATCH\VDM\Batch\BatchRunSas\PCRPManualAdjustmentsDaily_testing.sas"
Then finally we are trying to schedule the .bat file in Tidal. We have received the status as “status change to Externally Defined” without executing the job in SAS server.

Hi seniblue,
Welcome to TES @ Support Forums. Have you reviewed your MLA to see what it covers - and how long support is for? And did you know that Cisco has pushed the EOL & EOS date further into January 31, 2016. So you still have time, but planning should start now.
http://www.cisco.com/c/en/us/products/collateral/cloud-systems-management/tidal-enterprise-scheduler/eol_c51-697468.html
Tidal 6.0 is pretty buggy from what I've been told, and to perform an upgrade -- it would be better to jump from 5.3 to 6.2 directly. There are a lot of people in a similar situation, please check out
https://supportforums.cisco.com/discussion/12348951/tidal-621-client-manager-and-fault-monitor
BR,
Derrick Au

Similar Messages

  • Cicso Tidal Enterprise Scheduler

                       We use Tidal Enterprise Scheduler for the submitting of our batch processes on Unix and Windows platforms.  Currently we run SAS on windows and use the SAS adapter to make this happnen.  Now a director wants to know how we can run SAS using Tidal on a Unix platform.  Does Tidal require another adapter for this?, if not does anyone have an example of how to get Tidal to submit batch processes to run SAS on  Unix?
    Thanks

    It disturbs me you received no answer on this forum. I'll leave something for others who still have this question.
    We use the Oracle adapters (not SAP) but ERP adapters are platform independent.  You may have a component that installs on your unix SAS platform different than on Windows; however, you license to the SAS adapter doesn't change.
    If you were using Windows command line processes as well since your platform was on Windows but will now be on Unix, you may have to get the SSH adapter for unix/linux so that you can invoke OS level processes in the new SAS environment. But you business processes scheduled under the SAS adapter should work as is (or by increasing the patch level of them). Typically going from Windows to unix you're likely updating your SAS version so you need to check that version support with Tidal.
    SAS platform are a good time to get your Tidal SAS agent up to the latest patch level as well.
    http://www.cisco.com/c/dam/en/us/products/collateral/cloud-systems-management/tidal-enterprise-adapter-sap-businessobjects/1014F0710_cte_adapter_for_sap.pdf

  • Tidal Enterprise Scheduler - Get Job status using c#

    Is it possible to get the list of jobs scheduled and their status in Tidal Enterprise scheduler using a programming language like C# ?

    API depends on your version and you need to have the client installed from Server/DEsktop initiating the API
    the PDF document should have been included on you CD2 called Command Line Program Guide
    I will use 5.3.1 as an example:
    open a command prompt
    Browse to C:\Program Files (x86)\TIDAL\Scheduler\client
    type in set alias=DEV > example=DEV otherwise it defaults to Admiral
    type in SACMD
    type  HOST I always type in HOST so I can verify what master I am running against (nio need if only one connection)
    type in jobmon with your options I included below from doc
    [-d date] +display_options [filtering_options] [-b]
    It may be of limited use in 5.3.1 because to isolate you need to know Job ID or Alias or some other filter critiera... Job ID is in database jobmst.dbo.jobmst_id which is the unique identified and can be different from alias... depending on your  requirements (dashboard?) and how you have organized your jobs a SQL query would be the better option. 
    DISPLAY
    r
    Job rule ID
    i
    Job run ID
    p
    Parent job group ID
    j
    Job type (job or job group)
    c
    Occurrence number
    o
    Job or job group owner
    u
    Runtime user
    h
    Agent The Agent the job runs on
    z
    Scheduled vs. unscheduled job
    t
    Job start time
    s
    Job status
    v
    Job duration
    n
    Job name
    a
    Job alias
    q
    Queue
    x
    Exit code
    FILTER
    -r
    rule_id Job rule ID
    -p
    group_id Parent job group ID
    -j
    type Job type. You can choose: job group: group, or 1 job: Job, or 2
    -o
    owner Job or job group owner
    -u
    run_user Runtime user
    -h
    agent The Agent name the job runs on
    -s
    job Status ( Completed Abnormally=103, Normal=101)
    -a
    alias Job alias
    -x
    exit_code Exit code
    -b
    Suppresses the header information

  • Tidal Enterprise Scheduler Upgrade Paths

    Hi guys....
    We currently run Tidal Masters v5.3.1 and Linux Agents 3.0.x. We've been running in an environment so strict to changes that I didn't look at upgrade options for years. But now that EOL already kicks in... I have no choice but to look at upgrades.
    From my understanding ... the highest available upgrade for this version is Masters 6.0 using the same licensing methods.
    To upgrade to latest version (6.2?) ... the licensing model will change to per physical machine.
    Did I understand things correctly?
    I've been trying to understand the technical changes too... but it seems a little vague... can a Cisco professional help me understand the major differences between
    - 5.3.1 and 6.0
    - 6.0 and 6.2

    Hi seniblue,
    Welcome to TES @ Support Forums. Have you reviewed your MLA to see what it covers - and how long support is for? And did you know that Cisco has pushed the EOL & EOS date further into January 31, 2016. So you still have time, but planning should start now.
    http://www.cisco.com/c/en/us/products/collateral/cloud-systems-management/tidal-enterprise-scheduler/eol_c51-697468.html
    Tidal 6.0 is pretty buggy from what I've been told, and to perform an upgrade -- it would be better to jump from 5.3 to 6.2 directly. There are a lot of people in a similar situation, please check out
    https://supportforums.cisco.com/discussion/12348951/tidal-621-client-manager-and-fault-monitor
    BR,
    Derrick Au

  • Informatica Concurrent Schedules from Tidal Enterprise Scheduler

    Hi, I'm trying to run a Informatica job which has been set up with 3 instances.  If I run if from Informatica it runs all 3 instances  just as expected.  If I run it from Tidal Enterprise Scheduler, it only ever runs 1.
    Anyone have any ideas please>

    Hi seniblue,
    Welcome to TES @ Support Forums. Have you reviewed your MLA to see what it covers - and how long support is for? And did you know that Cisco has pushed the EOL & EOS date further into January 31, 2016. So you still have time, but planning should start now.
    http://www.cisco.com/c/en/us/products/collateral/cloud-systems-management/tidal-enterprise-scheduler/eol_c51-697468.html
    Tidal 6.0 is pretty buggy from what I've been told, and to perform an upgrade -- it would be better to jump from 5.3 to 6.2 directly. There are a lot of people in a similar situation, please check out
    https://supportforums.cisco.com/discussion/12348951/tidal-621-client-manager-and-fault-monitor
    BR,
    Derrick Au

  • Announcing Cisco Tidal Enterprise Scheduler (TES) 6.2.1

    We are happy to announce the general availability of TES 6.2.1!
    TES 6.2.1 software and related documents have been published in Cisco.com as of Aug 5, 2014.
    What is new in TES 6.2.1:
    Full-fledged version of Java Client
    JDE Adapter Enhancement to support OSA_CLASS
    Oracle Apps 12.1 MOAC support
    Oracle 12c support
    Master and Client Manager database
    Oracle DB and JDBC Adapter
    Windows 2012 R2 Server DC edition support
    MSSQL Server 2012 Always-On support
    Master and Client Manager database
    MSSQL DB and JDBC Adapter
    AD 2012 support
    Derby cache deprecation for Client Manager
    Internet Explorer 11 support (compatibility mode)
    Bug fixes and hot fix roll ups
    Here are the links to the key documents and download site for quick reference:
    Install and Upgrade Guides
    Cisco Tidal Enterprise Scheduler 6.2.1 Installation Guide
    Technical References
    Cisco Tidal Enterprise Scheduler 6.2.1 Performance Tuning Guide
    Release Notes
    Cisco Tidal Enterprise Scheduler 6.2.1 Release Notes
    Software Download
    Download TES 6.2.1
    In case if you missed our July 31 webinar on TES 6.2.1, we encourage you to take a look at the presentation attached here.
    For more on the Tidal Enterprise Scheduler visit http://www.cisco.com/go/workloadautomation

    Yah....!! Tidal 6.2X offering good features like Java Client which will help Tidal Developers to work more enthusiastically.

  • Using BOE Enterprise Scheduler with Sap BODI?

    Hi,
      I am under the impression that you can use the BOE Enterprise Scheduler to schedule BODS jobs. Can you also use the BOE Enterprise Scheduler to schedule BODI jobs? Is there someplace I can get some documentation on how to integrate the BOE Scheduler with BODI and/or BODS? I haven't been able to find any yet...
    Thanks in advance!
    Mike

    you can open the technical manuals from Designer
    or from the following location
    %LINK_DIR%\Doc\Books\en\DITechnicalManuals.pdf
    navigate to following section from the PDF doc (left pane will display the doc Map)
    Data Integrator Management Console: Administrator Guide
    -Batch jobs
         -Scheduling jobs
              -Scheduling jobs in BusinessObjects Enterprise

  • Regarding Calendar Expiry in Tidal Enterprise Scheduler

    Hi All,
    While checking the Tidal Admiral DB i found that the Table evntmst contains a column evntmst_untildt which contains information about the Last possible calendar date to include. If the date mentioned is 31st DEC 2013 does it means after this date the Calendar will get expire? if so how to change the expiration date.
    Thanks.     
    Parul.          

    The data model says that field is Last possible calendar date to include
    Looking at our dates in our database I would say that that field isn't used for either calculation or expiraiton.
    I think Cisco TAC would have to comment further, but if I were to bet... I would say that it was obsoleted...
    I just created a calendar in our dev environment and heres what I found:
    evntmst_untildt        <--- looks like this stores the calculated date 3 years out to the end of that year
    2016-12-31 00:00:00.000
    evntmst_lstcmptm   <-- last Last time dates for this calendar were compiled
    2013-09-11 11:43:50.000
    if Calendars did expire it would create huge operational headaches..
    How would you even know what the value is as I don't think that field is exposed through the GUI
    From a best practices/maintenance perspective
    We calculate all our calendards annually in december to project out the date 3 years
    Marc

  • Help regarding pm tables link with fi/co tables

    Hi ,
           I need urgent requirement regarding one object.
    my need is i want to know the link among the plant maintenance tables with fi/co tables.
    my out put is depends on equipment no fetch diff g/l accounts.
    how to fetch data from diff g/l accounts depends on pm table equi.becoz i am getting equipment no from equi table.
    Thanks n regards,
    khadar.

    thanq for ur reply ,
    In my selection criteria I have equipment no and date and diff radio buttons for diff g/l accounts ,depends on that I have to fetch dig g/l accounts with equipment and class
    with regards,
    khadar.

  • Tidal Enterprise Scheduler is Sending Blank E-mails

    Hi,
    We're trying to pin down what exactly is happening - jobs running (whether they fail or not) are returning e-mails to users (as intended) with nothing in them (which is not intended).
    It was my understanding that the emails returned to users usually do not behave in this manner. They seem to be sending them repeatedly during one time interval (one user got three emails with nothing in them at 10:00AM).
    Thanks.

    I'd suggest going to 6.2.1 patched up to the eyeballs There have been some big improvements in performance and the new java client is actually pretty nice.
    A big win was swapping ojdbc7.jar to ojdbc6.jar which I think is something you can do in 6.1.
    For us it turned the web client from borderline useless to very effective.

  • Help regarding XML-Based Integration with XAware

    If any one have some tutorial related with this topic:
    XML-Based Integration with XAware Kirstan Vandersluis

    It's a book. Go and buy it. Why would any part of it be available for free on the web?

  • Help Regarding Xi integrating with Seibel System.

    HI @,
    I have to intergrate a seible system with R/3 but I haven't worked on the same before.
    I need help regarding seibel inetrgartion scenarions and various adapters that can be used in that conditions.
    Documents on Seible Integration will b really helpful.
    Regards

    It would be better to go for the iway adapter for this integration requirement. The other documents can be obtained direclty from iway
    Regards,
    Prateek

  • Hello Creative Cloud Illustrator Community. Help Please! This is with regard to compound paths and transparencies. I have set some type on a circle and then created outlines. I then placed the outlined type on a black stroked ring which I then selected "o

    Hello Creative Cloud Illustrator Community:
    Help Please!
    This is with regard to creating a compound path:
    I have set some white type on a circle and then created outlines. I then placed the outlined type on a black stroked ring which I then selected "outlined stroke." I then put both "outlined" graphical elements on a separate solid bkg. (all 3 are on the same layer). Lastly, I then selected the top two elements and went to "make" a "compound path" (because I want the type to be the "holes" so I can see through to the background). However, the only effect I get is the white outlined type turning black (the same color as the black ring). What am i doing wrong? I can achieve the desired result with simple boxes but it won't work with a circular type path, a stroked ring and a solid bkg.
    Any help on this would be greatly appreciated!
    Thank You!

    Thanks for the response Jacob.
    Unfortunately, I tried your suggestion with no success. BTW, minus front is now Subtract. Apparently, by clicking option>subtract, it works in the same way as minus front. I tried this to no avail.
    Let me reiterate please.
    I have 3 graphic elements-all on the same layer:
    1. Background: Gold circle with a fill and no stroke.
    2. Middle: Black ring (Stroked) inside gold background circle.
    3. Top: White copy set on a circular type path and placed directly on top of middle black ring.
    Both the middle black ring and top type path HAVE BEEN CONVERTED TO OUTLINES.
    LASTLY, I select the Middle and Top, go to Compound Paths and choose "Make" and my white copy turns to black. Wrong!
    WHAT I WANT TO HAPPEN: I want the white copy to become HOLES, so the GOLD background shows through.
    Any solutions would be very much appreciated!

  • Any help regarding iphone 4 and locks with o2

    any help regarding iphone 4 and locks with o2
    i just got my second hand iphone4
    and a friend of a friend said it was factory unlocked
    and received txt from o2 saying it was unlocked
    however when i got home i put my micro sim into it
    and
    itunes said
    "this sim card appears to be unsupported" or something similer
    it is factory unlocked because the model number in the settings is
    MC603B
    i rang o2 to ask for unlock. gave them the imei code and they said they have to send the request off to apple for a code

    i rang o2 to ask for unlock. gave them the imei code and they said they have to send the request off to apple for a code
    Obviously the iPhone was/is not unlocked or this would not be required, and there is your answer, which can take up to two weeks.

  • How do I fix BIP Enterprise Scheduler critical error : JMSAdminWrapper?

    Hi
    I'm having a problem with BI Publisher Enterprise Scheduler running on WebLogic.
    The Scheduler Diagnostics tab states the following Critical error :
    +*"Start Error; JMSAdminWrapper failed to start JMSWrapper, javax.naming.NameNotFoundException: While trying to lookup 'BIP.JMS.CF' didn't find subcontext 'BIP'. Resolved '' [Root exception is javax.naming.NameNotFoundException: While trying to lookup 'BIP.JMS.CF' didn't find subcontext 'BIP'. Resolved '']; remaining name 'BIP/JMS/CF'"+*
    The Scheduler Config settings are all default values:
    - Scheduler: Quartz
    - Database Connection Type: JNDI
    - JMS Provider: WebLogic
    - JMS JNDI URL: t3://localhost:7001
    Would anyone know what the problem is and how to resolve it?
    Any help would be much appreciated.
    Thanks
    Greg

    I had the same error, my BI Publisher domain is as follows:
    AdminServer: localhost: 7001
    bi_server1: localhost 9704
    In the default installation, the configuration is assigned the AdminSever (7001), if you look at the file */oracle/domains/bipublisher_domain/config/bipublisher/repository/Admin/Scheduler/jms_cluster_config.properties* you'll find that setting.
    see: JMS_WEBLOGIC_JNDI_URL=t3\://localhost\:7001
    Option 1: change the file and then restart the server.
    Option 2: Login in http://localhost:9704/xmlpserver/, then go to "*Administration*" -> "*Scheduler Diagnostics*" -> "*Scheduler Configuration*" in the text box "*WebLogic JNDI URL*" you can change the setting, then apply the changes and finally restart the server.
    Best Regards.-
    Alexis Quiros
    Edited by: alexisquiros on 17-sep-2011 7:08

Maybe you are looking for

  • Mis match in attributes of item category B-limit and PO item details

    Hi I could not able to create a Blanket PO with document type FO and item category B (limit). Normally for a blanket PO, GR is not allowed and IR is mandatory. So, I could able to see these checkboxes for GR (not set and grayed) and IR (set and graye

  • I have pre-ordered an album and all of the songs are available for download apart from one which is listed as 99p to buy?

    Hello, I hope someone can help me. I pre-ordered Justin Timberlake's new album and have tried to download the album today, however for some reason "Suit & Tie" is listed as unpurchased and will charge me 99p to download? All the other tracks have dow

  • How do I get my HP Touchpad to turn on?

    My Touchpad will not turn on. When i plug in the charger it still won't boot up. But it does show lights at the bottom center button flashing left, right, and back to left...then a pause and the same sequence starts again.

  • Summary report needs one type condition

    I have a summary report which has this data: transcode     count 001              10 WOC           12 MOC            14 we have making up the orders that are summarized many order_types. For the 001 transcode, we only want to process a specific order

  • Float before production reg.

    HI dudes, one of my client is having one issue regarding floats, they are using float before production in the schedule margin key and they complaining that the total production time for production order according the basic start  and finish dates is