How assignmnt finish date is calculated in project plan

We enable Single Entry Mode, protect acutals in our environments, and during our testing, we found that the Finish date of the task is auto re-calculated while the hours input is diffferently from the planned hours. And we have tested with different scenarios:
Fixed Work, Fixed Duration, Fixed Units etc, but we still do not understand the exact calculation logic of the new Finish date.
Does Microsoft have any document descrbing this logic?
Thanks.
Kevin Li

Hi Kevin,
It is normal that the finish date is recalculated by Project. When the team member enter actual work starting later from the start date, after the task update is approved and the project published, Project pushes the actual work, updates the actual start
date then recalculate the finish date based. 
This is actually why you do use a project planning software as Microsoft Project: you want the application to help you forecasting your project dates. If you do not want Project to recalculate, then you miht consider using a simpler tool like Excel.
Basically the process is that the team member gives the information that the task started later than planned, the project manager approves the start date and the actual work. Project calculates the planned finish date. But the last step is very important:
the project manager should review how did MS Project do the recalculation and update the project plan with the remaining work and eventually add or move resources on assignments to adjust the capacity and delivery dates based on priority.
Hope this helps,
Guillaume Rouyre, MBA, MVP, P-Seller |

Similar Messages

  • Why the basic finish date is not adjusted in planned orders

    Hi, all.
    Can anybody help me to understand:
    "Why the basic finish date is not adjusted in planned orders during
    forward scheduling, but in production order basic finish date is adjusted?
    It is look like non-coordination between groups of developers.
    And lead to situation, when planner don't see in MD04 when he can really wait material receipt. He must go to planed order and check production data there, it's unusable."
    Am I right, or SAP have it's own logic.

    Hi,
    Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
    MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

  • How to make the 'Finish Date' field Editable in Project server 2013

    Hi All,
    In Project server 2013 on premises deployment, When I try to create a new enterprise project [Also in case of new custom project type], Only the 'Start Date' field is available. The 'Finish Date' field is by default taking the value of the 'start Date' itself.
    I am unable to make this 'Finish Date' field editable.
    Any pointers on this would be very helpful,
    Thanks
    Shanky

    Shanky --
    When you create a new project in either Microsoft Project Professional or Project Online, the system does not allow you to enter both a Start date and a Finish date for the project.  Here is how the software works:
    You enter the Start date of the project.
    You completely plan the project with tasks, task dependencies, task Durations, and assigning resources to tasks.
    Based on the Start date you provide, plus all of the task information, the software calculates the Finish date of the project for you.  So, you cannot provide both the Start date and the Finish date, nor is they any way to force the system to allow
    you to do this.  Hope this helps.
    Dale A. Howard [MVP]

  • Best Practice for Using Static Data in PDPs or Project Plan

    Hi There,
    I want to make custom reports using PDPs & Project Plan data.
    What is the Best Practice for using "Static/Random Data" (which is not available in MS Project 2013 columns) in PDPs & MS Project 2013?
    Should I add that data in Custom Field (in MS Project 2013) or make PDPs?
    Thanks,
    EPM Consultant
    Noman Sohail

    Hi Dale,
    I have a Project Level custom field "Supervisor Name" that is used for Project Information.
    For the purpose of viewing that "Project Level custom field Data" in
    Project views , I have made Task Level custom field
    "SupName" and used Formula:
    [SupName] = [Supervisor Name]
    That shows Supervisor Name in Schedule.aspx
    ============
    Question: I want that Project Level custom field "Supervisor Name" in
    My Work views (Tasks.aspx).
    The field is enabled in Task.aspx BUT Data is not present / blank column.
    How can I get the data in "My Work views" ?
    Noman Sohail

  • How to pull data from oracle GL to planning

    Hi all
    Can one suggest me how to pull data from oracle GL in to hyperion planning(we are using hyperion planning 9.3 with limited licence for analytic services). i guess we can use HAL ..any thing else
    any help is appreciable
    regards
    M.V

    Hi
    I appreciate for your response. Yep you are exactly right it is data only, but I do have a problem these people have their licence of limited version of Essbase.
    Let me give you the information of their licence agreement.
    The licence for the hyperion planning- sytem9 programs includes a limited use license for both the hyperion Essbase- system 9 and hyperion Financial reporting - system 9 programs. Such limited use license means that the hyperion Essbase- system 9 and Hyperion financial reporting -system 9 programs may only be used to access data from the Hyperion planning -system 9 program.
    Specifically, the hyperion essbase- system 9 program cannot be used to create Essbase cubes that do not contain data used by the Hyperion planning- system 9 program and the Aggregate storage option component of the Hyperion Essbase - system 9 program may not be used.
    1) what it(licence agreement) really means - can you install Essbase, if not how can you create dimensions dynamically using planning.
    2) Is it possible without Essbase as far as I know its not possible
    3) are we going to face any issues with this licence.
    4) Is it possibe to pull data with planning
    I appreciate if any one resolve this issue
    regards
    M.V

  • How to extract data from planning book

    nu t apo. need help regarding how to extract data from planning book givn the planning book name , view name & some key figures.
    Total Demand (Key Figure DMDTO):
    o     Forecast
    o     Sales Order
    o     Distribution Demand (Planned)
    o     Distribution Demand (Confirmed)
    o     Distribution Demand (TLB-Confirmed)
    o     Dependent Demand
    Total Receipts (Key Figure RECTO):
    o     Distribution Receipt (Planned)
    o     Distribution Receipt (Confirmed)
    o     Distribution Receipt (TLB-Confirmed)
    o     In-Transit
    o     Production (Planned)
    o     Production (Confirmed)
    o     Manufacture of Co-Products
    Stock on Hand (Key Figure STOCK):
    o     Stock on Hand (Excluding Blocked stock)
    o     Stock on Hand (Including Blocked stock)
    In-Transit Inventory (Cross-company stock transfers)
    Work-in-progress (Planned orders / Process orders with start date in one period and finish date in another period)
    Production (Planned), Production (Confirmed) and Distribution Receipt elements need to be converted based on Goods Receipt date for projected inventory calculation.

    Hello Debadrita,
    Function Module BAPI_PBSRVAPS_GETDETAIL2 or BAPI_PBSRVAPS_GETDETAIL can help you.
    For BAPI BAPI_PBSRVAPS_GETDETAIL, the parameters are:
    1) PLANNINGBOOK - the name of your planning book
    2) DATA_VIEW - name of your data view
    3) KEY_FIGURE_SELECTION - list of key figures you want to read
    4)  SELECTION - selection parameters which describe the attributes of the data you want to read (e.g. the category or brand). This is basically a list of characteristics and characteristic values.
    BAPI_PBSRVAPS_GETDETAIL2 is very similar to BAPI_PBSRVAPS_GETDETAI but is only available from SCM 4.1 onwards.
    For the complete list of parameters, you can go to transaction SE37, enter the function module names above and check out the documentation.
    Please post again if you have questions.
    Hope this helps.

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • Use Date() for calculation

    Dear sir,
    I want to know how to use Date() for calculation.
    For example:
    int rentday = 7;
    today = new Date();
    I want to add today and rentday to get dueday. I've try to use "dueday=today + rentday", but error.
    Pls help!!! Thanks!!!

    Hi "acos3ltd",
    I think, perhaps, that the "java.util.GregorianCalendar" class may be what you require:
    http://java.sun.com/j2se/1.4.1/docs/api/java/util/GregorianCalendar.html
    and this Web page may also be of help:
    http://java.sun.com/people/linden/faq_b2.html#Date
    Hope it helps.
    Good Luck,
    Avi.

  • The Basic Finish date is a Day earlier than Planned date

    Dear Experts,
    I am getting a strange behaviour about Maintenance order Basic Finish Date when generated from Maintenance Plan. I have Customizing settings (TCode : OPU7) Adjust: "Adjust Basic dates, adjust dep reqmts to order start date" and scheduling type : Backwards in Time. For this setting Order Basic Finish Date is a day earlier than Planned date , but when Schduling type is Backwards instead of Backwards in Time, Basic Finish date is same as Planned date.
    Example: The start of cycle of a monthly plan is 14-Nov-2010, 1st Planned date is 14-Dec-2010. When Scheduling type is " Backwards in time" , the order generated is having Basic Finish Date as 13-Dec-2010 .And when Scheduling type is "Backwards" , Basic finish date is 14-Dec-2010.
    Thank you.
    -Malay-

    Hi there,
    Please check the primilinairy buffer in your strategy package. This field have an effect on your order start date.
    But I agree on Pete, you should use a forward planning.
    Regards,
    Johan
    Edited by: Johan Zeeman on Dec 17, 2010 11:29 AM

  • How to get the finished date of production order

    hi guys
    now i want to get the finished date of production date.  when i search in the table afko , i found the field GLTRI is '0000.00.00'.
    BUT IN the production order display view , the confirm date is '2007.1.1'. so how can i get the confirm date with the production order number? thanks.

    For costing report, you have to read the following tables: based on material Qty/value/ Machine rate and machine posting date , machine rate ( T-code kp26)  and also types of material Raw, finished and semi finished ..
    AFRU ,AFPO,AFKO,AFVV,AFVC,CAUFV FOR PRODUCTION ORDER.
    For material calculation MARA, MSEG and MKPF as well as MAKT...
    Hope this’ll help you .
    Thanks

  • How Production Order finish date and time is being comptued by SAP?

    Hello Expert,
    How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.
    how does SAP compute the time 13:28 as it finished time
    Please explain me briefly.
    Thanks
    Ryan

    Hello Guys,
    When we create Production Order in R/3 the time is calculated by routing but it is extended at SetUp machine time. It is not correct?. SetUp imachines time used only for first Production Order for the same product and it is plan manually, for others Production Order we need calculate time for production without SetUp machine time being pick up to compute finish time. how could we achieve this? only those Machine time will be check.
    thanks

  • MO basic finish date how to compute

    Hi, i create a MO, qty = 42000, basic start date 200/12/01, the system automatic calculation basic finish date 2009/02/19, Can you tell me the basic finish date how to compute?
    our system setting:
    standard margin key = 000
    scheduling type = Forward

    Hi,
        it will consider your processing time if u have made a production order based on standard value & base qty u have given in routing. plz check them.
       In case of Planned order creation generally it will take ur in house production time but if u have maintained base qty & setup time, processing time etc in work scheduling view then it will take finish time according to that & it will not consider in house production time.
    Regards
    Rakesh

  • Update SharePoint list with project finish date on Project.Updated event

    Hello,
    I want to update a column in a SharePoint list with the project finish date when a project is updated on Project Server. My OnUpdated event handler is being called ok, but if I change the project start date Project Server runs an asynchronous republishing
    on the project, and my event handler ends up being called before the finish date is update by the republishing job, so the code writes the "old" finish date on the SharePoint list. The solutions I could think of are:
    Identify the republishing job on Project Server queue, pool the queue waiting for it to finish, then read the finish date and update the list item in SharePoint.
    Include a custom job on Project Server queue after the republishing job, that reads the finish date and update the list item in SharePoint.
    I don't know if any of the solutions are feasible and how to implement them. Has anyone coded something like this and/or have a better solution?
    Thanks,
    GB

    I vote for the option 1.
    I did for one of my event handler..Did you try "on published" event?
                projectSvc.QueueUpdateProject(jobUid, SessionUID, projectDss, false);
                //WaitForQueue(q, jobUid);
                jobUid = Guid.NewGuid();
                projectSvc.QueuePublish(jobUid, e.ProjectGuid, false, string.Empty);
                jobUid = Guid.NewGuid()
    Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management

  • Timeline Start and Finish Dates - how to not display finish dates for tasks not added to timeline

    I have a project, Project 1, with start date 1 Jan 2014 and finish date 31 Dec 2014.  When I switch to timeline view, the timeline spans this period. I now want to create a second view for a sub project within Project 1, called Project 1A.  It
    starts 1 June 2014 and finishes 31 August. I only want to see Project 1A's tasks and time span on this second custom timeline view. I create the new view, add the tasks from Project 1A to the timeline, and save the view as CustomView1A. My problem: CustomView1A
    shows the tasks for Project 1A, but also shows the dead space between 1 Jan 2014 and 1 June 2014, as well as the dead space between 31 August and 31 December.
    I dont want to see the dead space. I want CustomView 1A's timeline to start and finish on Project 1A's start and finish dates.
    How do I adjust CustomView 1A's timeline borders on the left and right to exclude the dead space?
    Hanneliese Fourie

    Dear Sir,
    I checked in CO41 and it allows me to convert planned order to production order and not have any provision to re-scheduling the planned order . Any function to reschedule planned order to future dates ( whose start dates and finish dates are in past ) ?
    Thanks,
    SL

  • Finish Date in the Project Definition / Network Header

    Dear Experts
    When I am creating project through CJ20N, system by default putting current date as finish date. for both project definition and network header.
    How can I make it start date.
    Thanking you.
    Best Regards,
    Abdul.

    Check out your project, is it created before you change these configuration parameters. In normal circumstances, it should work.
    Sorry I misunderstood, if you want system to ask you to put the start date enter scheduling type in both transactions as 'forward scheduling'.
    Regards,
    Mahendra
    Edited by: Mahendra Dighe on Jan 28, 2010 7:02 PM