How can i end the Process chain based on some condition

HI All,
I have a scenario where i have a main pc chain which call  the  new chain at the end which in turn again call pc1. So its more like a closed loop .
pc1-->pc2->pc1
What main chain does is it reads some field value from a dso and assign that to some variable and set some flag to identify that value has been used. My second chain just run the report using the same variables assign by first chain. Now i have to design the main chain such that when all the values have been read from the dso, it should exit and should not trigger 2nd chain. How can i achieve this scenario.
Thanks
Prashant

Hi,
For this try using Process Type-"Decision between multiple Alternatives" in your main chain.It helps you the set condieion based on some formulas
Pls refer links
Decision Between Multiple Alternatives
thanks
nilesh
Edited by: npathak on Aug 11, 2010 1:16 PM

Similar Messages

  • How can u know the process chain total time, individual time?

    Hi guru's
    How can u know the process chain total time, individual time?
    and what options will available in sm37?
    Thanks
    prabha reddy

    Hi Prabha
    Iam not very sure about total time and individual times.
    But you can go to tcode rspcm for monitoring the daily process chains. it gives you details like 1. status  2.start date & time  3. Log ID  of each process chain.
    or you can go to log view of particular individual chain to know how long it has run.
    SM37: tcode for simple job selection.
    here you check the status of job.
    you can select for certain conditions like
    1. scheduled
    2. released
    3. ready
    4.active
    5. cancelled
    Assign points if it was helpful
    Revert back if you need further info/
    regards
    AP

  • How can i understand the Process Chain management in real time!!!

    Hi,
    now i am learning BW concepts. now i would like to know the real time scenarios regarding Process chains. can any body help me in this matter?.
    thanks,
    stikanth.ch

    Hi,
    A process chain is a defined sequence of interdependent processes required to perform acomplex task in an SAPBW environment. Data maintenance tasks in SAPBW are notrestricted to uploading data. Aggregate rollups, index maintenance, master data and ODS activation, and a variety of other jobs are required to update data, guarantee best-possible performance, and maintain data integrity. Typical SAPBW implementa-tions have complex interdependent networks of jobs in place that run every night, week,or month.Previous releases of SAPBW did not provide an integrated solution for scheduling and monitoring those kinds of job networks. This has changed with the introduction of process chains in release 3.0. Process chains allow you to define complex job networks consisting of standard SAPBW jobs, as well as custom jobs; they support visualizing the job network and centrally controlling and monitoring the processes.
    (from "Mastering the SAP BIW")
    New Features in BI 2004s Process Chains
    /people/mallikarjuna.reddy7/blog/2007/02/08/new-features-in-bi-2004s-process-chains
    Designing
    /people/vishvesh.bahirat/blog/2006/11/29/bw-process-chain-design
    Process chain creation in 2004s - step by step
    /people/juergen.noe/blog/2008/01/11/process-chain-creation--step-by-step
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    http://help.sap.com/saphelp_erp2005/helpdata/en/87/13843b74f7be0fe10000000a114084/frameset.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/67/13843b74f7be0fe10000000a114084/content.htm
    Process Chain Errors
    /people/mona.kapur/blog/2008/01/14/process-chain-errors
    Common Process chain errors
    process chain issues or errors
    Try Searching in SDN for this Topic and you will find much detailed info as this is discussed very frequently.
    Hope this helps.
    Thanks,
    JituK

  • How do i export the table data based on some condition for backup

    Is is syntax correct
    exp scott@orcl92 file=emp_29aug.dmp tables=emp
    query=\"where emp_no in (1,2,3,4) \".
    How do i take the backup of more than one table?
    what is the syntax for that
    Thans

    Thanks for your response
    If i want to add more than one condition in the query, then how do i do that
    exp scott/tiger@orcl file=scott.dmp tables=(emp, dept) query=\"where deptno = 30\" and emp_no in (1,2,3,4);
    how do i do that

  • How can we set a process chain to trigger the nodes w/o manual intervention

    SDNers,
    We have a Master PC which has the loading & activation of some Hierarchies.Wats happening is some of the hier activations are failing (we got track of the root cause as well) and the nodes below are not getting triggered automatically, eventhough they have been designed to get triggered irrespective of success or failure of this hierarchy activation. The chain prompts for the u2018Status change & trigger the following eventsu2019 opo-up and only when it was said u2018yesu2019, the subsequent node gets triggered in the chain. If this manual intervention was not there, the Chain gets struck at the activation node, whic is running in yellow status for long, though a short dump - error has already been thrown.
    My query is how can we set a process chain not to anticipate the manual intervention of chnaging the status & trigger events pop-up

    Hi ravi,
    i'm not sure abt the query but what i got thru ur qustion is u have to automtaically go to the next load/step even the proceess chain fails in the step......
    for that we have the same master meta chains with link of so many local chains...for this even if there are some interventions/fails in between the process chains it never gets stopped....
    it goes to the next step and we'll work, analyse and finish the failed load manually....the next day it'll be
    fine...
    b4 to this make sure that there is no dependency for the previous loads....
    And now the solution i found for this is in the process chain design itself.......
    while giving the links itself we'll be getting the options as status RED,GREEN and RED(or)GREEN.....now if u got for the third option the event goes to the next step even it is unsuceesful....
    rgds,
    nkr.

  • How can i find the meta chain name?

    My process chains are running based on meta chain option,So how can i find the meta chain name???

    Hello
    Goto SE16
    Table RSPCCHAIN
    ut u r local chain name as varient and exe
    similerly goback if the chain you get is also a local chain....Until you get only one chain...
    Where Used List --
    RSPCPROCESSLOG table
    You can see the Process Logs at SM37 too based on the Technical name of the Chain you can trace the Meta chian
    Thanks
    Geeta

  • How can we automate the Depreciation keys based on production for business

    How can we automate the Depreciation keys based on production for business u2013 this is currently not an optimised process if we expect business to manually change the keyu2019s on a monthly basis.
    The end user updates the table, transaction AO25, manually on month end after the production calculations are completed. The question is, is it possible when the PP is completed, that the system updates the Period Unit table for that period?
    Thanks.
    Regards,
    PS PS

    Hi,
    I am new at this, so I need a explanation on how will this help me, and how do I get about doing this?
    Thanks a lot.
    Regards,
    PS PS

  • Can we stop the process chain in middle of the process ?

    hi experts,
        Can we stop the process chain in middle of the process after scheduled.
        my process chain is like  start--->load>psa>ods1-->further updates--->ods2. In this case I have already scheduled but i want to stop the process how can i. After rectifying the error I want to restart again.
    if it is possible what are the steps we fallow pl give me step by step procedure.
    thanks & regards.
    venkat

    stopping the process chain is pretty simple. you just need to kill the jobs associated to them as mentioned by other folks.
    for restarting, have a look at this blog.
    Restarting Processchains
    there he explains how to restart a stopped process chain.
    Raghav

  • How can we delete a process chain?

    Dear Ones,
    By Mistake I have converted an infopackage group into process chain in Quality system. How can we delete a process chain?
    Thanks,
    Raj

    Hi Bhanu,
    I've doubt that what is the difference between cancel with core and cancel without core with respect to process chain.
    Could you please advice how do we start a process chain daily without using the schedular window for transaction data.
    Thanks in advance...
    Amarnath.

  • CAN I END THE PROCESS NAMED sapissvc.exe

    Hi
    When I see in the task manager of windows server 2003 it shows that the application named as sapissvc.exe is using more number of CPU's. Can you tell me what is it? And is there any bad effect if i end the process of this application.
    Regards
    Rajneesh

    Hi,
    According to search result, sapissvc.exe belong to a program named Quick Heal Scanner.
    If it is installed and you do not need it any more, it is recommended to uninstall it instead of blocking the process.
    If you have any feedback on our support, please send to [email protected]

  • How can i start the process in the Process Overview?

    Hallo All,
    i make first steps with nw ce and work on a tutorial. But after i have deployed  my model i can't start the process in the process repository becaus the button "Start Process" is hidden, to see here: [screenshot|http://alexshram.al.ohost.de/pub/procRepOverview.jpg]
    Please, can me one explain how i can start my process.
    Thank you in advance!

    Hi Alex,
    The Process Flow and Start Process button are not enabled because you have selected the Task Definition item('Display Name Age') in the Processes and Tasks table. Please select  Process Defintion itme('prcNameAge' ).
    This should resolve your issue.
    Regards,
    Unni

  • How to find out the process chain

    Hi folks
    Hope every one is doing good..!
    in sm37 my job is running (ABAP program) which is in process chain, but i have to find out the process chain name..!
    Could any one help me on this..!

    hi,
      in SM37 select the job status as active and execute it, in the next screen you  will find only active jobs select your job (ABAP Program) click on step - > in th next screen put the cursor on the job -> select Goto option in menu bar click on variant it gives you the field names and desc like chain name, variant etc information.
    Regards
    Sankar

  • How can we automate the process of selective deletion in process chain

    Hi,
    I got to delete data from ODS and InfoCube selectively every Tuesday. So I am aware that there is an ABAP program through which we can automate the process of selective deletion in Process chain. So plz let me know the proceedure to automate this process.

    Hi,
    Try this.
    Need to genrate the deletion program using tcode Delete_Facts.
    steps : 1 run the Delete_Facts tcode and give your cube name in the input parameter
    step2 . select deletion program and execute . you will get the system genarated program
    step 3 copy this prg and save as zprg.
    step4 : run the program with selection
    step 5. if your selection is date then you need to create dynamic varient needs to be populate the value for the date fields
    step 6: you need to maintain the date values in the TVAR table if necessary
    step 7. you need to use this custom prg in your process chain after completion of test
    source : SDN.
    Thanks,
    JituK

  • How do we arrange the Process chain in BI7

    Hi,
    When I tried to create a chain in BI 7 it is not seen in usual 3.x style i.e., process types linked by a link. so  how do I see the chain in the easy way.
    Thank you,
    Prasad

    Hi Jr,
    Yes, I was talking of the tree display. so how can we so that in BI 7
    thank you for the response.

  • How can I display the Process Level by Phase in a Grid or Data Form?

    We are using phased submissions. I can see that changing the display options on a grid will show the current Process Level for the processing unit defined by the POV. But how can we break this down by phase?

    Try what is suggested in Page 243 of the User's Guide:
    You can display multiple submission phases, view review level status, and perform process management actions for multiple phases in Process Control.
    If you select Single period view, you can select one or more submission phases to include in the columns. For each column, you can display one or more of these options: Calculation Status, Journals, Review Level, Pass/Fail, and Validation. If selected, Review Level, Pass/Fail, and Validation are included for each phase. Since Calculation Status and Journals apply to the entire processing unit, they are displayed only once regardless of how many phases are selected. If you select All period view, you can select Calculation Status or Review Level information for the columns. If you select Review Level information, you should select one submission phase
    for display. When you select All periods, or Tree for the display, the filter option is unavailable.
    Here is the options:
    !http://0ue0ag.blu.livefilestore.com/y1pceBZ2nCvU8wYKj38bzK_O3B8eXo5XwfxwTkVeMdPu1fi6lHT_DcYrxlptGHYDm6N4lA0H2YMnWx4qtcOe4ttmM-Em-fheg5P/Phase%20Submission.jpg!
    And the Result:
    !http://0ue0ag.blu.livefilestore.com/y1pWfMkCFrViEuCRyAHWCphl7y0gZBAK3UY1f2ECi1kme3_xP2FQjyG5f4TC7QHwoHPxBSb0GTKpyU6TXMSp9P5wR5LbJeYl5eu/Phase%20Submission2.jpg!

Maybe you are looking for