How PO validity start and validity end works

In the PO Header (tab Additional data), there are fields: validity start and validity end.  The help text states the following:
Start of validity period
Date as of which services can be performed or materials delivered.
In the case of purchase orders:
Start of the period in which the service is to be performed or thematerial delivered.
End of validity period
Date up to which services can be performed or materials delivered.
In the case of POs:
End of the period in which the service is to be performed or thematerial delivered.
I maintained a validity date range 01/01/2007 to 01/10/2007.  When i tried to receive the item with posting date 01/15/2007, the system saved the GR without even a warning message that the GR was outside the PO validity date.
How does this field work?  Is this standard configuration or does this only work with a user-exit?
I would appreciate any input.
Regards,
Dominique

hi ,
use transaction OMCQ,
set the status of message for M7 163 to error. if this message is not present in the list , then go to new entries and select  this message and enter it into the list
after this set the status to "E".
let me know if this works
Regards
Mangesh.

Similar Messages

  • Validity start and Validity End date in PO

    HI  gurus
       can you plz tell me how to activate  validity start and Validity End date in PO
    Neha

    Hi,
    It is applicable for PO done for Frame work oder with Doc type - FO(Frame work order)as its an agreement of supply of stock only between specified period.For this kind of Doc type system makes it mandatory to enter the valisity start and end date.
    Thanks

  • Add Validity Start and Validity End On PO Header

    Dear SAP,
    need your help, I am trying to add Validity Start and Validity End Field on Additional Tab in Purchase Order header.
    How do i add this field ?
    i already check on MM define screen layout a document level, but there is not setting for this two field.

    Hi Nizam,
    The validity start date & end date are used only for service orders. In configuration goto IMG>MM>Purchasing>PO>Define screen layout at document level and check into Administrative data, header of ME21N , the field selection key attached to your document type (Say NBF) and for field selection key AKTH.
    The fields Start of validity period & Validity period end of field selection key ME21N, NBF & AKTH should be set as optional then only required fields will be visible on screen.

  • How to input my own Validity Start and End Dates in ME21N

    Hi All,
    I have to change the Validity Start and Validity End date in Addiitional Data Tab of ME21 transaction( PO Create ) using default Customer Values.How Can i accomplish it?
    I have used the BAdI ME_PROCESS_PO_CUST and implemented it, I have coded in the method PROCESS_HEADER.First I retrieved the data using get_data( ) method, changed the values with Customer Values and called the method set_data( ).
    However my validity start and End Dates and not changing.
    Even in ME21N if I create the PO with my own Validity Start and End dates, and go to ME23N to display the created PO, still in the additional data tab, the start and End dates are current date and Next date respectively.why its happening?
    Thanks in advance

    Hi,
    Can you please let us know in which business scenario this is required.
    SAP has provided separate functionality of Outline Agreement for considering validity period.
    If you let us know the business scenarion some solution/workaround can be suggested.
    Regards

  • How to change Validity Start and end dates on a lane ?

    Hi,
    I am trying to change Validity start and end dates on a lane for a product specific assignment.
    What I see is as follows
    1) Lane created by system /others I can delete and give the required start /end date ?
    I want to know if I can change the end date without deleting the lane as its tough to delete a lane in production.
    Thanks
    -Venky.

    Hi,
    we can change the start period and end period in the Transportation lane using the table /SAPAPO/TRPROD.
    And then using the update command you can change the start time and end time of the product.
    Regards,
    Hyma.

  • Report for Validity Start and End Date in PO

    Dear All
    Is there any report where I can get PO validity start and end date which user input in addtional data header tab of PO?
    Regards
    Satish Kumar

    Hi,
    Yes, It is available standard report using T-code ME2N - Purchasing Document (PO) Per Document Number, enter the T-code and provide the following input data's are as follows.
    Scope of List                 :  ALV ( for Ms-Excel format report)
    Plant                               :   __________ to __________ (if required)
    Document Date              : ____________ to ___________ (if Required)
    Execute the report shown by default in excel format and if required PO validity start and end data, you have to select Change Layout button and open new window options screen right side field option as Validity Per.Start, Validity Period End, Commutative number field data's are selected and click <--- arrow button and then click bottom tick marked button. Now, the report shown your requirement.
    Hope, it is useful for you,
    Regards,
    K.Rajendran

  • How to create the verify.der file in portal ? valid to and valid from

    hi Experts,
    am facing the problem in SAP logon method without user mapping but it's having a problem, The problem is  create the Transaction iview it's not there . Back end server is not response how to create the Valid TO and Valid From in portal.
    Thanks & Regards
    Chandu

    Chandu,
           1.      Start the SAP J2EE Engine Visual Administrator: C:\usr\sap\<SID>\JC00\j2ee\admin\go.bat.
           2.      Navigate in the left tree panel to Cluster -Server -Services -Key Storage - Runtime  TicketKeystore - SAPLogonTicketKeypair u2013cert.
    Here you can go ahead and create a new ticket.
    Hope that helps.
    Cheers,
    Sandeep Tudumu

  • How are valid-from and valid-to dates set in TRPROD table in APO during CIF

    First question:
    How are the valid-from and valid-to dates set in the APO TRPROD table?
    For example, if I activate a transportaion lane model on March 1, 2008, will the valid-from and valid-to in TRPROD be 20080301 and 99991231?
    Or are these dates defined in the model itself? Or in APO config somewhere?
    Next question:
    Suppose I rerun the model on May 1 2008 to add some records that didn't get added in the March 1 run.  But suppose I want to back-date the valid-from of these records to March 1, rather than use May 1 as the valid-from.
    Can this be done?
    Or is the valid-from always the date of the CIF that creates the TRPROD records?
    Please advise. 
    Thanks

    Hi Srinivas -
    Thanks very much for replying so quickly, but your response didn't answer the questions.
    Let me try again.
    1)
    If I run a CIF on March 1 2008 based on a model that will generate APO TLane data, will the TRPROD valid-from and valid-to get automatically set to 20080301 and 99991231?
    2) 
    If the answer to this question is yes, then is it also true that if I run a new set of records in on May 1, 2008 (no duplications with the original set), then the valid-from and valid-to dates will be 20080501 and 99991231.
    3)
    But if (1) and (2) are both true (if you answer them both "yes", then suppose I want the May 1 record set to have valid-from dates of March 1 (for example, if the May 1 record set includes records that didn't get included in the March 1 set due to an error in selection criteria).  How do I get the valid-from to be March 1 when I run the CIF on May 1?
    On the other hand, if (1) and (2) are NOT true, then how DO the two dates get set during a CIF ????
    Thanks
    djh

  • How to pass Valid from and Valid to Dates in CS_BOM_EXPLOSION

    Hii Experts,
    My requirement is to explode BOM using CMC LDB and generating files for all the remaining months by varying Valid from and Valid to dates. For this I am using CS_BOM_EXPLOSION but it has provision for a single date field.
    Can you please guide me how to pass both Valid from and Valid to dates in CS_BOM_EXPLOSION ? And if you can suggest any other alternative, its most welcome...
    Regards,
    Vikas

    Hi Vikas,
    There is a tables parameter STBP which is of type CSXGEN.
    This structure CSXGEN contains two fields valid from date(DATUV) and valid to date(DATUB).
    Is this what something you are looking for?
    Regards,
    Swarna Munukoti

  • How to retrieve start and end date values from sharepoint 2013

    Hi,
    How to retrieve start and end date values from new event form of calendar in SharePoint foundation2013
    Thanks
    Gowri Balaguru

    Hi Srini
    Yes i need to have parallel flow for both and in the cube where my reporting will be on monthly basis i need to read these 2 master data and get the required attributes ( considering last/first day of that month as per the requirement).......but i am just wondering this is common scenario....while there are so many threads written for populating 0employee from 0person......don't they have such requirement.....
    Thanks
    Tripple k

  • How to change dateformat of VALID FROM and VALID TO properties in xml forms

    Hi all,
                I have created a news using xml form bulider and i have given lifetime for that news ,also displaying the VALID FROM and VALID TO  in news.By default it is in mm.dd.yyyy format but i need to display the dateformat as dd.mm.yyyy in show form.Is there any possiblity to change the format in XSLT or any other solutions.
    Regards
    Bala

    Hi Bala
    Check this XML FORMS - Date Format.
    Its a quite easy way.
    Regards
    BP

  • Send email notification in latest start and latest end

    Hi all,
    My requirement is to send email notification on latest start and latest end. For latest start, a notification needs to be sent to the manager asking him to start processing the Leave request.
    Am not too concerned about the latest end, since the latest end takes the workitem(MODELED ACtion)  to the next manager, where I can insert a email step in the workflow.
    My concern is how can i send an email to the manager if he has not started processing the lave request within say 3 days
    thanks a ton.
    regards

    Hi,
      If you are looking to send notification ASA work item reaches a latest end then follow the below steps.
    1. Open the step for which you have set the latest end and click latest end tab.
    2. Under the same tab you will find a Drop down box you will find two entries 1 Display Text 2 Modeled  choose the 1 option. and define the text in the task description by choosing Latest End description.
    3. Choose the container element you might have populated the email address.
    Now the configuration that you need to make sure to send a mail to external email id is SCOT settings if SMTP node is configured  then this node would be sending mails to the
    Regards
    Pavan

  • Valid from and valid to properties under history preservation transform

    I have created_dt and last_updated both date columns in source table and also in target table.
    Now under history preservation transform for Date columns:
    For "Valid from" and "valid to" properties: which column should i pick?
    how can i use created_dt and last_updated columns under history preservation?
    What is current flag property, should i leave this blank if i don't have any flag "bit type" column like indicator in source or target table.
    My Dataflow has:
    Source_table -> Qry_Transform -> Table_comparison > history_preservation - > Key_gen - > Target_table.

    Valid from and Valid to in History Preservation transform deals with SCD (slowly changing dimensions).
    In most of the scenarios, Valid From comes from the source (as Effective From date) for which the dimension has a particular value.
    Eg:
    SALES REP, Region, Effective From
    A, California, 01.01.2011
    Valid To column in History Preservation is the default value that you provide inside. In case of preserving history of an update, Valid To column of the old record can have the Valid From value of the new record, or one day before that. You have option to set the same in History Preservation.

  • Date entered between valid from and valid to it should throw error

    HI  i have a doubt in the dates see
    i have a column for the valid  from and valid to date
    EXAMPLE
    customer  cform NO                 SUBMITTED               VALID FROM            VALID TO         uSER
    17     OUIIUYUIY     02.04.2008     03.04.2008     03.12.2008    SAB_BEGUM
    WHEN I GIVE  the dates in between the period it has to give throw the error
    example if i give like as shown below it should pass the error
    17      FHGFF2                   02.04.2008                     03.04.2008              03.06.2008         SAB_BEGUM
    now how can i pass and check the the dates, it has to accept ones the date is after 04.12.2008 , in between the period it should throw the error. please help me out

    have a look at this:
    http://help.sap.com/saphelp_nw70/helpdata/EN/a7/5139ef407a11d1893b0000e8323c4f/frameset.htm
    and search for the pre defined events in table maintenance dialog.
    generate table maintenance->create a maintenance dialog->Maintaining and changing an existing maintenance dialog ->Extended Table Maintenance Events.

  • Shipment completion check is erasing load start and load end dates & times

    Once the load start, load end is clicked during the pack process, the system reads this just fine.  Once ship complete happens, the system is erasing the load start load end.
    We are capturing the difference between Load end and Load start as Packing time in a custom report.  Similarly the difference between Shipment end and Shipment start as Loading time.  But we post goods issue the delivery by ship complete button the dates and times are gone.  Any idea of how and where I can configure this not to disappear even after the ship complete.  Thank you.

    Have you checked the table VTTK with different fields before completing PGI? In other words you are wiping out the loading start and loading end details some how. You should have a value in your VTTk value before PGI.  Check that.
    Regards,

Maybe you are looking for

  • Error in retrieving and parsing XML File

    Hi Folks I am Working on People centric user interface, While i am custimizing a application in Business application Builder i am getting this error " Error in retrieving and parsing XML File " can any body look on this and give me the solution it wi

  • How do I get a photo from a video in iMovie?

    how do I get a photo from a video in iMovie?

  • Mail not opening or closing correctly

    In the process of trying to configure my mail to gmail, I have done something wrong. Now when I click on mail a completely different icon appears. I can not go to preferences (or anywhere else). It will not shut down by itself. I have to use force qu

  • Cookie in LOV

    Hi All, I want to create a LOV with a cookie value in the where clause. How can I do it? -Vatsa

  • Smartform convert DINA4 to LETTER format

    hi expert, In my smartform i change the paper format DINA4 to LETTER format. Once i change the format into LETTER i adjusted the heights of window as per as LETTER formate sizes. Here the problem i am facing that the header and fotter titles or descr