How schedule line qty got changed?

Hi,
we observed there is a change in schedule line quantity. We have checked the change log in statistics but there is no record of change. We also checked in CDPOS for change record but there also there is no change record.
As there is Firm zone maintained and the date is with in firm zone, i am not sure MRP run resulted in Schedule line Quantity change.
Please suggest me how can i investigate who and how the quantity got changed.
Thanks,
Raghu

Dear,
Check this similar link: http://www.sapfans.com/forums/viewtopic.php?f=6&t=71921&start=0&st=0&sk=t&sd=a
Hope this will helpful.
Regards,
Syed Hussain.

Similar Messages

  • Scheduling Line qty greater than the Scheduling agreement qty

    Hi Experts,
    1. I have a scheduling Agreement (SA), and the qty mentioned against this SA is 1000 (say).
    2. Now when i generate schedule lines for this SA (ME38), I am allowed to schedule more than the quantity that's mentioned in the SA.
    3. Please advise, is it possible to restrict this behaviour. i.e. I want to give an error message if the Schedule Line qty exceeds the SA qty.
    Please advise. Very urgent.
    Regards,
    Manju.

    Hi Manju,
    Yes its possible to restrict the case as u mentioned.
    Check the below settings:
    IMG-MM-Purchasing-Environment data- Define Attributes for system messages
    go to meassage no : 00-06-067 set it as Error message.
    U'll achieve ur result.
    Award points if its helpful
    Sangram

  • How Schedule  line date is determmined

    Hi Experts,
    In my present issue i want to understand how schedule line date is determined for a document
    bcoz schedule date is for each item in a document but  not at document level
    Please Help
    Thanks in Advance ,
    Nitya

    Hi
    Thank you for your reply
    My question was wrong hence closing
    Thanks,
    Nitya

  • Schedule target qty is less than schedule line qty.....

    hi,
    please tell me can i avoid users to not to give schedule line qty more than target qty.....
    is it possible.....

    Hi friend,
    yes it can be possible.....
    there is a message for it,it may be a warning in your case.... just turn it to error,
    Go to spro--->Material management>Purchasing->Environment data--->define message systems...
    Go here select your message....it may be  some thing like M06xx
    select the message and turn it to error......
    Now while the user will crete a schedule line in Me38  he will not be able to create schedule line ....
    Hope it is usefull.....

  • Schedule line qty

    Hi,
    In sales order, scheduling line tab, the confirmed qty is reqd else it gives error at delivery creation.
    Client wants that it shall input qty only once. How can it be done?
    Also whats the concept of scheduling lines (apart from help.sap)
    regards
    Shruti

    Dear Shruti,
    You will be able to create delivery for only conformed quatity of the schedulelines and on specific conformed date only.
    Schedulelines will get conformed based on the availability of the material.
    If there is no stock at present scheduleline will get conformed in the future date based on the replenishment lead time(time will to produce the material or to procure the material).
    In scheduleline conformation process scheduleline categories will place a role.
    Scheduleline categories determination will takes place based on these combination
    Itemcategory+MRP type--->Scheduleline category
    While creating sales order availability check will takes place based on this scheduleline will get conformed.
    For example you have created sales for 100qty but only 50 qty avaialble at present for this system will conform 50 qty on present date remaining 50 qty will conform in the future date.
    Suppose if you got the stock before that future date you can do the reavailability chek (by clciking on Availability check icon)to confrom the remaining 50 qty on earlier date.
    I hope this will clear for you,
    Regards,
    Murali.

  • Delivery dates in schedule lines is not changing in sales order

    Dear all,
    delivery dates in schedule lines on line item in sales order is not changing.delivery dates are different in schedule line of partial qtys.i have to do same delivery date on all schedule lines.
    Regards,
    Praveen

    Hi Praveen
    1. Schedule Line dates can be changed manually or by doing an availability check only.
    2. In case if you change the delivery date in the header it will not change automatically in the line item level.
    3. You need to do it manually only.
    kindly let me know more details.
    reg
    dsk

  • Schedule line delivery dates change in VA01

    Experts,
    User is adding some days for a material in maintenance table and it is like below.
    Material Days Plant
    2525252 100 ABCD
    3636363 150 PQRS
    The requirement is --
    While creating sales orders or changing sales orders(VA01 or VA02) while adding this material(2525252)in the line item - In schedule line items Delivery date should changed (some thing like get added 100days)
    I have added my logic in routine RV03VFZZ. But some materials are not getting changed due to avilability check.
    How can i bypass availability check ?
    (tried in USEREXIT_MOVE_FIELD_TO_VBEP... but no use).
    Thanks,
    Priya

    Take a look an ATP00001 in SMOD. However, this looks to me as a classic case when we're trying to use ABAP to compensate for poor functional choices or an incorrect business process. I find it hard to believe this cannot be done by other means than such funky ABAP.

  • Re : schedule line item date change

    HI
        How to change schedule line item date. Default 5 days inadvance its coming. i want to change that into 8 days.
    thanks
    mani

    Hi,
    Please go to t-code VOV8,select your s.doc type and double click it.Pl check no of days in "Requested delivery date/pricing date/PO date" -Lead time in days.
    If it is 5,change it to 8.
    Schedule line date is also determined after system carry out availability check.
    thanks,
    vrajesh

  • Schedule lines should not change 3 weeks time from MRP date

    Hi
    Is there any specific customisation required to get following results in case of schedule lines.
    1) MRP should not change/adjust the already send delivery schedule lines  which are lying within 3 weeks time from MRP date
    2) System should not allow to book the GRN unless the messages / print out has been generated from the system in case of scheduling agreement.
    Thanking you
    Shantakumar
    09944009752

    Hi,
    There are 2 possibilities:
         1. use MRP fixing using planning time fences, this is done by putting the relevant settings in the MRP1 view of the material master
         2. use the firming options of the scheduling agreement, these are set per material number that is entered in the scheduling agreement.
    The GR can only be posted for schedule lines that have been processed aka output generated.
    Regards,

  • Mass Delete of Schedule Lines generated through changes in prod Schedule

    Hi friends,
    Kindly provide me the process of mass deleting schedule lines which are created through changes in Production Schedule in the month end.
    Regards,
    Ask

    Hi,
    Try T.code Me17
    thanks
    Rakesh

  • Schedule Line Date Showing in future in Sales Order though the Stock is available in system on same date

    Hello All,
    Good Morning,
    We have received an Incident where in the Sales Order during the ATP Check we do user is getting the future schedule line date in future as enclosed in the screen shot below. User has created the Sales Order on 12052014 for 7 line items. For the Line Item 7 the Stock is available in the system on same day but still after ATP Check the date is shown in future.
    I wan to replicate the scenario in Quality to find the exact bug to fix the Issue but not able to replicate for same customer and material i am getting the current date as confirmed delivery date. please guide me if you can share some inputs so that i can go in right direct and fix the issue.
    Please respond it is critical Issue.
    Thanks,
    Farhan.

    Hello All Experts,
    Many Thanks for all the Inputs you have given.
    Finally we have replicated the Issue in Quality 2 Days Back and Indeed it was great Achievement.
    Finally We have given to Abaper to debug it find the root cause.
    Let me summarise the actual Issue.
    Issue : Sales Order Schedule Line showing future date for the Materials which are having Product Allocation even though the Stock is available and Allocation Qty also available in the PA Master Data we maintained..
    We created one Sales Order for Line Item A and B. Line Item A is having Product Allocation. When we created Sales Order for both Line Item A and B we got Schedule Line Date as 13.06.2014. Then we Schedule the Re-Scheduling Job in V_V2 and check the effect. For Line Item A the Schedule Line Date got changed to 01.07.2014 and Line Item B it was same as before.
    Would like to know is there any config setting at Schedule Line Level we have missed just want to cross check if there is any or something in Product Allocation Configuration.
    Please refer screen shots below for more details of Sales Order before and after effect in Re-Scheduling.
    Please provide your inputs on this.
    Thanks,
    Farhan.

  • Delivery qty against schedule line

    Hi,
    I have specific requirement for a report where we need to determine the delivery qty against the schedule line qty for a sales order. In sales order in schedule line tab system shows the delivery qty. The field is VBEPD-VSMNG. VBEPD is a structure and I could not find the table in which this is actually stored. Does anybody know how to get the delivery qty for schedule line?
    Regards,
    Sachin.

    Dear Sachin,
    the delivery is always created in the ERP system on the item level. You cannot deliver a separate schedule line. This functionality does not exist.
    But if you go to the schedule line screen then the delivered quantity of the item will be distributed through all schedule lines which have the confirmed quantity. The distribution takes place starting from the earlier schedule line and goes to the later schedule lines and the delivered quantity ordered to a schedule line must be always not larger that the confirned quantity. If there will be undistributed rest of delivered quantity, it will be ordered to the last schedule line.
    This distribution takes place dynamically during the transaction VA02. The main program place here is the function module RV_SCHEDULE_CHECK_DELIVERIES.
    I hope, this information helps you further.
    Kind regards,
    Akmal Vakhidov
    Development Support SAP, Walldorf/Germany

  • How to get the Deliver Quantity against Schedule Line Quantity

    Hi,
    I have specific requirement for a report where we need to determine the delivery qty against the schedule line qty for a sales order. In sales order in schedule line tab system shows the delivery qty. The field is VBEPD-VSMNG. VBEPD is a structure and I could not find the table in which this is actually stored. Does anybody know how to get the delivery qty for schedule line?

    Hi,
    U can check the following tables:
    VBEP (Sales ScheduleLines) VBEP-VBELN =VBAP-VBELN and VBAP-POSNR = VBEP-POSNR
    LIPS (SalesDoc:Delivery Items) LIPS-VGBEL =VBAP-VBELN and LIPS-VGPOS =
    VBAP-POSNR
    VBEH (Schedule LineHistory) VBELN POSNR ETENR
    Regards
    Kannaiah

  • How system updating the delivery dates in sale order schedule line

    Hello
    i created a sales order with 2 line items. For the first line item the confirmed delivery date in the schedule line is 06.02.2012 and for the second line item the confirmed delivery date in the schedule line is 14.02.2012 . Both the line items are third party items and the PR created against the line items in the sales order .
    We created the PO with reference to the PR of the SO and we find there are different delivery dates coming in the PO document for the 2 line items . For the first line item the delivery date is coming as 14.11.2011 and for the second line item in the PO , the delivery date coming as 11.11.2011 . Firstly we are not understanding from where the delivery dates are picking in the PO.
    Secondly , once we saved the Purchase order and once we come back to the sales order , the schedule line dates are getting changed automatically in the sales order . For the first line item in the sales order the delivery date is changing to 22.11.2011 and for the second line item in the sales order the delivery date is changing to 22.11.2011.
    Now my question , is from where the delivery dates are updating in the Purchase order and once we save the purchase order how the delivery dates in the schedule line are getting changed .

    Now my question , is from where the delivery dates are updating in the Purchase order and once we save the purchase order how the delivery dates in the schedule line are getting changed .
    For third party processing, the delivery dates are updated in the purchase order based on the settings in the field Planned delivery time in the MRP2 view of the material master(defined in purchase info record in t.code ME11/ME12) and purchasing processing time defined in t.code OMEW. This means, since the date of PO created, it will take the days mentioned in the planned delivery time field and purchasing processing times to determine the delivery date, which will be copied into the sales order as delivery date. In your case, the purchase order delivery date is not copied into the sales order, hence you may need to check OSS note. How the PO is handled? Any confirmation control functionality is used?
    Regards,

  • Change schedule lines using bapi salesorder_change

    Hello,
    I am using 'SD_SALESDOCUMENT_CHANGE' to change sales order. schedule lines are not changed.
    I get an express inbox message saying :
    ===================================================================
    Update was terminated
    Error Info...   00 671: ABAP/4 processor: SAPSQL_ARRAY_INSERT_DUPREC
    ======================================================================
    I don't know what to do.
    any body solved this problem? what is wrong in the way I wrote it?
    Thanks in advanced ,
    Sara
    I populate schedule lines this way:
          lv_schedule-itm_number = svbap-posnr.
          lv_schedule-sched_line = '0001'.
         lv_schedule-req_qty    = svbap-kwmeng.
          lv_schedule-req_date   = im_vbak-vdatu.
          move im_vbak-vdatu to: lv_schedule-tp_date,
                                 lv_schedule-ms_date,
                                 lv_schedule-load_date,
                                 lv_schedule-gi_date.
          append lv_schedule to et_schedule.
      * schedule lines X
          lv_schedulex-itm_number = svbap-posnr.
          lv_schedulex-sched_line = '0001'.
          lv_schedulex-updateflag = 'U'.
          lv_schedulex-req_qty    = 'X'.
          lv_schedulex-req_date   = 'X'.
          move 'X' to: lv_schedulex-tp_date,
                      lv_schedulex-ms_date,
                      lv_schedulex-load_date,
                      lv_schedulex-gi_date.
          append lv_schedulex to et_schedulex.

    Hi,
    The function I use is the one used in the BAPI CHANGE.
    Online changing the delivery date changes the date in the schedule lines.
    I can't understand why it is not updated.
    Sara