How the prodution order start and finis dates are changeing...?

Dear friends,
It was observed that one of my client's production order start and finish dates are changing frequently.
No user is claiming the responsibility, I feel very dificult to to find out who did the changes.
When I  observed, it is happening for orders if we Revert the Teco, and that to for those orders which doesn't have the sale order assignment.
and some times it is not happenign for  even for the orders which does not have the sale order assignment also.
Here it is having Forward type Sheduling.
Please help me how and when , the prodcuction orders start and finish dates will get changed.

Dear RS,
Plz check in AUT10, by giving t-code CO02 for order changes
in AUT10, u can track user id also
this may help you to some extent
Regards
kumar
Edited by: kumar kumar on Sep 17, 2009 8:32 AM

Similar Messages

  • SNP Planned order start and end dates are not calculated correctly

    Hello SNP Guru's
    The SNP planned orders generated after the Heuristics run, have a start and end date based on the Activity Duration (Fixed), while the resource consumption is based on the Bucket Consumption (Variable), which is correct.
    The Activity Duration (Fixed) is based on the BOM Base Quantity. So if the Activity Duration = 1 day, and if the order quantity is more than a day, the start and end dates, still shows as 1 day. So no matter what is the order quantity, the start and end dates is always = 1 day.
    Does anyone have any experience in implementing any code to change the start and end dates on SNP Planned Order?
    Seems like it should work as standard.
    Am i missing something?
    Thanks,
    Mangesh

    Dear Mangesh,
    SNP is a infinite planning tool. If you have defined fixed duration to be 1 DAY in the activity, no matter how many quantity you input for your planned order, the order will last for one day. If the resourced is overloaded, you then run capacity levelling to
    banlance the capacity. What your expected beahavior happens in PPDS planning.
    Claire

  • How to cancel the sales order - header and line status are in Entered Stage

    Dears,
    I have some sales order to be cancelled in which the header and line status are in *"Entered"*. I am not able to cancel these sales order.
    Also note that these orders are for maintenance service.Once i book these orders the lines will change to closed status.
    So it is not possible to book and cancel the lines.
    Kindly me to resolve this.

    926530 wrote:
    Boss,
    If i do Action-->cancel on header, it just makes the qty to zero.But the header and line status still showing as entered.It will not cancel the order.
    The problem for me is that these lines are coming in my monthly reports. This is what your question says...be more specific as what is your issue..which in turn is your problem
    How to cancel the sales order - header and line status are in Entered Stage
    Coming to your Action-->cancel...as far as i know ...the header status will change to canceled..
    unless until you have some processing constraints in place...which is stopping you...
    HTH
    Mahendra

  • Generate all the quarters between start and end dates

    Hello all,
    I have a query in which i have two dates that is Start Date and End Date and now i have to populates all the quarters date between the date range:
    For eg:
    Start Date : 1-Apr-2011
    End Date: 1-Jul-2012
    Now taking these two values i want the recors as displayed below
    Apr 2011
    Jul 2011
    Oct 2011
    Jan 2012
    Apr 2012
    Jul 2012
    So how can write my PL/SQL query to accomplish this task
    Thanks in advance

    958964 wrote:
    Hello all,
    I have a query in which i have two dates that is Start Date and End Date and now i have to populates all the quarters date between the date range:
    For eg:
    Start Date : 1-Apr-2011
    End Date: 1-Jul-2012
    Now taking these two values i want the recors as displayed below
    Apr 2011
    Jul 2011
    Oct 2011
    Jan 2012
    Apr 2012
    Jul 2012
    So how can write my PL/SQL query to accomplish this task
    Thanks in advanceHow do I ask a question on the forums?
    SQL and PL/SQL FAQ
    solution can be done in SQL only; no PL/SQL.

  • How to set up start and end dates for validity of contract account in FICAx

    Hi,
      Can anyone tell me where can I set up the validitiy period for the contract account in FICA. In contract creation, I could just see the contract validity start date. I also need to know the validity end date. Please let me know the solution asap.
    Points will be awarded for all the useful answers.
    Thanks
    Santosh

    Yes, you're right, you would then need to develop a lot of user exits to prevent the re-use of the contract account after the validity date.
    I'm think in a strange solution, it could work but you'll need to test it. if a contract account is marked for deletion (Field FKKVKP-LOEVM equal to 'X') no further action can be made over it, When you create you contract account you can schedule a change using as validity date (Field BUS000FLDS-VALDT ins the change contract account screen) to the end date of you contract account and set this deletion flag. then you run FPP2A to activate the schedule changes, before you get to the end date the flag is not set, when you get to the end date FPP2A will activate the flag and the contract account becomes not usefull.
    If you do this, you have be careful because all the postings to the contract account won't be possible, it means that if there are payment to be made, interests to be calculated, etc... nothing will be posted.
    Cheers,

  • Accessing an Apple account when the e-mail address and birth date are incorrect??

    In updating to IOS yesterday I have stupidly ended up with three Apple accounts (It said I needed one with an e-mail address, there was my cloud account and my account I have used for years to purchase)
    I basically messed up and thought I could create a fresh account with my e-mail address and still cotinue to download updates for my previous purchases.
    Somehow my old Apple account that I bought all my apps on has become disconnected from my e-mail address and has the wrong date of birth - i threfore can't get in to the account or reset the password... is there a number I can call??
    Rspence234

    Good luck with this!!!
    EVEN USING what WAS my Username, this is the exact problem I am having having entered my correct ID and Password.
    Rgds
    Rod

  • What parameters determine Planned order production start and end dates?

    Greetings
    We are using the graphical planning table @ MF50 to firm Planned Orders (Basically checking off "Firm Order" field within the Planned Order). We are on ECC 6.0
    Whenever I backflush, the production start and end dates get overwritten (The Basic dates do not change).
    I would like to prevent this. Can someone advise me on what parameter controls how the production start and end dates getting changed?
    Thank you
    Hanarin

    Hi,
    Calculating production dates ( Lead time scheduling) are explained in detail in the SAP help URL as below:
    If "Automatci Scheduling indicator" is set in the customizing for scheduling parameters then after every change relevant to scheduling, the production order is also automatically rescheduled before saving.
    You need to check these settings.
    regards
    Datta

  • How to determine current period start and end dates

    Hi All,
    If given previous period start date and end date, how to determine current period start date and end date?
    Suppose if given previous period start and end dates are 12/28/08 - 01/30/09, then current period start date and end date will be 01/30/09 - 02/27/09. (where 12 is the previous period, 28 is the day, 08 is the year......)
    Can you please suggest an FM to determine the current period dates?
    Thanks & Regards
    Gowthami

    >
    gowthami karunya wrote:
    > If given previous period start date and end date, how to determine current period start date and end date?
    > Suppose if given previous period start and end dates are 12/28/08 - 01/30/09, then current period start date and end date will be 01/30/09 - 02/27/09. (where 12 is the previous period, 28 is the day, 08 is the year......)
    Hello,
    I am assuming you have the Company Code with you & proposing this solution.
    TABLES: bkpf.
    PARAMETERS:
    p_bukrs TYPE bukrs.
    SELECT-OPTIONS:
    s_date FOR bkpf-budat.
    DATA :
    l_perio LIKE bkpf-monat,
    l_poper TYPE poper,
    l_year  LIKE bkpf-gjahr,
    l_spmon TYPE spmon,
    l_periv TYPE periv,
    l_date1 TYPE datum,
    l_date2 TYPE datum.
    CALL FUNCTION 'BAPI_COMPANYCODE_GET_PERIOD'
      EXPORTING
        companycodeid = p_bukrs
        posting_date  = s_date-high
      IMPORTING
        fiscal_year   = l_year
        fiscal_period = l_perio.
    CONCATENATE l_year l_perio INTO l_spmon.
    * Get the next period
    IF l_perio < 12.
      l_perio = l_perio + 1.
    ELSE.
      l_perio = '01'.
      l_year = l_year + 1.
    ENDIF.
    MOVE l_perio TO l_poper.
    SELECT SINGLE periv INTO l_periv
    FROM t001
    WHERE bukrs = p_bukrs.
    IF sy-subrc = 0.
      CALL FUNCTION 'FIRST_DAY_IN_PERIOD_GET'
        EXPORTING
          i_gjahr        = l_year
          i_periv        = l_periv
          i_poper        = l_poper
        IMPORTING
          e_date         = l_date1
        EXCEPTIONS
          input_false    = 1
          t009_notfound  = 2
          t009b_notfound = 3
          OTHERS         = 4.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
      CALL FUNCTION 'LAST_DAY_IN_PERIOD_GET'
        EXPORTING
          i_gjahr        = l_year
          i_periv        = l_periv
          i_poper        = l_poper
        IMPORTING
          e_date         = l_date2
        EXCEPTIONS
          input_false    = 1
          t009_notfound  = 2
          t009b_notfound = 3
          OTHERS         = 4.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
      WRITE: / l_date1, l_date2.
    ENDIF.

  • Basic start and finish dates vs scheduled start and finish dates in work order

    Hi Friends,
    I have observed  that whenever releasing the work order,irresepective of number of operations in the work order, system generating scheduling start and finish dates are same, however after releasing the Work order and by adding another operation in the work order, immediately scheduling end date equaling to Basic finish date (i.e.: Basic start and finish dates are equal to Schedule start and finish dates).
    Can any body please explain why this is heppening
    Please find the screen shots.
    After adding one more operation in the operation list and save the Work order,then Basic start and finish dates are equal to schedule start and finish dates.
    Regards,
    Srinika

    Srinika
    There are many things that affect the order scheduling:
    IMG setting - scheduling parameters
    Work centre settings
    Operation values e.g. work, duration, operation control key settings
    Calendars
    Etc
    So one possible interpretation of the above data is that the initial order operations have no work assigned, or the operation control keys don't require scheduling, or the work centres arn't set up correctly.
    Then you add a new operation which does appear to work.
    Please supply a screen-shot of the operation tab.
    PeteA

  • How to input my own Validity Start and End Dates in ME21N

    Hi All,
    I have to change the Validity Start and Validity End date in Addiitional Data Tab of ME21 transaction( PO Create ) using default Customer Values.How Can i accomplish it?
    I have used the BAdI ME_PROCESS_PO_CUST and implemented it, I have coded in the method PROCESS_HEADER.First I retrieved the data using get_data( ) method, changed the values with Customer Values and called the method set_data( ).
    However my validity start and End Dates and not changing.
    Even in ME21N if I create the PO with my own Validity Start and End dates, and go to ME23N to display the created PO, still in the additional data tab, the start and End dates are current date and Next date respectively.why its happening?
    Thanks in advance

    Hi,
    Can you please let us know in which business scenario this is required.
    SAP has provided separate functionality of Outline Agreement for considering validity period.
    If you let us know the business scenarion some solution/workaround can be suggested.
    Regards

  • Update Contract Start and End dates via BAPI_SALESORDER_CREATEFROMDAT2

    Hi Experts.
    We are successfully using BAPI_SALESORDER_CREATEFROMDAT2 to create sales order.
    Only problem is that the contract start and end date do not get updated.
    We are passing that in ORDER_HEADER_in-CT_VALID_F and ORDER_HEADER_IN-CT_VALID_T.
    After debugging, I found that there is one more table SALES_CONTRACT_IN in SD_SALESDOCUMENT_CREATE. Updating the values in that table works.
    But the problem is this table is not available in BAPI_SALESORDER_CREATEFROMDAT2. How to update Contract start and end dates from this FM ?
    I could not find anything in the search of this forums. So I guess this is not an issue and I am doing something wrong. Can someone suggest to me please?
    Thanks in adv.
    Aishi

    Are you creating a contract or a sales order?

  • Start and End Dates check

    Hi,
    I have a requirement to find the list of persons who have overlapping dates.
    Each person can have many start and End Dates, but only one row that has a NULL end date, the active record. If the start and end dates are overlapped, like in the example below, the second row should have a start date of 24-DEC-2006 and not 22-DEC-2006. Is it possible to list those persons who have overlapping dates/gap in the dates.
    Empl_ID Start Date End Date
    12345 01-JAN-2006 23-DEC-2006
    12345 22-DEC-2006 13-JAN-2007
    12345 14-JAN-2007 NULL
    Any help is greatly appreciated.
    Thanks!

    Hi Patrick
    I like where you are coming from. I hope you don't mind but I have extended your idea slightly to add in a PARTITION BY clause to make sure we look at records for the same person. Also, if we LAG to get a previous record shouldn't we LAG the END_DATE and compare it with the current START_DATE?
    LAG(END_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)
    Doing this, then the results would look like this:
    Empl_ID Start Date End Date Lag Date
    12345 01-JAN-2006 23-DEC-2006 NULL
    12345 22-DEC-2006 13-JAN-2007 23-DEC-2006
    12345 14-JAN-2007 NULL 13-JAN-2007
    This would give the SIGN an issue because in the first record the LAG would be NULL and in the last record the END_DATE would be NULL. So it looks like some manipulation of NULLs has to take place as well which I will deal with later.
    SIGN((LAG(END_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)) - START_DATE)
    Anytime the difference between the Lag Date and the Start Date is positive this means this is an overlap which means we do need to look for any variance where the SIGN is 1.
    Using the other function, we could use LEAD like this:
    LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)
    Doing this, then the results would look like this:
    Empl_ID Start Date End Date Lead Date
    12345 01-JAN-2006 23-DEC-2006 22-DEC-2006
    12345 22-DEC-2006 13-JAN-2007 14-JAN-2007
    12345 14-JAN-2007 NULL NULL
    which when combined with SIGN becomes: SIGN((LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)) - END_DATE)
    This time you would be looking for the SIGN to be -1
    Personally, I think I would prefer the LEAD function because a) there would always be a START_DATE, and b) we could replace all of the possible NULLs with the SYSDATE to get a final calculation like this:
    SIGN(NVL(LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE),TRUNC(SYSDATE)) - NVL(END_DATE, TRUNC(SYSDATE)))
    Based on the current date being 17-NOV-2009, you would now get this result:
    Empl_ID Start Date End Date Lead Date
    12345 01-JAN-2006 23-DEC-2006 22-DEC-2006
    12345 22-DEC-2006 13-JAN-2007 14-JAN-2007
    12345 14-JAN-2007 17-NOV-2009 17-NOV-2009
    Best wishes
    Michael

  • Contract start and end date in BAPI_CONTRACT_CREATEFROMDATA

    HI,
    I am using BAPI_CONTRACT_CREATEFROMDATA to create a contract from within a custom ABAP program. However I cannot figure out how to get the contract start and end dates into the contract header. I know that you can enter them into the ONTRACT_DATA_IN table parameter but these dates only appear on the line items and not the header.
    Does anyone know which parameters on the function map to the contract header start and end dates.
    Thanks.

    Hi,
    there are also fields QT_VALID_F and QT_VALID_T for quotation or inquiry. So it looks like for different contract types you need to use different fields. This BAPI calls FM SD_SALESDOCUMENT_CREATE which has subroutine ms_move_header_in which maps from BAPI fields to internal fields. Here is a small part of this routine.
      MOVE order_header_in-qt_valid_f       TO e_vbakkom-angdt.
      MOVE order_header_in-qt_valid_t       TO e_vbakkom-bnddt.
      MOVE order_header_in-ct_valid_f       TO e_vbakkom-guebg.
      MOVE order_header_in-ct_valid_t       TO e_vbakkom-gueen.
    When I check technical fields for the screen  fields "Valid from" and "Valid to" in VA43 I get names GUEBG and GUEEN. So it still looks like you should use CT_VALID_F and CT_VALID_T.
    I forgot to mention you can still debug BAPI to figure out where the problem is.
    Good luck
    Edited by: Martin Voros on Sep 11, 2009 9:57 AM

  • Product View - Start and End dates

    Hi,
             I have a material that is externally procured from a vendor to a location. In product view, I have few purchase requisitions. When i double click on it, it takes me to the details of PR. I am trying to understand what start and end dates of the PR are.
    For some PRs, the start and end dates are same but for some there are is some times a day or two and even 3 in some cases.
    I am wondering what makes the end date differ from start date.
    There is a safety day's supply of 2.5 days
    We have a transportation lane with transportation duration 23hrs.
    Any of these play any role in the end date delay?

    Hi,
          Thanks for the reply. The vendor and the receiving location have a transportation lane defined.
    What do you mean by the  time duration that shows up in the T Lane corresponding to the inforecord?
    Here are the times I see in transportation Lane;
    Product Specific Transportation lane:
    GR processing times (checked) : (No value defined) days
    Planning Horizon: 0 days
    Partner Horizon: 0 days
    Horizon for Expctd receipts: 0 days
    Horiz. Fut. Aval. Whse Stck: 0 days
    Planned Delivery time:  (No value Defined)
    Means of Transport
    Tsp. duration: 23 hrs
    Bucket offset: 0.5
    Period factor: 0.5
    and no other times defined.
    Are any of these effect the delay?
    My ECC is EST and the timestream is EST. Should I change the product view (also my own data) to EST or UTC??
    I have a product that has no delay between the start and end dates. The difference I see between the one that I am having problem (the start and end dates are apart ( I'm calling it bad one) by atleast a day) with and the one that has no delay(I'm calling this good one) between the start and end dates is the "Planned Delivery time.
    The good one has 1 day and the bad one has nothing defined.
    Does this make any difference?
    Thanks.
    Edited by: Raj G on Jul 17, 2008 3:36 PM

  • Scheduled start and finish dates in the Work order.

    Hi Friends,
    I am facing peculiar issue that once the Work order has been released schedule start and finish dates should be derived from the control key and
    operation hours and work center capacity,infact in my case while releasing the Work order,these dates (scheduled start & finish) are not been
    populating in the Work order,(but SAP standard behavior is while releasing WO,the dates should be populated).
    though i have maintained proper configuration
    could you please light up some thing on it.
    Regards,
    Srinika

    Check Scheduling Parameters assignment to order type, Scheduling option in Control key.