How to assign work centre in OM

Hi,
In organizational structure how to assign work centre.
it is necessary to assign cost centre to org structure.how ?
President has to be given personnel no.?
if employee is reporting to two superiors of different depts or different regions ,how the employee should be placed i.e dual reporting?
Urgently reply.
Thks
Archana

Hi Archana,
1. To assign Work Center the T-code is PO01.
2. Yes. In SAP HR every employee has to be given Personnel Number irrespective of their designations.
3. No its not possible according to me (Gurus Pls correct me too if I am wrong)
Hope above answers are helpful to you.
Regards
Pavani
Remainder: Points to be given on answered.

Similar Messages

  • How to assign cost centre with position

    Hi Guys
    How to assign cost centre with a position?
    thanks

    Hi,
    Go to PPOM_OLD t code & select ur organisational unit.
    Then click on staff assignments & the GOTO in menu bar,click on Accounts assignment.
    Put cursor on the position & lick on master cost center icon & assign the cost center.
    Cheers
    Ramesh

  • How to measure work centre performance in the pp point and pm pinot of view

    Dear Guru`s,
    how to evaluate the work centre performance in the pp,pm point?
    how to evaluate the OEE (overall equipment efficieny)?
    can anybody suggest that, if there is any transactions are avialable to get the reports or any process is to be followed to evaluate these?.
    regards,

    hi
    you can evaluate the PM work center using t-codes
    CR05 - Work Center List
    CR06 - Cost Center Assignment
    CR07 - Work Center Capacity
    CR08 - Work Center Hierarchy
    with this you can get the requirment,available and overlaod of the capacity
    OEE cannot be directly calculated you can develop the custom based program to calulate the one with available input,( available hrs,down time hrs)
    regards
    thyagarajan

  • How to assign work center to class

    hi any one tell me how to assign w c to class

    Mukesh,
    In the Workcenter Create(CR01) or Change mode (CR02), in the basic data tab down you will find a function button "Classification" hit this button, system will prompt for Class assignment.
    Class Type for work center is 019.
    Regards,
    Prasobh

  • Work Centre in Org Management

    Hi Gurus,
    How to view work centre object A wither in organization & staffing or simple maintenance
    I assigned workcentre to the position through PP01 but couldn't view in either above.
    Sunny

    Hi,
    to view the Workcenter with the orgunit create the evaluation path (OOAW tcode)accordingly.
    then execute the report RHSTRU00 with the eveluation path.
    then you can see the work center..
    Try the std Evaluation path
    A_TASKS

  • How to assign approval task to a person who is not a member of the site

    Hi All,
    I need to assign approval task to a person who is not a member of site but member of team site.
    I know that if a person need to approve/reject task form should have atleast contribute permission.
    Is it possible to assign contribute permission to that person through workflow using impersonate step?

    You can assign permission through workflow using impersonate step and add list item permission. Few things to note here
    1) Impersonate step actually impersonate the person who last modified the workflow. This impersonation is similar to code impersonation. So you have to be careful that person who is creating this workflow does have permission to assign permission to others.
    2) You will have to assign permission to the list item (or list) where the item is as well as the task list item (or list) where your workflow task would be created. I think that would be Association: Task List when in SPD.
    3) If user does not have any permission at the site level then the only way they can access the item and/or the task item is through the link they would have received in email. 
    I am not 100% sure how permission assignment works from SPD when you list and list items are inheriting permission from parent so please verify that part as well.
    Amit

  • IS THERE ANY GUIDE FOR DOING CUSTOMIZATION SPECIALLY FOR WORK CENTRE.

    HOW TO CREATE WORK CENTRE CATAGARY PLEASE TELL ME NO BODY IS HELPING ME

    Please Check the following sites -
    http://www.easymarketplace.de/online-pdfs.php
    www.sap-img.com
    www.sapsuperusers.com
    The above sites have good information which can help you.
    Use the following Path -
    SPRO --> Production Planning for Process Industries --> Master Data --> Resource --> General Data --> Define Resource Categroy
    Hope this may help you.
    Reward Points if useful.

  • How to Create New Activity Type  for Assiged to work centre Costing in Acti

    Dear Sir,
    We have four activity type to assigned in workcentre Costing Activity. Details are as under
    AIRJET     2010     AIRJET
    DONIER     2010     DORNIER
    SULTEX     2010     SULTEX
    SULZER     2010     SULZER
    in addition one more loom is comming in our unit and require new activity type.
    How can i create new.
    Please guide.
    Thanks in advance
    Regards
    Ajit

    Dear ,
    To create new Activity Type  , you need to follow the below steps :
    KA01 - Create Primary Cost Element for the new activities type.
    KL01 - Create Activity Type tied to the primary cost element. 
    KP26 - Change Activity Type/Activity Price Planning - maintain the Variable price
    Assign the activity type to cost center using T code KP26.
    In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal Year as 20xx.
    Click on Overview tab on top and key in costing details in this screen.
    After performing this ,while creating the work center ,this combination of activity type & cost center should be assigned.
    At work centre level , you should have
    1.Create Standrad Value Key -OP19 and Formula Key in OP49.
    2.Create Formula Parameters in OP7B or u can use existing one to assing in the Standard Value Key
    3.In CR02-Assing the Standard value key in Basic Data  and select the Formula Key in Costing tab with cost centre assingement .Save
    Try and check
    Regards
    JH

  • How can we delte a work centre?

    hi Guru's,
    i want to delete a work centre that is dedicated for the inspection planing. how am i be able to do so?\
    Regards,
    sameer Jalal

    Hi
    You can not delete if its being used somewhere. If its being used,you can change those work centers and then mark deletion flag for WC( CR02> Basic Data>Extras>Status> Deletion Flag). In this case it can not be assigned in future.
    If WC is not being used, CR02> Basic Data> Work Center--> Delete
    You can do mass replace of WC in Tcode CA85

  • How do spaces work - assign applications to a space

    I have read through a number of documents. I have assigned a number of apps to Space 2. If I open them when I am space 1, I thought they would open automatically in space 2. Am I being stupid or missing the point about how how app assignment is supposed to work.

    I have found some programs work correctly in spaces and others don't. Besides assigning the space number I also go in and physically drag the window to the new space. I had this problem with Photoshop CS3 and had to do both to get it to open correctly.

  • How to assign a person to work center

    Hi All,
    Can you please let me know how to assign a person to work center?
    Regards,
    Nima

    Dear Nima,
    what is the exact query
    Go to
    Spro > Production > Basic data > Wrok center > determine person responsible
    click new entries & create
    Go to CR01, Basic data tab & in the field person responsible press F4 you can get
    List created in the above Spro
    Regards
    Madhu

  • HR posistion updated when person assigned to a work centre.

    Hello
    in SAP Plant Maintenance (PM), we are assigning persons to work centers.
    Some times a strange thing happen when we assign a person to a work center.
    The position for the person is updated with a wrong value in HR master data.
    We are not given any position in PM, and definitely do not want to update HR master data from PM.
    Anyone experienced something like this?
    Best regards
    Tom Saga

    Hello
    I have now tried to do the same in our test system.  And for the particular user I get an error message when doing this.
    The screen for "Copy Organizational Assigment" pop up.
    And SAP try to fill in the Work centre ID as Position.
    ut with error message:
    Entry in outbound table not found
    Message no. E0400
    Diagnosis
    No partner profile (outbound parameter) could be found using the following key:
    PXCCLNT100/LS//HRMD_A///
    This refers to the key fields in table EDP13:
    RCVPRN  Partner number
    RCVPRT  Partner type
    RCVPFC  Partner function
    MESTYP  Logical message
    MESTYP  Message code
    MESCOD  Message function
    TEST    Test indicator
    Procedure
    Please check the EDI partner profiles.
    We do not understand this.  And it only happend with this user, and with all work centres we try to add him to.
    Best regards
    Tom

  • Assignment of single capacities to a work centre

    Dear experts,
    I have following problem:
    We created capacities which we want to use for capacity planning using CR11.
    In the work centre maintenance I want to assign these capacities using CR02. -  Capacity header view --> ' go to individual capacities' . Here I want to fill the table 'capacity assignments - individual capacities' . When I put in the capacity code I get the error message CR100 'the capacity exists already'.
    I can only create new capacities (using new capacity codes). that doesn't help since we need to assign pool capacities which means these new capacites can not be assigned to the other work centres later on. For my problem it does not matter whether the capacity to be assigned is a pool capacity or not.
    What I want to do is exaclty what I found described in SAP documentations, unfortunately without detailed instruktions .
    What do I need to do to be able to assign these individual capacities?
    thanks in advance
    Kurt

    Dear,
    In Work center i.e CR02 capacity header, click Goto -> Individual Capacites . This will take you to the "Assignment tot the Individual Capacity" screen. Here you give names of the individual capacities and Click "Choose (F2)" , where you can maintain the header details for this individual capacity.
    For example:
    when You  give individual capacites as '2' ,youI have to go to GOTO field and select there Individual capacities. It asks for capacity and its short text.In capacity field  you can  give person1, person 2 etc and its short text as Ramesh, Kishan (name of operators).
    Regards,
    Ram,

  • HOW TO DISPLAY ITEMS OF FIELD 'ARBPL'(WORK CENTRE)IN HORIZONTAL IN ALV..

    HI FRIENDS .
    PLEASE GIVE THE SOLUTION OF THIS PROBLEM.
    I AM DOING THE REPORT OF CAPACITY PLANNING USING ALV LIST.IN THIS REPORT FC REQUIRES THAT ITEMS(SUCH AS 1050T,300T) OF FIELD 'ARBPL'IN HORIZONTAL MANNER.
    BUT THIER THE PROBLEM IS THESE ITEMS ARE VARIABLE FOR DIFFERENT PLANT FIELD IN REPORT.
    SUPPOSE PLANT =  F-II
    WORK CENTRE  = 1050T,300T.
            PLANT = G228
    WORK CENTRE = PRESS 250T,PRESS 300T.
    PLEASE GIVE THE SOLUTION IMEDIATE I HAVE WASTED SO MUCH TIME ON THAT PROBLEM.
    THANKS IN ADVANCE.
    VIKRAM

    Hi,
      Please Use field symbols and this method
    Declaration:
      FIELD-SYMBOLS: <dyn_table> TYPE STANDARD TABLE,
                     <dyn_wa> TYPE ANY ,
                     <dyn_field>,
                     <fs> TYPE ANY.
      DATA: dy_table TYPE REF TO data,
            dy_line  TYPE REF TO data,
            xfc TYPE lvc_s_fcat,
            ifc TYPE lvc_t_fcat.
    CALL METHOD cl_alv_table_create=>create_dynamic_table
        EXPORTING
          it_fieldcatalog = ifc
        IMPORTING
          ep_table        = dy_table.
        ASSIGN dy_table->* TO <dyn_table>.
        CREATE DATA dy_line LIKE LINE OF <dyn_table>.
        ASSIGN dy_line->* TO <dyn_wa>.
        Note:Pls Reward this answer if USEFUL.
    Regards,
    Kumaresh

  • Assignment of shift sequence to work centre

    I have created a new shift sequence. where can I assign it in the work centre?

    Hi,
    you need to define the grouping key /shift definition /shift sequence in SPRO.
    Assign the grouping key work center capacity tab pageunder capacity header.
    Regards,