Hello SAP Experts,
I've configured a Browser-based PI-Sheet using T.Code O12C. At that time, I've clicked the various input and output parameters like the material withdrawn, UOM, etc. for the GI.
Thereafter, I'm using transaction CO53 to send the process instructions for a particular process order and to view the PI-Sheet thus generated, we are using the transaction CO60.
Now I would like to know at which step of this configuration the process order is attached to the PI sheet? Actually, in the last step of O12C, there is a "COPY" button. What is the utility of that button?
Moreover, when I'm trying to select more than 1 Instruction category e.g. Goods Issue, Confirmation and Goods Receipt (say) in O12C, then system is giving warning "Select only ONE entry".
So, my question is:- can't we attach all my requirement related to GI,GR and confirmation in ONE SINGLE PI-SHEET, as my company is requiring for that.
SAP Gurus, please give inputs.
Thanks and regards,
Kaushik.

Hy Kaushik,
Your question is not clear , but still I am trying to resolve it upto my understanding.
- First of all PI catagory which you have created is link with Process order via Master Recipe.You have to attached PI catagory in Master recipe to the relavent phases and also to the Conrol Recipe destination
- How many control recipe genrates for one Process order is depends on Number of Control Recipe destination you have used in your master recipe.
- So if you want to do GR/GR and Confirmation thorugh One PI sheet then obviously you have to assigne all  that relavent PI catagories under one Control Recipe Destination.
- Copy button is help you to create new PI catagory by copying any existing PI catagory.
Transaction Codes:-
Cretae Control Recipe Destination is O10C
Create Process Instruction Catagory O12C
Cretae Process Massgae Catagory O13C
Control Recipe Monitor CO53
Maintain PI Sheet CO55
Find PI Sheet CO60
Message Monitor CO54
Pls revert back if requird further help.
Regards,
Dhaval

Similar Messages

  • How to close old process orders dated 2006?

    I have a open process order dated back to 2006. There is a negative balance of -$100 on this order.
    Now in 2010 i want to close this order. The status of this order is TECO. However when i want to close this order, the system says i need to settle the negative balance first before doing so.
    Hence when i run the settlement to material the system says the process order is not technically completed yet because i have not done the final delivery yet.
    When i do final delivery using a current date in 2010, the system said it could not determine the object currency for the activity types used in the order since the cost center tied to the activity type has a validity date of up to 31/12/2006 only.
    In this case i am stuck one after another situations. How can i close this order without going through all the above conditions?

    Hi,
    One alternative is to change the Settlement profile setting (attached to Order type) in OKO7 to 'Can be Settled' from 'To be settled in Full' briefly, which allows you to close the Order even with some balance on it. Revert back the setting once you are done.
    Hope this helps.

  • How can attach a sales order link into an Internal Mail - Workplace.

    Hello, is there somebody can give me some tips to do this.
    I need to attach a link of a sales order into a message of an internal mail (workplace).
    When a sales order is blocked by credit, one mail sent to the representative credit manager.
    The subject of the mail already have the number of the sales order (&VBAK-VBELN&), BUT I don't know how to attach the link of a sales order. The idea is the user that  will read the mail can clic the link to display the sales order.
    Thanks for your help,
    JEOS.

    Hi Jeos
    While maintaining condition record VV11 with transmission medium Internal Mail  you will get the option attach file then you can attach that file and send internally to the other user . But you cant attach the sales order , you convert the sales order data into an excel file and then upload that excel file and then send to the other user
    Regards
    Srinath

  • In-process inspection...how to stop the process order confirmation?

    Hi...i'm making an in-process inspection and i want to stop the movement to the next phase or the process order confirmation, until the usage decision is made...how can i make this ?

    Dear,
    You can do this with OPK4 setting here slect your plant and process order type go in details here change the setting to
    Results Rec. (QM) = Error message  if no inspection result exist.
    Regards,
    R.Brahmankar

  • How to review all process order for a month.

    Hi,
    I need advice to review all process order in a month in order to ensure Actual quantity usage for product (BOM) is correct without missing the quantity?
    Thank you.
    Br. Hadi

    Hi Hadi,
    Use report COOISPI with list as Components and input as process order numbers. In the output layout you can see the Requirement qty field which is qty as per process order BOM and Qty withdrawn which is the actual issue qty. From the layout you also select Pegged requirement field which display the components parent material.
    You also check MB24 - Reservation List against the process order number which also display the required qty, issued qty and difference.
    Thanks & Regards,
    Ramagiri

  • How to get the Process order Number (Deatials by providing Salese order)

    Hi
    I want help to get the Process order details against with sales order number
    in which table i ll get this information and any particular  Function module is available???
    Regards
    Jagadish

    here KDAUF is empty
    Any other table is there i checked AUFK also AFKO also i ma not getting.

  • Process order confirmation through PI sheet -reg

    Hi,
    Please tell how to confirm the operation/order through PI sheet.
    I have created the process order with PH_CON as process instruction catagory. after I sent the message thr. CO53 and in CO58 entered the actvity timining and then saved.
    But i am not getting any status in the order,
    Please tell me is there any mistake inthe process.
    Regards
    Karthik

    Hi,
    Process Massage will generate only after Completing the PI sheet.So after maintaining the PI sheet you have to press Complete button then only system will generate Process Massage regarding completion of PI sheet.
    But if you leave the PI sheet only with Save then it means still there are some entries are left or may be change.So in this case system will not generate process massage.
    Now first complete the PI sheet then check in CO54 with correct date , time and plant selection.Send it from here and then check in process order.
    Regards,
    Dhaval

  • Process order confirmation through PI sheet without Batch no.

    Hi Experts,
    Can any body tell me how can we confirm the process order through PI sheet without batch no.? I know though COEBR we can confirm the order through PI sheet but it requires batch no. & We don't have batch managenent implemented.
    Youe suggestions are valuable for me.
    Regards,
    Shivkumar Dachawar

    To make GR for the order for materials without PI sheet.
    1. Process instruction category PROD_2 - which does not require batch number. Tcode O12C
    2. Assign this Process instruction category to your Control recipe destination for your plant - SPRO- > PPPI -> Process management  -> Control recipe / PI sheets -> Contrl. rec. destination -> Define and setup
    If you need more information let me know.

  • How to know the processing ordering in Acrobat Action wizard

    Acrobat Action wizard process the files in a specific folder , I would like to know the ordering citeria of the acrobat, is it based on alphaethic/ numeric order just the same as sorting function in PHP?
    Since I have to get the last file in the files list, if the ordering citeria is different from PHP , it is hard to tell.
    Thanks.

    If you need the files processed in a specific order you're better off not counting on the order used in an Action.
    My solution to this problem is to collect the file paths of the files processed by the Action in a global array and then process them using my code (from a folder-level script), which can sort them in whatever way I need them to be sorted.

  • Attaching Standard Operating Procedure (SOP) in Process Order

    Hi All,
            How "Standard Operating Procedure" sheet attached into each and every process order, and also we have to restrict the release of process order which doesn't have this SOP attachment? Each and every in-house material has SOP with huge characteristic & Parameter data. How come achieve this, what is the best practice/procedure? Is this maintain through PI sheet or any other procedure along with PI sheet? Please suggest.
    Thanks

    Hi Anupam sharma,
          Thanks for your reply. Can we use the document creation (CV01N) functionality without implementing DMS? Our requirement is each and every in-house produced material having SOP sheet which is contain lot of parameters as well as having instruction (long text). We are currently maintain as an excel sheet. We have to attach each file against each material and it should be attached with PI sheet. Let us know the possibility, 2 cases we have planned to try,
    1. No input parameter value, all are having static value and instruction (attached with each and every process order as an PI sheet)
    2. Need to input value for some of the parameters along with some instruction steps (Long text)
    How the below functionality will help us to meet the requirement?
    Displaying of Documents From Document Management System - Process Management (PP-PI-PMA) - SAP Library
    How to attach a file against each and every material, where these file will stored? Please suggest us with some more information
    Thanks

  • Process order release reject.

    Hi Experts,
    Question related to Make to order (MTO)
    I was created one sales order successfully.
    Then I run MRP and i got Planned sales order.
    After that I converted that planned sales order sa process order.
    When i click on release icon, my proble arised.
    that is Released rejected.
    I checked the stock availability in MMBE/MB52, there I found lot of stock.
    But in the Process order message is comming that missing parts list.
    Can any body give me solution for how to release the process order.
    by
    M.Anand (Hyderabad)

    Hi,
    This has already been replied to in your earlier post...!!!
    check and revert.
    Cheers,
    Rajan.

  • Creation of process order

    Hello,
    I would like to know how to create a process order, the T-code for it and i would like to know the steps involved in lnking the process order and replenishment based on the process order.
    Expecting an earliest response.
    Thanks,
    Maxx

    Hi,
    Can i use the process order as a reference doucment while posting a MIGO transaction. I tried using the process order as a refernce document for Goods receipt with inbound delivery. but while posting, a statement indicated that the process order doesnot contain any selectable items.
    i want to know whether it is a right process or do i need to make any chnages whil creating the process order.
    Thanks,
    Maxx

  • Need to show data related to Process order request , BOM in a smart form

    Hi,
    I need to show data related to
    •     Process order request
    •     BoM
    Now in selection screen we are entering the followings.
    Manufacturing  Plant ,MRP Controller, Production scheduler, Order type , Order , Material, Sales order, WBS Element,Release,Scheduled start, Scheduled finish ,Selection profile.
    how to get 1> Process Order number,Produced Material,Material Description,Print date,Narcotics indicator , Quantity produced , Phase number , Phase description ,Resource description,Standard value  to show in a request form.
      2> Item category ,Component code,Component description , Component quantity ,Component Unit of measure ,BoM base quantity.
    Please help me how to get those values , what should be the aaproach , how to write the select quiry.
    Thanks

    Hi
    To get BOM details, do the following:
    1. Use the material number and goto Article to BOM link table (MAST) to get STLNR (BOM).
    2. With this STLNR, goto STPO table (where STLNR is the key field).  Here you will get all the BOM details like components (IDNRK), UoM (MEINS) etc....
    Hope this helps.
    THanks
    Vijay
    <b>PLZ REWARD POINTS IF HELPFUL</b>

  • Problem in reversing the released Process order.

    Hi PP Gurus,
    When I'm trying to reverse the Process order release in change process order COR2 system is not allowing me as the menu option is Gray. When I released processed order Control recipe is generated and due to some problem in PI sheet I discarded in CO60 transaction code. So can anybody please tell me how to handle this situation? I mean is this can be resolved by configuration or enhancement?
    Thanks & Regards,
    Abu Arbab

    Hi Krishna,
    Thanks for reply.
    Now tell me what should be the approach we if we don't want to delete the Process order? Say PI sheet is created and sent to it's destination through Background job and later we found some error in PI sheet so and we've discarded that PI sheet. In case when I don't want to delete or Teco Process order, what will be the process in this case?
    Thanks & Regards,
    Abu Arbab

  • Process order creation for Heat Number

    Hi experts ,
    Heat Number (Hot Metal) is produced from the Steel Melt Shop in steel Industry. Approximately 30 Heat Numbers will be produced per day 
    One HEAT Number = 75 Billets (PCu2019S)
    One HEAT Number is Approx 150 Tones, by taking the Each Billet weight as 2 Tones.Approx 2250 Billets will be produced per day.
    Raw Materials to produce the billets are DRI, Coke, and Lime etc.
    Finished Materials will be HEAT Number & Billets
    How to create the Process Order for HEAT Numbers & Billets?
    What function has to be done with each Process Oder for Heat Number & Billets?
    How to Apply the Original Batch Concept ?

    Hi Ranjan,
    I am new to this forums and I saw ur thread today.
    I was wondering if u found the solution for you thread.
    I have implemented SAP ECC ^ for steel industry.
    Here we have Heat capacity 78 TO around 36 Pc of billets.
    We used collective order and we create Process Orders for Billet and it will in inturn create process order for liquid steel.
    After producing Liquid steel users will do (auto GR) GR without Batch and issues directly to Billet order(As Collective Order is used).
    After Producing Billets GR will be done and billets are Batch Managed.So we put external Batch number (Ex:Heat Number) will given to these Billets.
    Hope this will help to feel the overal view.
    If any queries revert back to me.

Maybe you are looking for

  • BUG: Verizon iPhone Visual Voicemail Not Working with Ported Number

    I ported my number from ATT to Verizon with the new iPhone 5. Visual Voicemail keeps asking me to set it up with a password. Then it says unauthorized. I spent an hour on the phone with Verizon support. They said I had to wipe my phone and set it up

  • External iSight not recognized

    I have been reading up on iSight connection troubles for a while now, to no avail. My *external firewire isight* stopped being recognized and/or turned on from one day to the next. It *does not function in any software* (iVisit, iChat) i have been us

  • I tried updating Firefox, worked once, but i put it off, now I can't do it again

    but it asked for a password so I closed the window and thought I'll get it later, but now when I click Apply Update, it just closes and then reopens to my homepage.

  • VoIP (SIP) configuration guide for Nokia 5800xm

    hi.everybody i would like to ask how to configure this  VoIP (SIP) configuration for my n5800, because when i saw and follow this link http://www.elisanet.fi/craig/sipvoip/nokia_n97.html ,i only configure my SIP setting and not my net setting which i

  • Changing built in attribute names

    Can you change default attribute names? I want to keep the functionality of perspectives when using "item add" and searching but change the word perspectives to "applicable to" as an example to make it more user friendly.