How to calculate labour cost ?

Dear All,
              In my scenario one operation i.e. winding. in winding operation i have take set up time 12 hr. , machine time  48 hr., and labour time is 48 hr.as per calculation system show correct cost for that order. but in that operation  i have used three (3) labour but in production order cost view only one (1) labour cost showing. how the three labour cost is showing.
         Thanks ,
          Parag

Hi Parag........
Is your per hour cost for labour is fixed?
Regards,
Rahul

Similar Messages

  • How to calculate the costs of every item categary in costing run

    Hello Experts,
    Could anyone explain how to calculate the costs of every item categary when I carry out the costing run. For example, item categary: M, E, G.
    Thank you in advance.
    Maria

    This Applesctipt will add comma's to the file count:
    (Copy into Applescript Editor, and Save as File Format: App, then just click the App to run)
    set x to choose folder with prompt "Choose Folder to Count Files" default location alias (the path to pictures folder as text)
    set filecount to do shell script "find " & POSIX path of x & " ! -type d ! \\( -name \".*\" -or -name \"Icon*\" \\) | wc -l"
    display dialog "File Count: " & comma_delimit(trim(filecount))
    on trim(someText)
              repeat until someText does not start with " "
                        set someText to text 2 thru -1 of someText
              end repeat
              repeat until someText does not end with " "
                        set someText to text 1 thru -2 of someText
              end repeat
              return someText
    end trim
    on comma_delimit(this_number)
              set this_number to this_number as string
              if this_number contains "E" then set this_number to number_to_text(this_number)
              set the num_length to the length of this_number
              set the this_number to (the reverse of every character of this_number) as string
              set the new_num to ""
              repeat with i from 1 to the num_length
                        if i is the num_length or (i mod 3) is not 0 then
                                  set the new_num to (character i of this_number & the new_num) as string
                        else
                                  set the new_num to ("," & character i of this_number & the new_num) as string
                        end if
              end repeat
              return the new_num
    end comma_delimit

  • How we calculate product cost  without taken activity type

    Respected sir,
    pls tell me without taking activity type costing can we calculate product cost? is it possible through Overhead costing to  calculate product cost?
    or if we taken quantity base costing how we calculate each product cost?
    please help me.......
    Than'x
    Dhananjay

    Hi
    Without Activity type you cannot calculate Operation cost. It is not good practice. Why you want to do like this. Please explain.
    I think Over head cost can be calculated without operation cost.
    Regards
    J. Saravan

  • How to calculate fixed cost for by-product in costing run?

    Dear,
    We want to have some fixed cost calculated for by-product B in costing run.
    Our current practise,  we only calculate the delivery cost as variable cost for this by-product B in the costing run for B. The by-product B is a component in the BOM of finish product A.
    However, we need some fixed cost to be countered in for by-product B, which can be by controlled by us.
    Any thought?
    Thank you all in advance.
    Christina.

    Dear,
    You have to maintain  BOM Usage-Costing-6 i.e., Costing BOM with all your required  Fixed Cost related Material components and assign it  in the by-product Material Master to include the Fixed Cost in by-product Standard Cost Estimate.  Based on this setting, system will calculate Standard Cost Estimate with this Fixed Cost and display in the related reports.
    Regards
    appalas

  • How to calculate product cost without PP?

    Hi,all
    Now I have a question about product cost
    The system don't include PP, only FI/CO,MM, so there is not BOM,Routing and Product Order,and so on.
    Then how can I estimate the product cost?
    And how can I collect the product cost? And how can I calculate the actual cost in Period-End Closing?

    Hi Srikanth,
    thanks for your help.
    Yes,I will use CO Production Order to collect the costs.
    My flow is
    first,create CO Production Order using KKF1
    then, send material to the CO Order using MB1A (how does I send the activities from Cost Center to CO Order ?)
    then,receive goods from CO Order using MB31
    The flow is right?
    But how can I send the balance of the manufacture Cost Center  to the CO order?
    How do i process the balance of the order?
    and  how can i calcute the actual price of the goods?
    regard
    Edited by: Yongjin Feng on Feb 26, 2009 9:20 AM
    Edited by: Yongjin Feng on Feb 26, 2009 9:30 AM
    Edited by: Yongjin Feng on Feb 27, 2009 1:54 AM

  • How to handle labor cost?

    Dear All,
    Scenario:
    I have a finished component ;an assembly of 3 items,how to handle the labor cost i am paying for assembling in SBO.
    could you all please write in detail .
    Thanks,
    Nandakumar

    Hi Nandakumar,
    you could have a look at this Expert Empowerment Session:
    PDF:
    [18.05.2007 -  Moving Average Price calculation - effects of Rounding|https://websmp203.sap-ag.de/~sapidb/011000358700000418832007E/KP_MAP_in_BOM.pdf]
    Recorded Webex
    [18.05.2007 -  Moving Average Price calculation - effects of Rounding|https://websmp203.sap-ag.de/~sapidb/011000358700000415572007E/CW20_FIN_moving.wrf]
    There is an example involving a BOM with integrated labout costs.
    & also this Wiki:
    [How to include labour cost in a BOM. |https://wiki.sdn.sap.com/wiki/display/B1/Howtoincludelabourcostina+BOM.]
    All the best,
    Kerstin

  • How should calculate  variance between dynamic input?

    HI  Experts,
    how should calculate Actual cost varience  between two month.

    Hi
    From the screen shot it says only u r using 2 months here.
    But if you are running for year,then this can be the steps.
    1.sort month ..go to values and the arrange .
    2.The data should display properly monthly wise
    3.Then If you have direct month object then create Previous([Month]).we have previous function
    4.write Diff=[Actual Cost]-Previous Actual Cost

  • How can i calculate my planned  and actual labour cost with fields from tab

    Hi,
       i want to calculate my planned labour cost for all operations in my production order. how can i retrive form the tables and how the actual planned cost gets calcualted. where can i see the overhed calcualtion of the material and labour.
    please suggest.
    regards
    madan

    Hi,
    Planned cost is nothing but the Standard values which you give for each opearation in the routing.
    The actual values from the confirmation for production order
    The following table and fields you can get the values
    PLPO, AFVC  - look for setup time,labor time,machine time  fields
    AFRU - look for the required fields setup,labor,mcahine time etc
    Thanks and regards
    Murugesa

  • How to calculate cost(COGS) in Sales from project

    Dear all,
    I have a situation like this:
    My customer do not emplement PS(project system) and when managing sales from project, i don't know how to calculate cost of good sold for the service line.
    Each project (contruction site; building, ....), I use 1 material master as service item to manage. while project excecution, we issue material; collect labor cost; cost of external service, so on.... total up to COGS. but i don't know how to get this one in Sales order. Could you give me some suggestions?
    thanks!

    Dear,
    You need to create all these activities ( LABOUR CCOST/ COST OSFG EXTERNAL SERVICES)as Service Material and then put it into S.O. as Service Item and Bill the same.
    Regards
    AJIT K SINGH
    HAPPY TO HELP U

  • How to create the generic data source for Labour costs report in BI (actual& plan costs)?

    Hello Guru's
    My requirement is to get the total labour costs in BEx analyzer.So i need to create custom DS for that. But i am not sure about the FICO tables which are having the Labour info..
    I'm having the GR10 report from R/3 sidepls look at the document. But i am not sure about the report, how that built,and giude me on the report.
    Please help on this to going forward.

    Hi,
    There are COOM data source which may suits your needs.
    please check data source
    0CO_OM_WBS_6
    0CO_OM_WBS_3
    Base tables are COSP and COSS.
    Check about coom data source, if not suitable then go for custom data source.
    About table cross verify with your source team.
    Thanks

  • How to calculate the Current APC (Acquisition and Production Cost)

    Hi,
    Please help me how to calculate the Current APC.
    The Current APC (Acquisition and Production Cost) is a calculated value based on Previous Year Acquisition balance plus any value changes up to the time of the report.
    The Asset History Report (RAGITT_ALV01) calculates the Current APC value &
    The Current APC can also be found in the Asset Explorer (transaction code AW01N) under Country Book 10/ Posted Values tab then the line “Acquisition Value” and column “Posted values”.
    I suppose that the calculation of Current APC (Acquisition and Production Cost) is getting done in the GET statements in the report RAGITT_ALV01, but unable to find the actual logic.
    Please help me.
    Thanks in advance,
    Satish

    Hi,
    you'll find the logic in fm FI_AA_VALUES_CALCULATE
    A.

  • How to bring the labour cost into costestimate

    Hi friends,
    How to bring the labour cost into costing run, please let us know. i have given the configuration settings but i am not able to get the accurate result. so friends please help me on this.
    where were i have to give the config settings and the   links please tell me.

    Dear,
    The cost sheet format is,
    1. Material cost,
    *2. Labour cost -
    SPRO -> Controlling -> Product Cost Controlling -> Product Cost Planning -> Basic Settings for Material Costing -> Overhead -> Costing Sheet: Components -> Define Calculation Bases*
    1. Here just check whether you have assigned the Labour cost Cost elements with Labour group or not.
    2. T Code - OKTZ : Check whether you have assigned the Cost elemnts here or not
    3. Labour cost is based on : Activity types and Cost center figures updation in KP26
    Let us know if you still need any help
    Thanks
    Edited by: nkonnipati on Feb 15, 2012 4:01 PM

  • Need tables to pick the planned overhead & labour cost

    I need the tables form where I can pick the planned labour & overhead cost for a production order.
    i want to calculate my planned labour cost for all operations in my production order. how can i retrive form the tables and how the actual planned cost gets calcualted. where can i see the overhed calcualtion of the material and labour.
    please suggest.
    venkatesh

    Hi venkatesh,
    There is a help transaction RKACSHOW, to display all the costs related information for a CO-Object, in your case the oder. The involved table name is listed indirectly too. For example COSSA for the table COSS, and COSPA for table COSP and so on.
    Kind regards,
    Zhenbo

  • Posting of Commission Exp to calculate the Cost of Goods Sold

    Hi Team,
    I do work in an automobile manufacturing organization and is new to SAP FI module. I have a business requirement which I need to fulfill; I would appreciate if all you gurus help me with finding the solution.
    Business Scenario:  at present, we are posting the following entries to record the commission we paid to dealers for selling vehicles.
    Commission Exp (DR)
         Customer (CR)
    Customer (DR)
         Dealer (CR)
    With these entries we are not been able to track the commission based on vehicle variants i.e. Toyota GLI, XLI etc.
    New Requirement:
    To calculate the Cost of Goods Sold for a variant, I need to track the commission expense based on vehicleu2019s variants. Please help me in finding the solution.
    Thanks

    Thanks for quick response.
    Let me give little more details of type of commission entries we have
    1) Normal Commission - Fixed commission variant wise and is derived from SD.
    2) Additional Commission - No predefined formula, this is totally based on top management discretion. Management decides how much would be paid to a particular dealer.
    3) Sliding Commission deduction - Deduction of certain amount from commission on late payments.
    4) Additional Sliding Commission - Payment of additional commission based on early payment terms.
    Currently, FI department is calculating all these figures on Excel sheets and then post a JV for each type of above mentioned commission.
    How can I configure the system to calculate these amounts automatically without involving Excel Sheet help?
    and how to post these amounts variant wise along with dealers and customers.

  • How to calculate the Current APC

    Hi,
    Please help me how to calculate the Current APC.
    The Current APC (Acquisition and Production Cost) is a calculated value based on Previous Year Acquisition balance plus any value changes up to the time of the report.
    The Asset History Report (RAGITT_ALV01) calculates the Current APC value &
    The Current APC can also be found in the Asset Explorer (transaction code AW01N) under Country Book 10/ Posted Values tab then the line “Acquisition Value” and column “Posted values”. 
    Thanks in advance,
    Satish

    Hi,
    I suppose that the calculation of Current APC (Acquisition and Production Cost) is getting done in the GET statements in the report RAGITT_ALV01, but unable to find the actual logic where it is being done.
    Please help me.
    Thanks in advance,
    Satish

Maybe you are looking for

  • Can't see artwork

    Hi I've been sent a PSD which opens fine (although font's not available) but I can't see the artwork, all the layers are there, visible and selectable but the artwork is all grayed out on the artboard. Wondering if this is a glitch?

  • Throwing Microsoft.ReportingServices.Library.ReportServerDatabaseUnavailableException

    Hello, I am supporting Report Server 2008 R2 with integrated mode to SharePoint 2010. For one of the report, if records are over 300, the report will not show on IE, but on status bar, there will be error as: Message: Sys.WebForms.PageRequestManager

  • How to maintain pageFlowScope value across 2 japx??

    Hi All, How to maintain pageFlowScope values across the pages. In my application I got 2 jspx pages where the 1st page (result page) have two page fragments and no fragments in the 2nd page (Master Details page). I am triggering the 2nd jspx while cl

  • ITunes app purchase - to iPod app delay...

    Has anyone noticed that after purchasing a song from iTunes on a iPhone, there is a delay before the song shows in the iPod app? This delay has resulted in me purchasing the song over, and eventually seeing the song twice in my purchased folder. Is t

  • Does iTunes 11 behave differently in Snow Leopard?

    The reason I ask is I see no option for toggling the status bar on or off, and Enter Full Screen is grayed out. I'm guessing that Enter Full Screen works with Lion/Mountain Lion only. I'm less certain whether Hide Status Bar is excluded from Snow Leo