How to change Purchase Order currency after Good receipt and Good issue?

Hi,
I've a PO created last year. The PO currency has been entered wrongly.
My store colleague has been performed good received and consumed it.
Now, I am not able to change PO currency to correct one, due to this message:-
Currency can no longer be changed
Message no. 06489
Diagnosis
As a basic rule, the currency cannot be changed if there has already been a goods receipt against a document.
If the document contains external service and/or limit items, or if an invoicing plan has been assigned to an item, the currency cannot be changed following the receipt of an invoice either.
If external service items exist, the currency also cannot be changed if services that have actually been performed have already been recorded or if the item in question has been assigned to a preventive maintenance (servicing) plan.
Is there anyway to change PO currency after Good receipt and Good issue? Thanks !

Diagnosis
As a basic rule, the currency cannot be changed if there has already
been a goods receipt against a document.
If the document contains external service and/or limit items,
or if an invoicing plan has been assigned to an item,
the currency cannot be changed following the receipt of an invoice either.
If external service items exist, the currency also cannot be changed if
services that have actually been performed have already been recorded or
if the item in question has been assigned to a preventive maintenance (servicing) plan.
Answer in question itself,need to cancel all documents of wrong currency in order of LIFO,
Create a new purchase order.

Similar Messages

  • How to change purchase order's cost center in batch

    Dear all :
    how to change purchase order's cost center in batch?

    Dear Manish :
    thanks so much for you reply.
    the filed which i wanted to change it's content is cost center (KOSTL) in table EKKN.
    i couldn't find it in this t-code when i select fields.

  • Change in PO Price after goods receipts and goods issue

    Dear All,
    Happy Holidays!! Wishing you a happy and fun-filled holiday season.
    I would appreciate your input of the issue at hand. I support MM users in and Oil & Gas downstream company.
    Issue
    Purchase Orders are created using price estimates. The price of oil products fluctuates and we usually cannot get the exact price at the point of creation of the PO.
    We use Moving Average Price (MAP) for stock valuation and so the price & quantity in the PO affects the moving average price.
    We use price estimates to create the PO but when we receive the final price for the oil products from the Supplier, most times there is a significant difference between the estimated price and the final price. Usually, at this point, we have completed all goods receipts and goods issues against the PO and are unable to make changes.
    We have an issue posting the invoice because the invoice value is significantly higher than the PO value. We also have an issue with the moving average price because it is understated as a result of this.
    To reiterate, this is a summary of the issue:
    At the point if PO creation ; Quantity = 10, 000 MT Price = $650
    Later when final price is available; Quantity = 10, 000 MT Price = $715
    Any advise on how to treat this issue, please? Your assistance will be truly appreciated.
    Thanks

    Hi All
    For my client I have to map the similar requirement for material price which is subject to more than 15% fluctuation. The actual invoice price is having quite a huge difference.
    Below are my limitations within which need to give a solution.
    PO is subject to release strategy and Material is delivered over a longer duration of time. Hence there is problem to de-Release the PO everytime price is changed.
    Since differnce is so huge, the same can not be settled during the MIRO.
    Down Payments has to be posted hence PO has to be created with estimated base price.
    Please suggest me suitable alternative options which will require no changes in PO and the price change also can be accomodated during the MIRO for  Multiple goods receipts.

  • Goods Receipt and Goods Return entries shows as Zero in PO history.

    Dear All,
    The Goods Receipt and Goods Return entries are showing as "Zero" in Delivery Cost Quantity, Amt. in local currency fields in PO History (T.Code: ME23N)
    What could be the reason?   How to find out the error?
    Expectiing valuable guidelines from the forum.
    Thanks in Advance.
    GB

    Hi
    Not ticked.
    GB

  • How to change purchase order logo & company name in runtime

    Hi Experts,
              In Sap B1 9.0 i am adding a purchase order.after that i want to take a preview of that puchase order to take print out.but in my situation am having 2 logos and company names.while adding first purchase order i need a logo1 and company 1 routinly its keep on going after that am adding a purchase order 7 in that i want to change logo2 and company2 how to acheive this in crystal report.
    Regards
    Vinoth

    Hi,
    Not possible to select layout (run time). You have assign default layout for each vendor to get correct logo and company name.
    Why you want different logo and company names? Is it same DB or different DB?
    Thanks & Regards,
    Nagarajan

  • Goods receipts and Goods returns against PO

    Hello gurus
    Good day to you. please find my requirement below
    1. i am get ting GR against PO data from legacy system and i need to post Good receipts or Goods retruns documents (ie based on the quantity recieved, if it is +ve value for quantity then post goods receipt against PO and if it is -ve value for quantity then post goods returns against PO) in SAP by using PI as middleware.
    2. IDOC provided is MBGMCR03 and message type is MGBMCR.
    So now my question is based on the received quantity i have to change the movement type as 101 and 102 respectively in idoc mapping of PI but i want to know how can i do that. i am little  confused about the usage of the idoc type provided in mapping like how can create IDOC with goods receipt or goods return based on the received quantity.
    I request you to please let me know the process to follow. can i use only one idoc provided for mapping and can i do this task in only one interface, please clarify. if i can use the idoc provided and if i can do this task in one interface (ie legacy - PI - SAP), please let me know the steps which i need to follow to complete my scernario successfully.
    Thanks and Regards
    Raj

    Hi,
    >>>i am little confused about the usage of the idoc type provided in mapping like how can create IDOC with goods receipt or goods return based on the received quantity.
    you cna use function substring (from standard graphical message mapping)
    and use it to check the first char of the quantity
    if it's - then map 102 to the MOVE_TYPE field of the idoc
    if not then map 101...
    I never worked with 102 with MBGMCR but 101 against a PO works for 100%
    Regards,
    Michal Krawczyk

  • Goods Receipt and Goods Issue

    Hi Gurus,
    I am working on an interface where I need to work on a process that allows posting of Goods recipts and goods issue and for this I have been asked to create a custom transaction that will pull the data from the local file and replicate Goods receipt (MIGO) and goods issue process in Inventory Managemnt.
    Can anyone out there please help me out how to approach this development and what would be easiest way to accomplish this task.
    Help will really be appreciated.
    Thanks
    Rajeev...

    1.   Create a custom report which get the data from input file.
    2.   Populate the BAPI parameter with respective information and movement type.
    3.   Call BAPI - BAPI_GOODSMVT_CREATE .
    4.   Call BAPI_TRANSACTION_COMMIT.
    For the custome report you can create transaction and execute.
    I don;t have detail information - BAPI_GOODSMVT_CREATE  with example. Better you search on SDN.
    Regards
    Nilesh

  • Goods Receipt and Goods Issue - Posting Date and Document Date Problem

    Hi All,
    I was using SDK to build own add on to insert Posting Date and Document Date under Inventory> Inventory Transactions> Goods Receipt and  Inventory> Inventory Transactions> Goods Issue, but the UI Screen Posting Date and Document Date shown current date.
    My SAP Business One version was 2007A SP00 PL42 and alreadly upgrade to SP05.
    End up result still the same.
    Is there someone can help me?
    Thanks you.
    Best Regards,
    danny

    Hi there,
    I already solve it by myself.
    Actually is i call the initialization twice:
    Company.GetBusinessObject(SAPbobsCOM.BoObjectTypes.oInventoryGenEntry)
    Thats what make this problem happened.
    Sorry.
    Best Regards,
    danny

  • User Exit for MIGO (goods receipt and goods issue)

    Hi all ,
    When i create a cross company goods receipt or goods issue through MIGO,I need to add another line item to the accounting documents posted with the sales tax calculated.For this i need to use a user exit which adds another line item.
    Can someone suggest me the user exit which i need to use ?
    any input would be of great help.
    Thanks,
    nsp.

    Hi
    Available exits for MIGO are
    Transaction Code - MIGO                     Goods Movement
    Exit Name           Description
    MBCF0002            Customer function exit: Segment text in material doc. item
    MBCF0005            Material document item for goods receipt/issue slip
    MBCF0006            Customer function for WBS element
    MBCF0007            Customer function exit: Updating a reservation
    MBCF0009            Filling the storage location field
    MBCF0010            Customer exit: Create reservation BAPI_RESERVATION_CREATE1
    MBCF0011            Read from RESB and RKPF for print list in  MB26
    MB_CF001            Customer Function Exit in the Case of Updating a Mat. Doc.
    No of Exits:          8
    You would hav to search through these.
    Hope this helps to solve ur problem....
    <b>do reward if useful....</b>
    regards
    dinesh

  • How to change company code currency after psotings have been made

    Hi,
    Good day! May I ask for your expert advice about changing company code currency? Is it advisable? or is it at all possible? If so, do you have a procedure for this? Thanks in advance.
    Regards,
    Peter

    Dear,
    no this is not advisable.when You decide to create a Company, You have to decide which kind of currency You have to use for it. This is an asset. Therefor You have to take the correct decision before going live.
    Now You can think to activate a parallel currency( transaction OB22), but please have strongly a look at the note 39919.
    If You strictly wants to change the currency, You could refer to SLO service into SAP Market place.
    Go Service Market Place homepage or Sapnet                  
    http://service.sap.com/slo              
    I hope this helps You.
    Mauri

  • HOW to retrieve PURCHASE ORDER DATA from archieve file and print a report

    Dear all
    1) I have retrieve purchase order data from archived files.
    2)  print purchase order data and created pdf file.
    VIJ.............
    Moderator message - Please ask a specific question - post locked
    Edited by: Rob Burbank on Apr 28, 2009 12:00 PM

    Dear all
    1) I have retrieve purchase order data from archived files.
    2)  print purchase order data and created pdf file.
    VIJ.............
    Moderator message - Please ask a specific question - post locked
    Edited by: Rob Burbank on Apr 28, 2009 12:00 PM

  • Goods receipt and goods issue smartform

    Hi :
       Is there any standard smartform for Goods receipt / Goods issue slip ?
    How to create a customizing form using smartforms when a material document is created and saved .
    Thx.
    Raghu

    Hi,
    Convert the SAP SCript to Smartform by using the migration option in Smartform
    select the appropriate script for your requirement
    for example 
    for GI
    WASCHEIN
    WA_LB_VERS1
    WA_LB_VERS2
    for GR
    WESCHEINVERS1
    WESCHEINVERS2
    migrate the same from  script to form
    then use these
    /SMB40/MMGI1_A              Goods Issue slip version 1
    /SMB40/MMGI1_L              Goods Issue slip version 1
    /SMB40/MMGI2_A              Goods Issue slip version 2
    /SMB40/MMGI2_L              Goods Issue slip version 2
    /SMB40/MMGI3_A              Goods Issue Slip version 3
    /SMB40/MMGI3_L              Goods Issue Slip version 3
    /SMB40/MMGR1_A               Goods receipt slip version 1
    /SMB40/MMGR1_L               Goods receipt slip version 1
    /SMB40/MMGR2_A               Goods receipt slip version 2
    /SMB40/MMGR2_L               Goods receipt slip version 2
    /SMB40/MMGR3_A               Goods receipt slip version 3
    /SMB40/MMGR3_L               Goods receipt slip version 3
    Hope this helps
    regards
    Shiva

  • Goods Receipt And Goods issued

    When i made a goods Receipt document then
    Stock Account D
    Stock difference Gain Account C
    it is clear but one more account also Credit(Material Variance  C)
    Stock Account D
    Stock difference Gain Account C
    Material Variance  C
    why this ladger post entry(Material Variance  C) ?
    ii)
    made a goods Issued document then
    Stock Account D
    Stock difference Losses Account C
    why this ladger not  post entry(Material Variance  C) ?
    Edited by: Krishna Gopal Krishna on Oct 8, 2008 8:19 AM

    Hi Krishna
    I would expect this type of entry if you are processing an A/P Invoice or Landed Costs where the price varies from the Goods Receipt PO. The Goods Receipt PO is the first entry of the stock so there should not be any expense accounts involved unless adding Freight Charges. The only reason I can think of could be an incorrect account allocated in Account Determination. Are you posting any Freight Charges on the GRPO? Have you checked all your account determination in Item Warehouses or Groups to see if the G/L account it is posting to is listed there and under which type of posting? Can you please check your account determination and let me know which posting type the account is assigned to, then I can understand the issue better.
    Kind regards
    Peter Juby

  • Using VL02 to do a Good Receipt and Goods Issue

    We have a BDC that uses VL02 to do a Goods Receipt, then a Goods Issue for an exchange.  We are getting an error ME 021.  This is a results of the Goods Receipt failure.  We get a warning message O1 573, which states "Certain fields needed for posting Goods Receipt have not been entered." Any direction on determining what's missing?  (We do have many exhcanges working this way).
    Regards,
    Greg

    1. Try to doGoods receipt/issue in dialog mode for the failed DN and enter the data that woukd have been entered in BDC, you may find what is missing.
    2. Look for any applicable OSS messages for ME 021 error.
    or
    3. If possible create SM35 sessions ( by modifying the program ) for the failed DNs and process those sessions in foreground, you will find the reason.
    Muralidhar

  • Automatic ORDCHG Change Purchase Order after Order response from Vednor

    Hi
    How to trigger Change Purchase Order action after receiving PO Confirmation - Order Response from Vendor.
    The scenario is that Order Confirmation vednors sends contains delivery date or delivery qunatity variance within defined tolerances. In such cases it is acceptable to allow automatic PO change.
    This is an EDI scenario. Idocs ORDRSP and ORDCHG in use.
    Thanks for hints.
    Mariusz

    - For automatic document adjustment, you must make the necessary settings in Customizing (SPRO ->Materials Management->Purchasing->Conditions->Automatic Document Adjustment). The system logs all the relevant purchasing documents and can therefore determine all the documents affected by a change to a condition.                                    
    - This is only possible for purchasing documents for which follow-on documents (goods receipt, invoice receipt) do not exist.           
    - Before you run this report, you must have run report RMEBEIN4 (creation of worklist for automatic document adjustment).

Maybe you are looking for

  • JNDI setup

    Hi, How can I setup the jndi tree in oc4j? I'd like to store properties like the "SysAdminEmailAddress" in the JNDI. These properties should be accessible from all applications. In pre J2EE days we used a properties file loaded into the System.proper

  • 8i Installation

    Can I install 8i EE on a workstation installed edition of Redhat 6.1, or does 8i EE have to be installed on the Server installed edition of Redhat. I want to be sure I have the ability to create Databases.

  • The solution to most of your mobile video playback nightmares

    LiteracySoft.com » Example Project for FreshPlanet's Video player StageVideo is toast, it will never work right (at least it hasn't worked for several YEARS NOW). So I've found my solution. I hope this helps someone. I spent days trying to figure thi

  • Why is Emoji Keyboard not working with iOS7....??? Is there any setting which I am missing? Can anyone help

    Why is Emoji Keyboard not working with iOS7....??? Is there any setting which I am missing? Can anyone help

  • Audio Correction, need some assistance

    Good day all, I've got a noob question to ask, but how do I properly implement a dynamic processor or level limiter on FCP 5.0? I'm dealing with some footage of a vocal performance with piano accompaniment that wasn't mic'd very well, thus causing a