How to changed the Cost Center Date

Hi All,
I have an issue. Cost center is created which have a valid date from 10.01.2009.
Upon checking my set up in the SAP my default date format it is DD.MM.YYYY.
It have mistakenly inputted a different date instead of October 1, 2009 it inputted January 10, 2009.
To resolved: When i went to KS02. I could not edit the valid dates just the master information. And also in KS12.
Is there a way i could change the valid dates of the cost center?

Hi,
But did you succeed to delete it via KS04 or not? If there are postings in this period, then obviously, it won't be possible to delete it and the validity period could not be shortened retroactively anymore.
Regards,
Eli
P.S. OKEON won't help you...

Similar Messages

  • How to delete the Cost center line item data

    How to delete the cost center line item data of particular cost center and only one cost center is exisiting for that company code.
    Is there any way to delete the line items in that cost center.
    Can data archiving & deleting can help us..........
    does it have any effect over other cost center data....
    any input needed.........
    regards
    rajesh

    Hi,
    i found 2 reports for you:
    1) CO_TOTAL_WRI - Archiving CO Totals Records   
    2) RKCOITW1     - Archiving CO Line Items: Write Program        
    from 2) is a linlk to customize archiv-parameters
    -> start it with transaction se38 / sa38
    A.

  • How to block the cost center

    Dear Guru's
    Can any tell me how to block the cost center, can we detele which is having values. can we delete which is not having values
    Regards
    Chandra Sekhar Reddy.P

    Hi,
    Once you post actual values or any planning exists on this cost center you cant delete.
    To ristrict posting to cost you have two options.
    1.You can change validity period.
      change  end from 12/31/9999 to what ever date you want to stop posting(e.g. as of today 10/23/08)
    2. lock all postings to cost center on Control data tab in KS02.
    Thanks,
    Rau

  • Change the cost center

    Hi all,
    In a report, I must change the cost center for Purchase Requisition and Purchase Order.
    In my opinion I must use the bapi: "BAPI_REQUISITION_CHANGE" and "BAPI_PO_CHANGE", but I don't know how to use.
    Is this correct ?
    If yes, can someone explain to me how to call them to change cost center ?
    Thank you in advance.

    Hi
    Please refer the below link you may useful.
    BAPI_REQUISITION_CHANGE
    Thanks and regards,
    Syf

  • How to change in cost center?

    Can some body please explain:
    How to change the depreciation expenditure charged from one cost center to another? Since the depreciation has been posted for the 2 months that have been closed, is it possible still to repost line items?
    To change the cost center thru KB61, is accounting document necessary?

    thanks for your reply!
    Actually the cost center is being changed from Aug onwards ,so the Depn posted to the old cost center for July needs to be reposted to the new cost center using KB61 taking the reference of accounting doc from KSB1 for the old cost center.
    But when i am using KB61 to repost the depn , system gives the error message " Transaction Repost CO Line item has been locked"
    ie July period is already closed.
    I do not have the authority to open the closed periods and repost. Is there is any other way?
    Also, once the reposting is done, Cost center can be changed for the assets thru AS02 so that system automatically posts the accumulated depn to the new cost center

  • How to find the cost center group from cycle/ segment in CO module?

    Hi All,
    I need to fetch the list of cost centers in the cost center group against the cycle.
    Is there any table which will store the list of cost centers against the cycle?
    or else, what I was thinking is use of BAPI BAPI_COSTCENTERGROUP_GETDETAIL, which will give me the list of cost centers,
    but we need to pass the controlling area + cost center grp to fetch the cost centers from BAPI, I have controlling area with me but not the cost center grp name, only I have Cycle info lke cycle name, segment name, seq number. so how to find the cost center grp name from the cycle name?
    Regards,
    Mrunal

    FM: RK_AL_CYCLE_READ
    CHECK TABLE: T811K

  • How to change the Profit Center in Sales Order

    Hi Gurus,
    Previously they setted the profit center (YB999) in sales order, now i want to change the profit center and need to give the amount into this profit center 100500.
    So, could you guide me how to change the profit center in sales order.
    Thank you for your replies.....
    Thanks & Regards,
    Chandrababu.B
    Edited by: Chandrababu Naidu on May 25, 2011 12:44 PM

    Hi
    If this SO is processed partially - i.e. transactions happened - You cant change it
    You can use ABAP and change it in Debug mode, but not advisable... Better to short close the SO and open a new SO for Balance qty
    br, Ajay M
    Edited by: Ajay Maheshwari on May 25, 2011 5:10 PM

  • How to determine the cost center

    Dear experts:
    Could you give me some suggestions about how to determine the cost center depending on the different
    storage location when we use the t-cdoe MI07
    Thanks in advance.
    Rong

    Hello experts!!!
    how have you resolved this issue???
    I have the same situation, and i dont know how to manage this.
    Thank you very much in advance.
    Best regards,
    M. Cecilia Vacatello.

  • How to change a cost center ?

    Hi
    Currently one of our Price variance account is updated in a cost center. We want to change the cost center ?
    Any input will be highly appreciated
    Thanks
    Ni

    HI,
    the corresponding cost element to your price diff. account has a cost center assigned as default CO-object.
    Check:
    1: if its on cost element master level (KA02) and change it
    2: if it is defaulted for the combination of company code+cost element (T-Code OKB9) and change it
    3: if the cost center is substituted via substitution rule ( T-Code OKC9) and change it.
    Best regards, Christian
    Edited by: Christian Ortner on Jan 21, 2010 1:06 PM

  • How to Make the Cost Center filed Mandatory ?

    While entring the Doc in FI  for Expense A/c, How to Make the Cost Center filed Mandatory?

    Hi,
    Got to field status groups and select cost center field as required field.
    Refer to this documentation
    http://www.sap-basis-abap.com/sapfi012.htm
    Please let me know if you need more information.
    Assign points if useful.
    Regards
    Sridhar M

  • How can define the cost center (department) manager?

    We are on 11.5.0.10
    Financials implementation is done(GL,AP,AR,FA,IA)
    In iAssets System, we want to set up the approval method to use "cost center-based approvals". (For cost center-based approvals to work properly, each cost center must have a manager defined.)
    How can define the cost center (department) manager? Thanks.

    I believe this is done in the organization definition screen. For each organization, we attach a classification "Company Cost Centre" (the same place where we attach the classification operating unit, inv org etc). In the others section, there are 2 additional information - GL company cost centre and reporting information. In the GL company cost, you need to attach the balancing segment value and the cost centre value. In the reporting information, you need to attach the manager for that organization. This ay the relationship between the cost centre and manager is created.
    Hope this clarifies.
    Vinit

  • Why can't I change the cost center in PA0001 using PA30?

    Hi Gurus,
    Please help.  I cannot seem to find the means to enter the cost center in the organizational assignment infotype PA0001.  It is showing as greyed out/display only. 
    As background, these personnel files were setup for time entry.  Other infotypes populated that might be impacting it are 0315.  We are not setup for organizational management within SAP.
    As I remember if I don't populate sender cost center/create infotype in 0315, I can change the cost center in PA0001 using PA30, but if I do I'm greyed out.
    Can anyone provide some insights and a possible fix for this?
    Thanks.

    Try turning it OFF by removing the X and saving it.
    Then check on PA30 if the cost center field is enabled for you to enter.
    If this doesn't work, please put the X back in the table and save it.

  • Implication of changing the Cost center during posting

    Hi all,
    Due to business reasons, we have unchecked the 'Agree' indicator in the Acct assignment configuration for Asset accounting.   Hence, cost center becomes editable during document posting.
    We want the cost center to be editable only for ABF1 t-code and for other asset t-codes like acquistion, retirement, scrapping, transfer etc, we want to derieve the cost center from the master data.
    Given the situation, I request experts' input on 2 questions -
    1.  Is it possible to have the cost center editable only in ABF1 and disabled in other AA transactions?
    2.  If cost center is editable in all the t-codes, what is the implication if the cost center is mismatched with the data available in the master record?
    Please provide your inputs.
    Thanks in advance.
    Regards,
    Sridevi

    Hi,
    The client has many plants, of which only few are running in SAP and the rest non-SAP.
    Whenever there is transfer of asset from non-sap plant to SAP implemented plants, we handle the situation as below in the receiver plant-
    1. Treat the asset transfer as legacy asset transfer and create asset master record through AS91.  Maintain the cummulative acq value and Cummu depn value till the last period in master data.
    2. As legacy transfer is not real time integrated with FI, we are doing ABF1 posting to pass manual JV to record APC and Acc depn. posting.  At this instance, we want the cost center to be manually keyed in.  This is because, we have yet another situation, where we need to have the net book value of the asset at cost center level for our allocation cycles.  Hence,
    3. But, for other normal AA transactions, it shd automatically derieve from asset master.
    Request your suggestion on achieving the above requirement.
    Regards,
    Sridevi

  • How to change the schedule line date in SO with reference to value contract

    Hi SD Guru's,
    I need to change the schedule line date in the sales order with reference to the value contract by using some algorithm that i will write. The problem that i can't find the suitable place to add the algorithm. I can't add it to the Copy control because there is no schedule lines in value contract and copy control for schedule lines does no exist.
    I can not add to user exit MV45AFZZ  , because order that was created with reference to the value contract, does not go through this user exit.
    Do you have some ideas where i can add it?
    Thanks and Regards
    Viky
    Edited by: Viky Sloutsky on Oct 20, 2010 12:43 PM

    Hello Viky
    How about using program MV45AFZB- USEREXIT_CHECK_VBEP or USEREXIT_MOVE_FIELD_TO_VBEPKOM
    or program FV45EFZ1- USEREXIT_CHANGE_SALES_ORDER
    Does the program go through these exits when an order is created with ref to a value contract??
    Also I am wondering why you need to change a Schedule line determined by Availability check and/or delivery scheduling?

  • OLMRLIST screen how to fix the cost center tab and its impact?

    Hi
    Explain the function of the T-Code OLMRLIST.
    How does it interact with the MIRO T-Code?
    What is the significance of a field check box being checked in OLMRLIST. I particularly want to know about the Cost center field.
    Raja

    OLMRLIST is used to adjust teh screen variant for the MIRO screen. At the line item level you see layouts and each layout has a set of fields in the form of columns. These are adjusted via the screen layout variants in OLMRLIST like 7_6310 which is all information and like wise you have 6_6310, etc...

Maybe you are looking for