How to de reporting on links between projects

All,
Whats the best known way to create a report on links between projects. I want to provide the PMO of my customer with a report, where they can see:
1. Delivery dates
2. whether changes are accepted
3. Who is delivering to whom
Regards,
Sander

Hi Sander,
Are you using the
deliverables/dependencies feature? In case you are, I'd suggest you to use the following tables from the Reporting DB:
[dbo.MSP_WssDeliverable]
[dbo.MSP_WssDeliverableToProjectLinks_UserView]
[dbo.MSP_WssDeliverableToTaskLinks_UserView]
You'll find in the 2 last tables the relation between the delivrables. The delivery date will be found in the first table.
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS |

Similar Messages

  • Link between Project and Sales Order

    Apart from sales order can we have a link between project and customer master ??
    I know that WBS element assignment can be made in sales order but i want to have link between
    customer master and project. I don't want any user field or text field in sales order.
    Any idea ?
    Regards
    Ashish

    Yes Mr Ashish!
    As far as iam concern there is no link between Project & Customer Master, you have to link it with SALES order, I had check in XD03,XD01, the complete customer master, i didnt find any field in customer master which links with Project.
    I'll let you know if i find any links.
    Regards,
    ANSAR

  • File not found in Link Between Projects Window - test no edit rights to other file

    Hi,
    I am doing a test to see if i can create a link by typing the link path (f.i. <>\plan2\1) in the predecessor column without having edit rights to the other plan.
    I expect this to be possible as the edit in the other plan (creation of link) is only done after the change is accepted through the LBP (link between projects) window. Besides, when i do it to both my own plans, in this LBP window i get 'create external
    link' as difference to accept.
    When I do it on Project Server 2010 to a plan I do not own or having edit rights on, I got the message 'file not found'.
    Is this message related to what I am trying or does it have another cause?
    Does someone know if what I want can be done?
    Rgds
    Sander

    Hi Sander,
    I confirm that for creating a link between projects, you need to have access in read-write to both files.
    Indeed creating such a link will write in both files information about successors (in the source file) and predecessors (in the destination file).
    Note that if you only need to update the successor, you don't need anymore to open in read-write mode the source file, since you won't write any more information in it.
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • RoboHelp5: Linking between project and subproject

    I have a master project and four subprojects They all exist
    in a flat directory; that is, the master project folder and all
    subproject folders are on the same directory level. I can merge the
    projects fine but when I try to add a hyperlink from a topic in the
    master project to a topic in one of the subprojects, the link
    disappears when I compile the master project.
    I searched adobe for the answer and found a page that
    describes "Linking Between Merged WebHelp Projects", however the
    instructions suggest putting the subproject folders within the
    master project directory. I keep a set of test projects available
    just to practice things on without breaking my actual work and
    tried this out. I couldn't create merged projects using this method
    at all. The merged project link would appear in the TOC but when I
    complied the master project and viewed the results. the merged
    projects didn't appear.
    Any ideas on how I can merge projects *and* create hyperlinks
    between the master and subprojects? Thanks.

    Just to clarify, I've got my test project organized as
    follows (as per information from Peter Grainge's site):
    Master: This is the top-level master project. The single
    folder contains only one topic which is named "null" and I deleted
    all text including the title from that topic. The TOC of this
    project starts out as containing no information.
    Child: This folder is at the same level of the directory as
    the Master folder and contains the directories for each of the
    subprojects.
    Subproject1
    Subproject2
    Subproject3
    All three of these subprojects are located inside the Child
    folder so that all of my actual project content exist on the same
    directory level.
    From here, I go to the master project in the Null topic and
    on Null's TOC, I create the Merged Project links to the three
    subprojects. So far, everything works swimmingly. Then I try to
    create a link between a topic in Subproject1 and Subproject3.
    The link seems to be created correctly, but I do get a
    warning message stating that it may not endure when the project
    files are moved. When I look at the page with the link in preview
    mode, the link exists and works.
    I compile the three subprojects and recreate the merge links
    to the subprojects in the master project, the recompile the master.
    I click "view result" and navigate to the page that is supposed to
    contain the link and (alas) the link is just plain text.
    That's where I am so far. Still going to work through the
    material on Peter's site to see if I missed something.
    EDIT: I can see the subprojects in the master just fine,
    Colum. But when I try to create a hyperlink on one topic in one
    subproject to a topic in another subproject, when all the projects
    are compiled, the hyperlink itself is broken. Does that
    clarify?

  • How do i remove the link between my apple ID and my mobile number?

    i decided to move away from iPhone a couple of days ago as a result of renewing my contract. When I got my new phone, I factory re-set it and handed it in to my network provider as part of a recycling scheme. Since getting my new phone, when people send me texts they are still sending as iMessages. I have logged onto my iTunes and removed my iPhone from the account but still nothing. How do I completely remove the link between my mobile nuber and iMessenger?

    Contact Apple support to deactivated iMessage: https://www.apple.com/support/appleid/contact/

  • How can I keep the links between pages in a PDF file after the file has been saved?

    My accounting department has just starting using Adobe Acrobat XI Standard to make our account reconciliations.  I like that we can create links between one page and the next, so that we can show our supervisor where the account balances tie to the supporting documentation.  But I have noticed the links disappear after my supervisor reviews and signs the PDF file.  Is there a way we can keep the links after it is signed?  Please note that we are not using EchoSign, just the “place signature” function in Acrobat.

    When a document is signed, the signer has the option of locking the document. The links won't be active if the document is locked, so to avoid this, instruct the signer not to lock when signing.

  • How do I break a link between apps under ios 8?

    I inadvertently OK'd "sharing" weight watchers data from the IOS 8 health app. How do I break that link?

    Hello johnedearborn,
    After reviewing your post, I have located an article that can help with Health. You can choose what data is shared with Health via the "Sources" pane in the app itself:
    Sources
    Here you'll find any third-party apps and devices that can send data to Health. You can control which apps have access to your health data.
    You can also see which apps have access to your health data by going to Settings > Privacy > Health.
    Thank you for contributing to Apple Support Communities.
    Cheers,
    BobbyD

  • Link between Project and Inventory?

    Could you please guide me how can i get link from inventory to project?

    Hi,
    If you want to expense inventory to a project, you can create a transaction type with project enabled.
    If you want to capture inventory cost for a project with inventory tracked, then license Project manufacturing, setups the PJM parameteres. Activate the locator control. With all these done, you can transfer inventory to projects.
    Make sure you run the project cost collection report and do the import of transactions by running PRC: Transaction import from projects with source inventory.
    Regards
    Leo

  • SD-How to find table of link between delivery and sales order?

    Hi Experts,
    I have a requirement as below.
    In LIPS table (SD document: Delivery: Item data), in this table has one kind data.
    One record has maintianed 2 fields PSPNR(Project definition (internal)) and PS_PSP_PNR(Work Breakdown Structure Element (WBS Element)).
    How to find sales order number of the above record? Could you tell me which table link the delivery item data and sales order number?
    Thanks a lot,
    Frank

    Hi frank
    Check the following tables  VBAP , VAPMA , VBUP . It may help you
    Regards
    Srinath

  • How to set up a link between sap fica transaction and cic front office

    Hi Guys,
    How to configure between SAP FICA transaction (FPR1 for create installation plan) to CIC front office.
    I did some changes in FPR1 transaction, same changes which are not reflecting on CIC screen, when i log on to CIC0 and select the create install plan, It is automatically go to FPR1 but it is not showing with that changes.
    I checked all the way but it is missing the link some where. plz drop any ideas on this.
    Thanks
    Venkat.

    Hi Matt, create a column of type "enhanced rich text." Then in your datasheet view, double click on the field in that column and use your "insert" tab to upload a file. You'll then see the file in this cell and you can open it straight
    from the datasheet view.
    cameron rautmann

  • Linking between projects in merged WebHelp

    I have a merged WebHelp (created using RoboHelp 10) that has several child projects. I now need to have the same topic in two child projects and I want to prevent duplicate maintenance.
    I tried making the topic a snippet and adding the snippet to the Resource Manager; however, when the snippet is updated in project A, the snippet in project B doesn't reflect the updates. The only other alternative I could think of is linking the topic from project A to project B.
    So that leads me to my question - how can you update project A so that when the user clicks a topic, it automatically displays the topic from project B (but without leaving the frame of project A)? Is there a better method to accomplish this?
    Thank you in advance for your help, I GREATLY appreciate it!
    Nikki

    Weird. I just exported a Snippet from Project 1 to Resource Manager and then dragged it into Project 2 where I made a change. That put the red icon on RM until I hit sync. I then when back to Project 1 and, as you say, the snippet was not updated in the project or showing that it was out of sync. Here's the weird bit. I then added the snippet from RM to another topic and it came with the amendment and updated the first snippet. Weird bit 2 is it seems to be working OK now although it was a quick test really needing a few more attempts.
    Might be worth you pursuing this to see if you can get it working.
    Otherwise the topic in Project B could be a Redirect to the one in Project A. That would only be practical if you always supply all the projects in the merge.
    See www.grainge.org for RoboHelp and Authoring tips
    @petergrainge

  • I have 2 iphones, 1 personal and 1 for work under the same apple ID ( dont want 2 IDs) and I'd like to keep them separate from each other.When I receive phone calls and message they both get them and so does apps,how do I break the link between them?

    I just my two phones to act as two separate entities and not being linked together and I don't want to create 2 apple IDs. one is for work and the other private, I don't want my private phone to get work related material and vise et versa.

    As I stated in my question that I do not want 2 Apple accounts, I already have one with all my private information and it should be good enough regardless how many devices. I didn't tried the iCloud but I don't think I actually had it setup. 

  • Linking between projects in CaptivatePlayer

    I'm investigating using Captivate Player to group together
    several projects.
    The first project I want to set up as a menu that links out
    to the others, and at the end of each project I want to include
    buttons that allow the user to continue with the next one (link to
    subsequent project) or go back to the menu (link to first project).
    I've tried different combinations of making my links open in
    new, current, parent window, etc. but no matter what I do, the
    Captivate Player is lost when using those links (even though the
    projects load and run in their own html wrapper).
    Thanks for your insight.

    Hey there.
    I am thinking of doing the same. Have you sorted out the
    problem?
    Regards
    Jan

  • How to create a database link between an 8i (apps) database and APEX

    Want to link my Oracle APPS databse on 8i with Oracle XE and APEX. Any idea how to achieve this ?

    I don't know what Apex is!!! But try to follow these instructions.
    It works for Oracle 9i.
    As far as I know, you are supposed to have installed other than ORACLE Client to complete these instructions.
    1. Control Panel / Administrative Tools / Data Sources (ODBC)
    Folder: System DSN /
    click add
    Choose : Microsoft Access Driver
    Data Source Name : my_test
    Description : any_description_you_want
    click Database/Select... : full pathname for <your_file.mdb>
    click OK
    Click OK
    2. Goto OH\hs\admin:
    2.1) Create a copy of "inithsodbc.ora" file giving it this name:
    initmy_test.ora
    2.2) Edit "initmy_test.ora" and change as below.
    # HS init parameters
    HS_FDS_CONNECT_INFO = my_test
    HS_FDS_TRACE_LEVEL = OFF
    3. Add this entry to listener ( Don't forget to stop/start the listener )
    (SID_DESC =
    (SID_NAME = my_teste)
    (ORACLE_HOME = <Path to OH> ) ### Ex: D:\ORANT901
    (PROGRAM = hsolesql)
    4. Now you need to add entries to point to the HS in the tnsnames.ora :
    access =
    (DESCRIPTION=
    (ADDRESS=(PROTOCOL=tcp)(HOST=<your_host>)(PORT=1521))
    (CONNECT_DATA=(SID=my_test))
    (HS=my_test)
    5. Now you need to go into the database and create the database link:
    CREATE PUBLIC DATABASE LINK "ACCESS_DB" USING 'access';
    6. select * from your_table@ACCESS_DB;
    HTH
    RK
    Message was edited by:
    RKravcenko

  • How to create a view link between ViewObject Instance in nested AM

    Hi all,
    I am using JDev 11.1.1.0. I am a bit confused about working with nested AM
    I have found the sample #33 in http://blogs.oracle.com/smuenchadf/examples/ to solve my problem, where the link is created programmatically.
    Is it that an old example? Because it seems to be that I can create the link in a declarative way in a tab of the Application Module.
    What is the advantage of creating the link on runtime?
    Thanks

    This sample is really old.
    If you can do the link declarative just do so. I guess this was not possible in the older version of jdev.
    Timo

Maybe you are looking for

  • Smartforms output as HTML in email

    Hi, I want to send the output of a smartform as html in email body. I found and used this bolg: :<a href="/people/pavan.bayyapu/blog/2005/08/30/sending-html-email-from-sap-crmerp HTML Email from SAP CRM/ERP</a> I did everything as per the blog. Howev

  • SCCM 2007 R3 Software Updates Sync : 6703 WSUS server not configured

    Hi, We run SCCM 2007 R3 in native mode (Software Update Point and WSUS both reside on SCCM site server). We're having issues running Software Updates Synchronization which have previously worked fine. In SMS_WSUS_Control_Manager the errors appear as

  • Adobe Muse: images in slideshow lose contrast/dull

    I'm hoping there's an easy workaround or solution for this. When I put my images in a slideshow and view in Preview mode or publish and view in my browser, the images look flat, with dull blacks and desaturated colors. The images look fine in design

  • BADI while Cancellation of Invoice in SRM5.0

    Hi, I need to fill some own data while cancellation of invoice. Which BADI will be suitable for it? e.g. I need to fill field REF_DOC_NO (Inv (ext) number) data for canceled new invoice with own logic instead SAP's standard one. Currently SAP is fill

  • Trouble with WRT-54G

    I have a new WRT-54G wireless router. I am on DSL. I had another wireless box and it went bad so I purchased the Linksys. Since I have hooked it up my lap top will not recieved data. It shows that it is connected but when I try to bring up Internet E