How to Disable/End Date an Element Link/Element in HR 11.5.7(Fam.Pack G)

We want to disable some element links that are no longer valid. These element links are assigned (element entries) to certain employees based on the eligibility criteria set (e.g. Organization/Job/Grade/etc). However we want to disable these elements from a specific date onward as they are no longer valid. I tried to end date either the element entry or the element link but I got the message "Field is protected against update".
From help the only thing I found regarding deleting an element is to delete all element entries linked to that element link and then delete all element links linked to that element to be able to delete or end date the element.
But what we need to do is only to disable the element links and not to delete them all together and lose any historical records related to these element entries.
If anyone has any idea on how to deal with this issue will be highly appreciated.
Thanking you in advance.
Elena

Hi again,
I made a search regarding elements/links and managed to find an old document (2002) regarding links and following the suggestion there I managed to end date the element links in request.
In order to end date the Element Link since it does not allow
you to make any updates you have to try to DELETE it and then select END DATE instead of PURGE.
Thank you!
Best regards,
Elena

Similar Messages

  • How to disable or grey out a link in detailed Navigation

    Hi All,
    We have requirement in which few of the links in are to be displayed as greyed out or disabled in detailed navigation and in navigational pages. This is to stop the users from accessing the link for sometime say for a week or so.
    I have managed to grey out the link in navigational area. But couldnt find a way to do it from Detailed Navigation. If i click on the link on detailed navigation, it would open the applicaton.
    Kindly help me on how to disable or grey out a link in detailed navigation.
    Thanks
    Namit

    Hi Namit,
    Open the particular page , and select dynamic navigation (from the right hand side corner Display drop down menu ) .
    U will get all the links which r there in the detailed navigation.
    and uncheck the visible property .
    Surekha.

  • How can I generate data when the link is click on?

    i have written a stackoverflow question ,
    would like some input if you have any , thanks, i would like to stay away from using jquery
    http://stackoverflow.com/questions/23143436/how-can-i-generate-data-when-the-link-is-click -on/23143813?noredirect=1#23143813

    I think you need to rephrase your question and be more specific. Also for me the images you are referring to do not exist. From your question I am interpreting it as "how do I program?"

  • How to disable end user personalisation for all webdynpro application.

    Dear Experts,
    I have a requirement where I have to disable the end user personalization of each and every
    webdynpro application in my server.
    I know how to disable the personalization of a single application or a single component, but my requirement is to disable the personalization of all applications.
    Request you to please suggest.
    Warm Regards,
    Upendra Agrawal

    Hi,
    As per SAP help,
    Customizing: User-Independent, Client-Wide Modifications
    While a single user u2013 during a personalization process u2013 can manipulate his or her own settings, an administrator has the option of executing Customizing settings for all users. Technically, this procedure is not different from personalization; both take place at runtime of an application. The difference lies in the range of the settings. In addition, for these global settings an application must run in a special administration session. This is always automatically the case if an application was started in the portal in the preview session. Independently of the portal, you can start an application in the following manner from within the workbench in administration mode:
    Double-click the name of the application in the object list.
    In the Web Dynpro Applications menu in the upper, left-hand corner of the Workbench window, choose  Test  Execute in Admin Mode .
    The configuration mode is passed to an application as the sap-config-mode=X URL parameter.
    Note
    All the adjustments made by the administrator in admin mode are stored as client-specific. Presently no option is available for structuring smaller user groups on an administrative basis. Since cross-client adjustment applies to the respective configuration, the structuring of smaller groups can be implemented currently through the maintenance of different configurations.
    End of the note.
    You start personalization by calling up the context menu for the respective UI element in your application. In the corresponding context menu for an administrator (that is, with URL parameter sap-config-mode=X), in addition to the standard settings administrators have the option within a UI element container to sort either single lines (Grid, Matrix aund RowLayout) or single elements (FlowLayout).
    Note
    Administrators require special authorization for client-wide modifications. This can be a developer authorization or the special authorization S_WDR_P13N. You cannot create configurations at design time with this authorization, but you can make modifications at runtime.
    End of the note.
    These modifications are valid for all users but take place in the current client only.
    Thanks,
    Chandra

  • How can I change dates on photos in Elements so I can control order of photos in album in adoberevel

    I have some of my photos in adoberevel albums, and have learned the only way to change the order of those photos in those albums is to change the date or event in my Elements 9 library. I'd prefer to work with changing the photo date, but don't know how. Can anyone help me?
    Trish 

    Jon, Thanks for responding. I have only the "free" cloud uploads allowed on Revel, so they were uploaded automatically some time ago. When I first looked at them, they appeared to be a total disaster and I decided not to look again, and was happy to keep my images on my computer in Elements 9. But looking yesterday (someone had contacted me about images of my art), I found things looked better. The only problem is the sequencing of the images, and from what I read on a Community thread is that I have to change either the dates or the events. Well, today I saw how to change the dates on Adobe (only did it with one photo as a test), but that ____ so far___ has not changed the sequence in Revel. So, I will close and re-boot my computer to see if that makes a difference, and get righy back to you. Thanks again for responding!
    Trish

  • How do you end date an objective in table per_objectives_library?

    Hi,
    I would like to find out how to end date an objective in table per_objectives_library.
    I have checked HR_OBJECTIVES_API.update_objective but there is parameters there for Valid_from and Valid_to dates. Is there any other API Package that can be used to do this?
    Thanks
    Shalantha

    Ok, found it....will use HR_OBJECTIVE_LIBRARY_API

  • How to disable International Data Roaming

    Today I connected to wireless data service from my Samsung Tab from India unintentionally and without being aware of the extremely high cost of such usage.  I got an email alert and estimated charges of $ 81.92 for merely 3.53 MB.   More expensive than GOLD !!!
    I was trying to send Verizon an email to disable INTERNATIONAL DATA ACCESS & ROAMING for my Tablet BUT cannot find any Verizon Support email address to contact them.  THATS A SHAME.
    I also signed to my account but there is no feature to disable international roaming. 
    I am so scarred even to turn on my tab for the fear that the device may automatically try to connect with service providers here in India and incur big charges for me. 

    Hi Melissa,
    I don't know how the device/service started communicating via 3G when the icon on the Samsung Galaxy Tab was showing as Wi-Fi connection.  I am having this device/service from Verizon for over 3 years now & been using a lot & had no similar incident when using in the US.  
    For the fear of unintended 3G connectivity & the charges there-off, I have completely stopped the usage of my Samsung Tab in India.  It has been TURNED OFF since 10/09/13.    I will check to see if I can find Deny Data Roaming on my Samsung Galaxy Device.  I did not find any such feature on my Verizon web account.
    As, I will be back in the US by 10/28/13 -  it does not make much sense to change plans for such a short time.  However,  I would like to know if the charges can be discounted or partially waived on a one time basis and to be considered in the $ 25 / 100 MB international data package instead of $ 81.92 charged at this time.
    Thank you.
    Veena

  • How to Calculate End-Date for a given Startdate in business hours without holidays

    Hello Experts,
    I need to create a plsql function where we need to determine end date for a task. For this, input will be only start date & number of hours allocated for that task. Based on this input we need to exclude Business hours & need to include only Business hours. and in the end we need to achieve the end date after the hour addition to the start date.
    Example : INPUT: 03-OCT-2013 12:00:00 PM /
                                  Hours Allocated 30 Hrs.
    Business Hours - 11 AM to 9 PM.
    So time starts from or Startdate is Friday 03-OCT-2013 12:00:00 PM. 
    So If I want to calculate the end-date by adding 30 hours to it, it should come WednesDay 09-OCT-2013 12:00:00 PM because I excluded Weekends & considered only business hours that is 11 am to 9 pm.
    I am not able to get any such guidance in Internet as most of the docs are having start & end date as input.
    Please help!
    Thanks in advance !!

    Hi,
    As Christ said, there's no nuilt-in Oracle function to tell whether a given DATE is a holiday or not, partially because there's so much local variation in holidays.  You can write a function like that (see http://forums.oracle.com/forums/message.jspa?messageID=3351081 ), but creating a table will be simpler and more efficient.
    I suggest creating a row for every date, whether it's a work day or not; that way, you can have variations in the schedule (e.g., schedule changes and
    partial holidays).
    CREATE TABLE  work_calendar
    (   dt  DATE       PRIMARY KEY
                       CONSTRAINT  work_calendar_dt
                           CHECK (dt = TRUNC (dt))
    ,   day_type       VARCHAR2 (8)  NOT NULL
                       CONSTRAINT  work_calendar_day_type
                           CHECK ( day_type IN ( 'HOLIDAY'
                                               , 'WEEKEND'
                                               , 'WORK DAY'
    ,   start_time     DATE
    ,   end_time       DATE
    ,   work_hours     NUMBER
    ,   work_hours_since_1970     -- or some point earlier than you'll ever need
                       NUMBER
    ,   CONSTRAINT  work_calendar_start_time
            CHECK ( TRUNC (start_time) = dt)
    ,   CONSTRAINT  work_calendar_end_time
            CHECK ( TRUNC (end_time) = dt)
    This will let you do a lot of the calculations you need without a function.

  • How to add different data types in Linked list?

    The basic idea is that I want to implement a linked list like the one which we generally implement in C. I need to store different data types in a single node. Is it possible to implement like this or I have to implement a linked list for each different data type?

    I have an application program in which there is a form. In this form there are different text fields in which data is to be inserted by the user. These data's will be inserted into the database. I want to hit the database only once. So I need to store these data in a data structure before I insert into the database. I think it will be easy for me to handle the data in a linked list if I can have different data types in a single node.
    Moreover, I think u're not getting my question. This pic will help u.
    http://img522.imageshack.us/img522/4500/sampler.jpg
    I'm not sure about that the code which u have written will have different data types in single node. I have to try that.
    And of course if anyone has any better idea than me, it will be very helpful.

  • How programmatically to end date employee element?

    I have requirement to create a new element that has to expire in three month.
    Can anybody point me in the right direction on how to do it?
    Thank you,

    To clarify, do you require the element type to end after 3 months of the effective start date, or do you require the element entries to end 3 months after the entry start date? If it's the latter, and you are running payroll, you could easily do it using a formula (or a change to the existing formula if there is one already against that element)
    If you really want to do it programatically like through pl/sql, then use pay_element_entry_api.delete_element_entry (with a date-track mode of 'DELETE') - the entry will then be end-dated as at the supplied p_effective_date value.
    Clive

  • How to disable unlimited data?

    Hi Meteor! I would like to disable for few months my unlimited data because I wont be in Ireland for few months and I would like to keep the money only for calls.  How I could disable it? Thanks in advance,Loren

    Hi Loren81,
    If you are on the 7.5GB Data plan you just need to choose a plan where you keep your credit and your old plan will be removed.
    Here's a link https://www.meteor.ie/pay-as-you-go/simply-top-up/
    -Kev

  • How to Disable Rate Date in 1 OU

    Hello All,
    Client on 11.5.10.2 has found that someone on their system has made 'rate date' auto-populate in their system in a particular OU and they would like to find a way to disable this. (They are not aware of how or when this setup was done)
    It is causing an error of 'EU02' on their Journal Import process report due to the currency conversion date not being null.
    Example: receipt created on 9-May-13 - the rate date is populating as 18-Mar-13.
    We have tried the following navigation's:
    1. purchasing > setup > financials > currency
    2. general ledger > setup > currencies
    Customer found that daily rates were setup under GL and deleted them but this did not resolve the issue.
    Could someone advise on where the setup may be that is causing the auto populate of rate date on a receipt?
    We are interested in disabling this on only 1 OU as others may need it in the future.
    Regards and Thanks

    Since you have deleted the rates in GL, now the exchange rates might have been NULL only at the GL level. However to have effect on the subledgers, you may need to run AUTO RATE concurrent program from your subledger ....
    Try running it from your subledger responsibility for respective operating unit ...
    Regards,
    Ivruksha

  • How to see what data fields are linked to

    OK, not sure if that is even how to ask for what I am looking for. I am using Jetform Design version 5.3. There is a file at my company that was created before I took over as Systems Admin and one of the fields is cutting off the test string.  It is actually the text pay line on a check ie. One hundred twenty three thousand and.......It stops at the word and. It is pulling data from our ERP system somehow and has been confirmed that it does print the cents amount when not printing thru Jetforms to Adobe Central Server.  Somewhere in the conversion those final words are getting lost and I have no clue where. I don't know how to look at the link of that pay field on the form.  Can somebody please try and give me a hand. Thanks alot!

    Can you take a look into the data file (eg. DAT file) which is used to merge with the Jetform template?
    I suppose you could see some text like:
    ^field FD_PAY_TEXT
    One hundred twenty three thousand and ...
    Please be noted that FD_PAY_TEXT is sample. It could be another name. Then, opening Jetform template by Output Designer and seeking a textbox named FD_PAY_TEXT. You can use the combo box (in the top-right side) that listing all of objects in current template to reach a specified object.
    Hope it helps.

  • How to disable ' End Employment' functionality for a responsibility

    Dear Experts,
    I want to disable or unable 'End Employment' functionality present in "Enter and Maintain>Others>End Employment" for a specific responsibility of a user.
    What i want is that when that particular user clicks on that functionality, nothing should happen or a message regarding permission from system administrator should appear.
    I appreciate your prompt response
    Regards

    You can check this article (Task Flow). In same way you apply for your requirement.
    How Does One Hide The Salary History Option That Is Available On The Assignment Form From US HR Manager Responsibility [ID 1068012.1].
    Thanks, Avaneesh

  • How to Disable Lync 2013 Web app link in Lync meeting

    I want disable Lync 2013 Web App , because it is  confuse WinXP user(no sound suuport) , I reference the topic(Disable Lync Web App link) but not work in 2013 version. How can I disable that?

    I assume you're referring to this link:
    http://social.technet.microsoft.com/Forums/lync/en-US/33fbfa3f-e7dd-43a7-85f4-43c280e17d4f/disable-lync-web-app-link?forum=ocsconferencing
    That was an unsupported but clever hack that we developed by the user asking the question.   There is not supported method for doing this in Lync 2013. 
    If it's an audio only meeting, I'd suggest removing the URL completely from each individual the meeting invite before sending it out.  If it's not, then the WinXP user would either need Lync, which they would then automatically join with anyway, or
    they wouldn't in which case sending them the meeting invite wouldn't help.
    Please remember, if you see a post that helped you please click "Vote As Helpful" and if it answered your question please click "Mark As Answer".