How to do backflush of alternate material in a bom?

Hi,
   My user wants to do choose alternate material at the time of backflushing  according to material availability..
currently we are maintaining as following priority - 1
                                                           strategy - 2
                                                            probability - for first material (100)
                                                             rest of material as  blank.
any body please guide me what should be the right procedure to achieve this.
Already iu have searched found a thread Can we define alternate material in a BOM  try to apply our expert suggestion but it is not working.
Kindly anybody help me to solve the issue.
Thanks & Regards
Sandeep Kumar Praharaj

Hi Ramagiri,
  I have gone through your document but my user wants he should select the component according to his requirement.
for that purpose i have opened the planned order in md12
select the first component make the usage probability to 0.
select the second component change the usage probability to 100
after that requirement has been transfer from first alternate component to second alternate component.
But after when i am trying to do the backflushing through MFBF second alternate component is not showing in overview screen it is still showing the first component.
can u please help me why it is happening & explain how to achieve this point as you mentioned
Thanks& Regards
Sandeep Kumar Praharaj

Similar Messages

  • Can we define alternate material in a BOM

    Dear All,
    Can we define alternate material in a BOM,If yes,How???
    pl. guide....
    Tushar Aute

    Hi,
    In BOM , alternative items are assigned to alternative item group on the general data tab page.
    In the production order in the general data tab page.
    We can define the alternative item based on priority , strategy and usage probability.
    Priority:
    This defines the priority of the item within the alternative item group.
    This determines the priority of planned withdrawls of items.
    EX Two items are assigned to alternative item group
    item A Priority 1
    item B Priority 2
    The system reads the item A first.
    Strategy:
    use the strategy to determine how the planned withdrawl is controlled
    within the alternative item group.
    The strategy should be same for all alternative items within a alternative
    item group.
    If the value 2( 100% check) is defined for the strategy the first material in
    the defined priority sequence for which sufficient quantities are available
    are reserved.
    Usage Probability:
    MRP Plans these alternative material components according to probability
    of use.Material requirements for BOM Components are planned according
    to usage probability.
    The planned withdrawls for the production order are based on the reservation lists.These lists are based on the priority and strategy.
    Regards,
    nandha
    Edited by: S.Nandakumar on Feb 21, 2008 7:21 AM

  • How to manage the alternative / interchangeable material in a BOM

    Dear Sir ,
    firstly i appreciate any effor to handle this problem ...
    secondly excuse me for long problem description and details .
    thirdly consider it as a challenge for you .
    Suppose we have a (Finished Goods -> M1,M2) and (Raw Materials -> x1, x2 , x3 , y1 , y2 ) , Suppose the BOMs are :
    M1—( x1 , x3 ) , M2—( x1 , x2 ).
    - We receive Change notes type ( A , B , or C ) from the designer :
    Type (A) : For M1 that x1 will be replaced by y1 --> (Stop use of x1 for M1)
    or type (B) : For M2 that y1 will be Alternative for x2. (It mean that we can use both of x2 & y1 alternatively)
    or Type (C) : For M2 that x1 used qty in the BOM will be changed (change in Qty.)
    Find the flow chart in order to know the requirements of the business .
    So how i can control this bussines for each type (A,B,C) ?

    dear,
    all alternative at SAP system can you handle by many  method ,
    1- if you didn't use this item again related to all BOM you can use
    follow up material method .
    you can use it at master data tap "mrp4" put discontinue indicator 1 also, put the follow up material.
    after that go to specified BOM and link the follow up material item by follow up group,
    2- if you will use  two alternative item parallel you can use
    alt.item method :
    you make alt. item related to 2 item at one BOM , it will depend to strategy method
    3- if you know the date that the old material will sufficient your production ,you can use the
    changing note method
    you will create changing note and after that apply it at the BOM .
    thx.
    Amira

  • Using CS_BOM_EXPL_MAT_V2 how to find last children of material in the bom.

    Hi,
    I want to find last children of a material.I am using FM CS_BOM_EXPL_MAT_V2. Although STPOX internal table as STUFE for level but we can't get all the last child of material directly.
    For example material A as child A1 and A2 this sub divided into A1- A11, A12 and A2 - A21 , A22 and again A21 -A211,A212 and A22 - A221,A222
    so the last children are A11,A12,A211,A212,A221,A222. So if we use max of STUFE it will omit A11 and A12.Do i need to program a custom logic to get last child using Stufe and WEGXX or is there any other method available to get Last Children of the Material or is there any other Function module to get the Last child of the material.
    Thanks in Advance.

    You will have to write your own custom logic after calling the function module.  In my case, it is easy, because the lowest level materials will always be raw materials(material type ZROH) as opposed to a semi-finished material(material type HALB).  Your's may be different.
    REgards,
    Rich Heilman

  • Add alternate material to BOM

    Hi All,
             I have a requirement in which i have to add alternate material to the BOM, I am using the transaction MRTRS_START  for transformation of General recipe to Master recipe.
    I have implemented the BADI BOM_UPDATE and used the method CHANGE_BEFORE_UPDATE to add my code to add alternate material to the DELTA_STPOB table.
    Problem is,it is reflecting in C202/C203 but change number is not updated for the same and operation number  is also missing for the added material.
    Then i came across a class CL_RMXM_ROM_MR_MAT_ASSIGN and several other similar classes. I am not able to figure out how to proceed?
      Thanks in advance.
    Alok Patel

    If you want it to be last for sure, why don't give it a number like 999? Or 777, so you will be able to add more later?

  • Lot size in BOM as well as for alternate material

    how can we define the Lot size and validity period for a BOM means we want to define that 1 to 100 qty are to be produced with alternate 1 and 101 to 1000 for alternate 2. How the same can be defined in the master BOM.
    There is one component in the BOM and there is a alternate material is also, Users want to define that while issuing the material , system allow to issue only say qty " 50" and then alternate material for next lot.
    Is there any possibility to define the BOM as per the above requirement.
    thanks
    harish

    Dear Harish,
    if u have alternative BOM's, then creat production versions
    1) creat BOM with two alternatives (say alt 1 1to 100 & alt 2 101 to 200)
    2) creat multiple Routings with two group counters
    3) creat production version in MM02 in MRP 4 view or work scheduling view
    4) in BOM slection in MRP 4 view maitain the prameter as 3 or 4
    Then MRP takes care of lot sizes difined in PV & BOM and creat procurment proposals
    Regards
    kumar
    Edited by: kumar kumar on Aug 3, 2009 8:02 AM

  • How to maintain alternative material in a BOM for a component.

    how to maintain alternative material in a BOM for a component.if stock for existing bom component is less then it should consider other alternative material in the same BOM

    HI,
    You can maintain alternate material for BOM Component by specifying Alternate Item group as below;
    Go to CS03/CS02--> Items-> Select Component and go to details->Basic Data Tab--> General Data
    Pls. find more details about Alternate Item group maintainance as below:
    Alternative item: group
    Consolidation of alternative items within a BOM. Every material in the assembly can be included in the alternative item group.
    Use
    As soon as you enter an alternative item group, you see an additional dialog box with the following data: ranking order, strategy, usage probability.
    You can maintain alternative items in the following situations:
    Alternative positions with specific usage probability
    These alternative items are incorporated with a specific usage probability. Enter the usage probability for each alternative item in the group, so that:
    dependent requirements are determined in requirements planning
    dependent requirements are changed to a reservation in the production order
    Alternative positions as information
    You can enter an alternative item for information purposes. This item would then, for example, only be taken into account in situations involving missing parts.
    As there should be neither dependent requirements nor a reservation for this item, enter no usage probability.
    Procedure
    Enter the same character string to denote the alternative items of an alternative item group.
    Enter the same strategy for all alternative items in the alternative item group.
    Dependencies
    Alternative items are valuated in the following way:
    Dependent requirements determination
    Requirements planning determines the dependent requirements according to the usage probabilities that have been entered.
    If the usage probability is 0%, then no procurement is planned for the item. For information purposes, however, dependent requirements with 0 as quantity are created.
    Withdrawal posting
    You can control the withdrawal posting for the resevation in the production order in the following way:
    Withdrawal according to usage probability (manual change is possible)
    Withdrawal if there is 100% availability
    (Check ranking order and strategy)
    Example: See Strategy for alternative position
    Further you can also maintain alternate material if you want to stop using this material at certain time as below:
    In material master of the material ,
    Go to MRP-4 View----> Under Discongtinued parts specify
    Discontinuation Indicator
    Eff-out.
    Follow-up matl
    So system will automatically consider follow up material in BOM as per the settings you have maintained for the material to be replaced.
    Hope this helps.
    Regards,
    Tejas

  • Alternate material in BOM

    Can we use any material as a alternate material in BOM

    Check this good explanation from Rich... U can easily understand the concept
    A Bill of Material is used to know how to build a product. For example, say your product is a bicycle. What are the components of the bicycle. Well, we have a frame, seat, wheels, handle bars, brakes, etc. These components make up the bill of material. In SAP, you create a BOM using transaction CS01, to change is CS02, to display is CS03. Alternative BOMs, are versions of BOMs tied to the same parent material.
    codeParent Materail - Bicycle
    Component Materials - Frame
    Wheels
    Seat
    Handle Bars
    Brakes[/code]
    In simple words... Alternate BOM means for the same material group we can have have multiple alternatives 1 and 2 with the same BOM.
    goog example would be....
    Let the FERT be a car.
    The BOM of a car will have various components. Suppose if we want to use
    a different type of siren in some models then here we can create a 2 bom(alternate) & add siren along with the other components.
    Hence depending upon the model ordered we can choose the BOM.
    For a normal car, BOM 1 &
    for a car along with siren BOM 2.

  • How to prevent error message for material description in MDG material detail screen, when user click on check action

    Dear Experts,
    I have a requirement for making material description as non mandetory in change request view of mdg material screen.
    I have done that using field usage in get data method of feeder classes, but still message is displaying.
    This message 'Material description is mandatory is displaying with check action only, but not with save or submit after i anhance field property as not mandetory.
    How to prevent error message for material description in MDG material detail screen, when user click on check action.
    Thanks
    Sukumar

    Hello Sukumar
    In IMG activity "Configure Properties of Change Request Step", you can completely deactivate the reuse area checks (but will then loose all other checks of the backend business logic as well).
    You can also set the error severity of the checks from Error to Warning (per CR type, not per check).
    Or you provide a default value for the material description, e.g. by implementing the BAdI USMD_RULE_SERVICE.
    Regards, Ingo Bruß

  • How do I change my alternate apple id from the old email address I no longer use? I am not given an edit option. Thx

    How do I change my alternate apple id which is an old email address I no longer use? I am not given an edit option. This old email address has already been removed from alternate email options but does not want to leave the alternate ID position! Thx

    Your apps were purchased under the old ID, so they will have to be deleted and re-purchased/downloaded under your new one.

  • How do I access backed-up material after i changed my Apple ID

    Good morning I am trying to get to my backed-up material that is under a previous Apple ID.
    Until July I had only one Apple ID. I had a personal I-phone connected to that account and also a work iPhone.  From July I no longer had the work phone but know that somewhere a whole raft of photos had been “backed up” to the Apple ID.  In July I also had the feeling my account might have been compromised, so I changed the Apple ID.
    I have just set up iCloud as I want to manage all the previous photos and the music from one place. On my personal iPhone under the Settings/General/Usage menu it says I have 4.2 GB of space available on iCloud. Under the Manager Storage section it shows my old work phone as having 538 MB and my personal phone at 233 MB. Firstly, how do I access that stored material? Secondly, if go into the Settings/iCloud it shows my account as being the old Apple ID – which you can’t change. You can delete the account but then I’d be in danger of deleting the 538 + 233 backups/stored material.
    Any help gratefully received thanks.
    Jack

    You need to restore the last backed up library and check it to see if it's working and contains all your photos.  When asked select Keep Both when restoring. 
    When you're satisfied your photos are backed up delete the restored version and continue with the orignal library.
    OT

  • How to upload PO text of material master ?

    dear gurus,
    how to upload PO text in material master in mass , can i use LSMW or BDC ? if yes then how?
    I have done the recording but LSMW is not working for PO text.
    Upesh khairnar.

    Hi!
    try using Purchasing Inforecord for this. in here you maintain master data linkage for Material Master and Vendor Master. You will just have to input the Material Number, the Vendor Account, and the Purchasing Org. In here you can maintain the PO text defaulted per Material Number. After the maintenance of Inforecord, the PO text will be reflected on the PO document.
    Here is the ff Transaction Code:
    - ME11 (Create Inforecord)
    - ME12 (Change Inforecord)
    - ME13 (Display Inforecord)
    Hope this helps, Thank you.
    Mik

  • How to Change Batch Classification of material master

    Hi,
    How to Change Batch Classification of material master  in a production system,Pl note that there is no stock and no open qty still system is not allowing me to delete the old Classification and add my new classification.
    Guys any solution for this.
    Thanks in advance
    rgds
    bijaya pradhan

    I believe there is a FM VB_CHANGE_BATCH for this, any body tried this FM?

  • From a table how do u find whether a material is used in another material B

    hi,
    From a table how do u find whether a material is used in another material BOM
    thanks in advance

    Yes as Velu mentioned you can get the details from STPO.
    Note that you have to use field IDNRK in table STPO to check if the material is used as a BOM Component.
    Regards
    Eswar

  • How to clear the stock of material provided to vendor(subcontracting stock)

    Hi SAP Gurus,
    Please let me know how to clear the stock of material provided to vendor(subcontracting stock) and need your help in what senario this stock will show in " Matl prov. to vendor "
    Thanks and Regards,
    SHARAN.

    Hi Sharan,
    Matl Povided to Vendor stock will appear in Subcontracting scenario.
    If at all you have given some material to a subcontractor , this will be consumed automaticaly when you will recieve the ordered material from subcontractor.that is 543 movement will take place in the backgroung when u do the GR.
    In case if u need to clear the stock u can do 542 and take the stock back to unrestricted.
    Edited by: Donsandy on Jan 21, 2009 6:19 PM