How to enable Alerts in Project Server 2013

Dears,
I am using Project Server 2013 trial edition to manage project in my organization. The problem is that no alert emails are sent to team members when there tasks expire.
I have check relevant settings in both SharePoint server side and project server side.
btw, members can receive  notification email when project manager updates the project or assign new tasks to them.

Hi,
The Alerts and Reminders Project Server settings page in SharePoint Central Administration is used to configure notification email settings in your Project Server 2013 environment.
You can refer this article which explains about alerts and notifications in Project Server 2013
https://technet.microsoft.com/en-us/library/jj635886(v=office.15).aspx
Thanks,
Phani

Similar Messages

  • How to use impersonation in project server 2013 using csom object model

    Hi sir ,
    I have try to see only my projects.Means with project server permission with help of impersonation .
    vijay

    In addition to Lars' good advice, please find this
    blog from Paul about risks and issues reporting with OData.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • How to enable alerts for app server?

    We have setup a central autoreaction for our ECC6 system. Central autoreaction is in solman.
    We have registered separate sapccm4x agents in the CI and apps instances & both are ONLINE in solman. But when we try to assign the central autoreaction to the system in RZ21, it only assigns to the CI, not to apps instance.
    How can we assign the autoreaction to the app instance?
    Note: We do not want to use solman BPM, so please do not suggest that.
    Thanks
    Prasad

    Hi prasad,
    You cannot assign any central auto-reaction methods to the MTE classes that belong to the application servers of CEN as described below.
    In this case, use the conventional assignment using a local auto-reaction method, means assign directly.
    look at the constraints as described below
    .[http://help.sap.com/saphelp_nw70/helpdata/en/ac/825f18c02e454dac8da51f4eb22265/content.htm|http://help.sap.com/saphelp_nw70/helpdata/en/ac/825f18c02e454dac8da51f4eb22265/content.htm]
    jansi

  • Project Server 2013 Ribbon Customization using a custom action

    Is it possible to customize the ribbon in the Project Center through a Solution? Is the only way to add a button to the Ribbon through an app?
    I am using Project Server 2013 on Prem and every time I deploy a custom action - button to the ribbon in the Project Center the button becomes greyed out/disabled and says "This control is currently disabled." I haven't been able to find any examples
    of how to do this in Project Server 2013 using a solution.
    Here is the custom action, I have tried with and without the EnableScript attribute but nothing seems to work:
    <?xml version="1.0" encoding="utf-8"?>
    <Elements xmlns="http://schemas.microsoft.com/sharepoint/">
    <CustomAction Id="Ribbon.Library.Actions.AddAButton"
    Location="CommandUI.Ribbon">
    <CommandUIExtension>
    <CommandUIDefinitions>
    <CommandUIDefinition
    Location="Ribbon.ContextualTabs.ProjectCenter.Home.Editing.Controls._children">
    <Button
    Id="Ribbon.Library.Share.NewRibbonButton"
    Command="NewRibbonButtonCommand"
    Image16by16="http://s10.postimage.org/lhar0oijp/U16.png"
    Image32by32="http://s17.postimage.org/trf3y2ui3/U32.png"
    LabelText="UniqueId"
    ToolTipTitle="UniqueId Displayer"
    ToolTipDescription="Displays UniqueId for the list item."
    TemplateAlias="o2" />
    </CommandUIDefinition>
    </CommandUIDefinitions>
    <CommandUIHandlers>
    <CommandUIHandler
    EnabledScript="javascript: function ReturnTrue() { return true; } ReturnTrue();"
    Command="NewRibbonButtonCommand"
    CommandAction="javascript:alert('Hello, world');" />
    </CommandUIHandlers>
    </CommandUIExtension>
    </CustomAction>
    </Elements>

    Hello,
    You can add a new button using a SharePoint feature or via an app. If you haven't see the links below already, take a look. These are for 2010 but would be very similar for 2013:
    http://msdn.microsoft.com/en-us/library/office/gg549101(v=office.14).aspx
    http://msdn.microsoft.com/en-us/library/office/ff535984(v=office.14).aspx
    http://blogs.msdn.com/b/project_programmability/archive/2011/04/08/trials-and-tribulations-in-customizing-the-project-center-ribbon.aspx
    http://epmsource.com/2012/01/26/adding-print-capabilities-to-project-detail-pages/
    http://epmsource.com/2011/12/07/hiding-disabling-ribbon-items-in-project-server-part-i/
    http://epmsource.com/2011/12/13/hiding-disabling-ribbon-items-in-project-server-part-ii/
    http://msdn.microsoft.com/en-us/library/office/jj873844(v=office.15).aspx#pj15_StatusingApp_ribbon
    Follow
    some of those example to get those buttons working / hiding then modify your code.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Send email is not working in share point desinger 2013 for project server 2013 workflow

    Hi,
      How to configure email for project server 2013. i have created workflow where i am sending email. It is not sending it.
     i have set outgoing mail setting. Tasks are created in my workflow but mail is not sending.
    Thank you for helping us.
    Thank You
    Vinay

    Hi,
      How to configure email for project server 2013. i have created workflow where i am sending email. It is not sending it.
     i have set outgoing mail setting. Tasks are created in my workflow but mail is not sending.
    Thank you for helping us.
    Thank You
    Vinay

  • Upload button in PDP page in Project Server 2013

    Hi,
    I am using SP 2013 and Project Server 2013.  I want to create a project detail page with a upload button to save document to project's site(generated from site template).
    In 2010,in solution starter kit ,there was a list viewer control to achieve this.But how to do this in Project server 2013
    Please let me know way ahead to achieve this?
    Thanks,
    Sachin 
    Sachin Sisodiya Associate,Dev Services ASPL,Udaipur

    Hi sachin,
    It seems to be Project Server issue, I will move it to Project Server forum.
    Thanks,
    Wendy
    Wendy Li
    TechNet Community Support

  • How to get timesheet information in a javascript (Project Server 2013)

    Hi all,
    In Project Server 2013, I'm trying to customize the Timesheet ribbon. This far, I've been able to add a new button and tie an event to it. All is working well. This is all done using elements.xml and a javascripts.
    Now the problem is that I want to get some informations about the timesheet (the Guid for example) and, for now, I've got no success. I know that there is an object called PS.TimeSheet, but when I try to use some PS.TimeSheet's methods I get an error.
    Note that i'm in the page http://servername/pwa/timesheet.aspx (there is not Guid in the address) and all the treatments should be done in the javascript (no call to another aspx page)
    Thanks !

    Finally, I've found the solution.
    My goal was to add a button in the timesheet ribbon to launch a special report showing some data about the timesheet. The report has the timesheet Guid as parameter.
    To customize the Sharepoint ribbon, you have to do it via an xml file and a javascript (a lot of explanation is available in the internet that explains how to do it). So I had to call a function in the javascript to launch the report (which is a SSRS report).
    When you are in a javascript you have access to many global variables. When the timesheet.aspx is displayed, there is a global variable called "timesheetComponent".
    Using this variable we can call the method :
    timesheetComponent.m_consumedApi.get_Impl()
    to get an implementation of the current timesheet. This implementation has an attibute that has a lot of nice stuff about the current user and the current time sheet. This attribute is 
    _headerInfo
    _headerInfo is a structure that includes tsUid which contains the timesheet Guid I was looking for.
    Finally, the function attached to the button goes like this :
    function _LaunchReport() {
    var tsUId;
    var rptPath;
    var tsImpl = timesheetComponent.m_consumedApi.get_Impl();
    try
    if (CONST_REPORT_PATH == null || CONST_REPORT_PATH == "" ) {
    alert("Constant CONST_REPORT_PATH is not defined")
    else {
    tsUId = tsImpl._headerInfo.tsUid;
    rptPath = CONST_REPORT_PATH + 'TimesheetDetails&rs:Command=Render&rc:Parameters=false&TimesheetUID=' + tsUId;
    window.open(rptPath);
    catch (Err) {
    alert(Err)
    CONST_REPORT_PATH is the path to SSRS defined elsewhere
    I hope this will help some other poeple !

  • How do I create a project site after I publish a project in Project Server 2013?

    How do I create a project site after I publish a project from project pro 2013 in Project Server 2013? I'm trying to look for an option in the ribbon but haven't found any. 
    Thanks
    James T.F

    Hi James,
    See in the article the procedure for site provisionning settings.
    Note that the project site is created based on the template associated to the chosen project type (EPT) when the user first publishes his project. Be aware that if you allow the user to choose weither or not he'll create a sharepoint site when publishing
    his project, he will be prompted in Project Pro with a dialog box giving the choice to create or not the site.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • How to import the Issues list from an Excel File in Project Server 2013

    Hi,
    I'm using Project Server 2013.
    A Project Manager has been playing with the Issues List, deleting some fields, creating new columns and modifying some columns name. The result of this is that I'm getting this error everytime the task
    Reporting (Project Sync) is executed:
    General
    Reporting Wss list sync failed:
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='4feafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='5deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='69eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='75eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='81eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='8deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    Reporting message processor failed:
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='5beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='67eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='73eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='7feafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='8beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='97eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    Queue:
    GeneralQueueJobFailed (26000) - ReportingWSSSync.WSSSyncMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='98eafda7-f147-e411-940d-005056957f05' JobUID='9e937da7-f147-e411-940e-005056957f0d' ComputerName='b579360a-53ab-4fe0-bf9b-c62f5e8d3529'
    GroupType='ReportingWSSSync' MessageType='WSSSyncMessageEx' MessageId='1' Stage='' CorrelationUID='0945bd9c-0d6a-a0f1-47b0-68cdfcfbff9a'. For more details, check the ULS logs on machine
    b579360a-53ab-4fe0-bf9b-c62f5e8d3529 for entries with JobUID
    9e937da7-f147-e411-940e-005056957f0d
    What I'm trying to do is to create a new Project from the scratch, update the Issues List, not deleting or modifying columns, just creating new columns in order to match the names he (the Project Manager) put in his Issues List, then Export the list to Excel,
    and then create a datasheet view matching the Exported list, but here I don't know how to import the list (copy / paste or whatsoever it can be done...)
    Do you know how to do it, or do you know another/any method to solve this problem?
    Thank you in advance,
    José Espases

    Hi José,
    2 considerations: 
    The first one is that (as you experienced) one should not delete or rename any of the predefined columns in the risk/issue list. What you did is the right way, meaning keeping the native column as is and creating new ones based on the business needs. Finally
    you just need to create view with the appropriate fields.
    Then for importing risks from an Excel list, I can't test it right now, but you should have a datagrid view (MS Access type) allowing you pasting data from Excel.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Error when create a project in newly Enabled features for Project Web App site collection in Project Server 2013

    I Enable the Project Web App site collection features in Project Server 2013 based on
    http://technet.microsoft.com/en-us/library/jj200305.aspx
    when i try to create a project i get error "GeneralUnhandledException"
    Yasser

    Also, after you provisioned PWA, are you able to get to the server settings? Did you do any configurations with PWA or using the defaults?
    Are you trying to add the project using the FarmAdmin account or did you add yourself as a resource with project manager role?
    Cheers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • How to make the 'Finish Date' field Editable in Project server 2013

    Hi All,
    In Project server 2013 on premises deployment, When I try to create a new enterprise project [Also in case of new custom project type], Only the 'Start Date' field is available. The 'Finish Date' field is by default taking the value of the 'start Date' itself.
    I am unable to make this 'Finish Date' field editable.
    Any pointers on this would be very helpful,
    Thanks
    Shanky

    Shanky --
    When you create a new project in either Microsoft Project Professional or Project Online, the system does not allow you to enter both a Start date and a Finish date for the project.  Here is how the software works:
    You enter the Start date of the project.
    You completely plan the project with tasks, task dependencies, task Durations, and assigning resources to tasks.
    Based on the Start date you provide, plus all of the task information, the software calculates the Finish date of the project for you.  So, you cannot provide both the Start date and the Finish date, nor is they any way to force the system to allow
    you to do this.  Hope this helps.
    Dale A. Howard [MVP]

  • How to make the entire project in the project server 2013 reschedule؟

    How to make the entire project in the project server 2013 reschedule ?
    Because item %compelet related to reschedule
    In this photo it is known there are no items update project

    Hi,
    In PWA, you do not have the feature to update the project plan in one click, meaning marking as completed the work before the status date or reschedule after the status date the remaining work. Either you have to use Project Pro, or edit individually the
    assignments with the actual work (if not comming from timesheets) and remaining work.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to configure Time-sheet in Project server 2013 please share the doc with screen shot

    How to configure Time-sheet in Project server 2013 please share the doc with screen shot
    Thanks and Regards, Rangnath Mali

    Hi,
    Please refer to the following Youtube video and article.
    https://www.youtube.com/watch?v=lZWvg4q17JE
    https://support.office.com/en-sg/article/Set-up-timesheets-and-task-status-672fa06f-8c4b-4e43-bfbc-4c355d681605
    Please don't forget to mark it answered, if your problem resolved or helpful.

  • How to achieve multiple hirearcy structure using RBS feature in Project server 2013

    HI,
    How can we achieve multiple hirearcy structure using RBS feature in Project server 2013?
    The below is the screen shot of hirearcy.
    GM
    DGM
    AGM
    CM
    Officers
    There are different departments and one AM may handle 4 or more department. How to achieve this permission levels so that GM can see all departments officers created project, same with other levels
    Thanks,
    Sunitha

    Hi Sunitha,
    You could populate the RBS lookup table with 2 levels (department and sub department). Then configuring correctly your
    security categories based on the RBS, the resources in the 1st level (departments) will see projects from all theirs sub departments.
    Some more references:
    http://aboutmsproject.com/project-server-securitypart-1/
    http://ntrajkovski.com/2012/06/04/the-rbs-lookup-table-in-ms-project-server-2010/
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to handle PSW approval task in project server 2013 through declarative workflow VS 2013

    Hello,
    Plz explain in detail handling PSW approval task in project server 2013 through declarative workflow VS 2013
    bcoz when using am posted on with this error when i try to approve the item
     "This list item  has not been created by the workflow.you cannot apply this content type"
    any help would be appreciated!!!!
    Thanks regards, Vignesh.

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

Maybe you are looking for

  • Multiple Choice Quiz issues

    Hello I just build a multiple choice quiz using Captivate 3. The quiz have3 right answers. I set it up so that the user has infinite number of attempts. However after the first try I can try the quiz again. Has anyone experienced this problem. If it'

  • How to set the view, which has to be shown at runtime?

    Hi, in my application i have more than one view, but at runtime only one of these views has to be shown. I want to decide this via a parameter that I get from the url. How can i set the right view to be showing at runtime? I tried it with a StartView

  • Viewing .svg thumbnails in Bridge CS5.5

    I need to organize a large number of .svg files I have in folders. I opened Bridge and found it only shows an icon for the .svg files instead of a thumnail of what the file looks like. This is very frustrating. Is there a way around this? A way I can

  • Payment Run program for china country code

    Hi all, We have a requirement where, after running a payment program we need a generate a dme file. till now we were using rffod__u which is for derman, But our requirement is for china. Can anyone suggest which is the payment run program that is use

  • How to correct bad PDF display of Excel 2007 graph-Adobe Pro X?

    Just installed Adobe Acrobat Pro X; previously had Adobe Pro 8, which worked fine.  Have Excel 2007 files with an Excel graph and a JPG image on the spreadsheet tab.  Both the graph and the JPG are too big, are displaced, and hide spreadsheet data, w