How to make material availability check work during Work Order creation

Hi Experts,
Kindly advice about these matters:
1. How to make material availability check work during Work Order creation?
My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
2. How to make information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
Thank you
-amoonra-

Hi Maheswaran,
I have implement the prerequisite notes. (Notes 790219 and 1034962). Do you know why it is still does not work?
Thanks
-amoonra-

Similar Messages

  • How to block material issue to work order

    Dear Expert,
    How do block material issue to work order when the item have been flag for deletion in MM module and have also been block for procurement and inventory in mm module.
    Please help

    Hi,
    Thank you for the prompt reply, what you mean by the Standard SAP? can you provide the reference link? I am facing the problem that the item material have been flag for deletion and been block for procurement and inventory in MM module material master data however it still able to material issue to work order. Any ideal how to block the material issue to work order when the material item have been flag for deletion and block for movement in MM material.
    Please help.

  • How to ignore Assembly Scrap of MRP during Production order Creation

    Hi All,
    We want to ignore the Assembly Scrap maintained in MRP View during production order creation.
    We are maintaining assembly Scrap for planning so we do not want to remove that.
    Please let us know if any User exit is there during Production Order Creation.
    Thanks,
    Amit

    Dear Amit,
    Assume in CO01,once after entering the total order quantity the system proposes the scrap quantity field separately,now
    remove this quantity for scrap field and press enter and once again adjust the total quantity and check for what quantity the
    system is proposing the BOM components.
    check whether this works for your requirement.
    Regards
    Mangalraj.S

  • Work Order Material Availability Check Customizing

    Hi,
    I am currently trying to set up material availability check in the work order before saving. I am testing it by entering a material in the work order for which there is zero stock. Then clicking on ORDER > FUNCTIONS > AVAILABILITY > CHECK STOCK MATERIAL. However SAP would return 'All checked materials in order 100000317 are available' in status bar.
    My customizing is as follows:
    Define Checking Rules (SPRO):
    PM     Checking rule for plant maintenance
    Define Scope of Check (OPJJ):
       Availability Check: 01 (Daily Requirements)
       Checking Rule: PM (Checking rule for plant maintenance)
       Availability check: 2 (Check availability during order release)
        Stocks
        Include safety stock: X
        StockIn Transfer: X
        Incl. quality insp. stock: X
        Replenishment lead time
        Check without RLT: X
        In/outward movement
        Incl. purchase orders: X
        Incl. purchase requisitions: X
        Incl. dependant reqs: X
        Include reservations: X
        Include sales reqmts: X
        Include deliveries: X
        Incl. planned orders: X (check all planned o)
        Incl. production orders: X (take all production)
    Define Scope of Check (OIOI):
       Plant: (Corresponds to Work Order)
       Order Type: (Corresponds to Work Order)
       Check material availability when saving order: X
       Check rule: 02 (Corresponds to material being used)
       Release Material: 3 (No release if parts are missing)
       PRT Availability: No check
       Capacity Availability: No check
    I would appreciate if you could indicate if I am missing something in the customizing or if there is some sort of error. I would like SAP to display a system message on the status bar stating that this material is not available once the user enters this material.
    Regards,
    Nikolai

    I'am facing the almost the same problem. Could anyone tell me:
    1. How to make material availability check work  during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make  information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

  • Hi regarding material availability check

    hi
    can any body let me know how to perform material availability check for a sales order to promise delivery date to customer.
    regards
    jaya prasanna kumar.d

    Hello
    Please check if setting for Res/Purc.req. is set as 'from release' or 'immediately'. I assume you system is set as 'from release' .
    Via note 790219 the material availability check was corrected and has replaced note 168373. From prospect of standard it does not make sense to execute a detailed material availabilty check when the material is still not mrp relevant. The detailed material check makes only sense when the component is relevant for MRP. As still mentioned above this MRP relevance can be handeled via order type customizing. When the order type set the MRP relevance to 'immediately' instead of 'from release'.
    For influencing the MRP relevance you can change the default values of the order type or set it manually. Via the follwing customizing path you can set the MRP relevance to 'immediately' for the order type and plant:
    Plant Maintenance
    -> Maintenance and Service Processing
       -> Maintenance and Service Orders
         -> Functions and Settings for Order Types
           -> Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval.
    Regards,
    Jane

  • How to address missing parts during material availability check

    The system prompts that a particular component is missing during material availability check of a production order. Said component is available in the system upon verification in MMBE.
    We noted that the goods receipt date of the material is way beyond the requirement date, hence the system still prompts that it is missing.
    What we did to correct this is to change the basic start date of the production order thus changing the requirement date of the material.
    The resolution unfortunately, brought another problem, another planned order was generated, which consequently generated another purchase requisition.
    What is the proper way of addressing the missing parts prompt during material availability check?

    Hi
    Not able to understand why you are using BAPI & function module.
    It is a simple function of avaialbility check.
    For this you have to fill the availability chk field in material amster of all components &  givecheckinh rule  inOPPQ .
    After creation of process order, you can check COR2 it self.
    It is a std functionality.
    It should definitely work.
    Regards
    YMREDDY

  • Material availability check not being executed

    First of all: I’m an SD consultant with limited knowledge about PS
    At our current client are we facing an issue with the material availability check in project system orders, created through e.g. CJ20N. The client mentions, that the availability check on the components is not being executed and therefore is effecting their operations
    I did check SAP OSS and found the following OSS notes:
    01774744           Planning quantity of PIR is not getting updated properly
    01745038           BAPI_NETWORK_COMP_CHANGE is updating PBED-PLNMG incorrectly
    01774657           BAPI_NETWORK_COMP_CHANGE is not updating PBED-PLNMG –III
    Those notes were also implemented
    Did find transaction CJBN and did some testing, but did get the message
    BL 001
    Availability check not activated
    I did check transaction
    OPJJ and everything looks good.
    OPJK and everything looks good
    At this point I’m totally clueless on how to resolve the issue.
    If you would have any suggestions, pointers or remarks: they would be appreciated.
    Thanks and regards,
    Jan Pel

    Hi,
    Can you please check whether the configuration of material availability check in PS is proper and in place or not. Please check the following sap help link on material's availability check in PS:
    Material Availability Check - Material - SAP Library
    Regards
    Saurabh

  • Material Availability check during work order creation and Release

    Hello All,
    We are checking material availability at creation as well as release
    Say we have Material XYZ=100 in stock MMBE
    Now XYZ =100 is say at normal storage location =75
    and scrap storage location=05 and serviceable =20
    Currently when availability check is performed it checks for 95 (It excludes scrap storage location 05 )
    but we want  Availability check to be only for normal stock =75 and not for Serviceable and Scrap location
    how to do this in configuration or via exits
    Since if the material is under Scrap location it is not counting in Availability check at work order creation this logic is working fine but I do know from where this control is put that when the material is in the stock of scrap it is not counting in Availability check for work orders.Same thing I want to extend it to Serviceable stock .
    Why not it is consider it for Scrap storage location , what is config or any MM enhancement
    So that when Availability check run it will not consider Materials at SCRAP as well as SERVISABLE storage location also.
    Please have your views on this
    Regards
    pratap

    Hello
    There are two option for your requiement
    1. Changing the status of the servisable storage location stock to restricted use stock . You can include or exclude this stock status material in OPJJ. This solution is not storage location dependent. It is stock status dependent.
    2. Please refer the enhancement for the storage location determination. I am not sure about this funtionality:
    For production orders the following enhancement is available:
    PPCO0005 enhancement for storage loc. determination/backflushing
    You can use this enhancement to change the storage location and the indicator 'backflushing' in the reservation.
    The enhancement PPCO0005 contains the following enhancement components:
    Function exit
    EXIT_SAPLCOSD_001 storage location determination/backflushing
    You can find the description in modification text of the function exit.
    You can find an example of the user exit in the function group XC01 in the include LXCO1F05.
    warm regards
    Ramakrishna

  • Material availability check be switched off for during dispatching of order

    Hi All,
    Material availability u2013 can the material availability check be switched off during  dispatching of production order but kept when order is created? 
    Is there any implications on availibilty check.
    How can we do this?
    Regards,
    Vidyasagar

    Dear
    If you want to do Material Availablity Check only at the time of order creation , please choose Availability Check Business Function 1  with your order type  /plant combination .Keep No Check  in Capacity  and do not assing  the Overall Capacity Profile Here .
    Where as keep the Capacity Overall Profile for Production Order Type with Availablity Check  -2  and Mark No Check to material availablity  option in the same .
    In OPKP -make sure that you have Capacity Profile assinged and do not mark Confirm Partial Available Qty .
    How ever , in capacity requirement , material availablity is the intregrated part  and while dispathcing production order with in the available capacity of any operation in work centre , system tries to make sure the materials are available for processing just before actual operation starts .
    Check in CM21-Setting-Strategy -Dispatch Control -Check if you have option to un-check the Material Availability .
    Regards
    JH

  • COHVPI Material Availability Check

    Hi All
    I am using COHVPI for collective check of material availability:
    1. For all packaging material it checks and show me the log if there is material shortfall, however for Batch managed semifinish product it does not show shortfall if there is any! ( I am using batch strategy to pick batch automatically, but dont think it makes any difference here)
    2. Also, after the Material Availability check the order status stilt l remains MANC, rather I expect it to change to MACM.
    Can you guys please suggest any solution for this!
    Thanks in advance
    Rahul

    The status MANC suggests that a dynamic availability check is not being executed.
    Check if the same occurs in COR2 as well as COHVPI. If so, you then need to check if availability check is actually switched on for the material;
    First, check if a checking group has been assigned to the material master and ensure "No Check" is not selected in transaction OVZ2.
    Then check the checking rule assigned to the order type in transaction OPJK. Here, you can check if a check is executed during release or during creation. It may be you have only activated a dynamic ATP check at order release for example and the orders being processed in COHVPI are CRTD.
    Also, You should check tranaction OVZ9 to ensure the availability check is checking receipts that you expect it to check.

  • Availability check during process order creation

    Hi all,
    can anyone tell me significance of availability check during creation /change of process order?? ( in terms of business)
    how is the usual processs?

    Hi,
    Availability check for a material is carried out only if the material is
    1. A stock item
    2. Not a phantom item
    3. Not a bulk material.
    This can be carried out
    1. during order creation
    2. during order release
    3. when a created order is saved
    Availability check can be triggered either manually or automatically.
    For this we need to define in checking control(opjk)
    First define a checking group(ovz2) and checking rule and this
    must be assigned to checking scope.(opjj)
    In the checking scope(opjj) we should define
    1. which Mrp elements are to be considered during check
    2. which inventory categories are to be taken into account
    3. whether Replinishment lead time is to be taken into account or not
    4. whether check is also to be carried at storage location level.
    This checking rule must be linked to checking control(opjk)in which you can say
    1.No availability check for the material
    2.Availability check when saving the order
    3.What type of check is to be carried
    whether ATP CHECK or Check against PIR quantities
    4. Whether order should be released or not if there is
    any missing parts.
    The checking group is assigned to material master MRP3 view.Please check whether checking gorup is assigned to all the components in the BOM.
    Regards,
    nandha

  • Material Availability Check Upon Confirmation

    Hello Everyone,
    I had a question regarding Material Availability check.
    Here My raw material and Semifinished Goods are Backflushed during confirmation. My client wants to check material availability check upon confirmation of production order. System should not allow Confirmation if no stock is available. Is there any way how I can do this?
    I know we can perform material availability check upon release and prevent the same, but user does not accept this since change in production order is possible even after release.
    Any suggestion would be greatly appreciated.
    Sincerely,
    Aji Kurian Mani

    Hi,
          you can configure this in the confirmation parametres --OPK4.In General individual entry tab Error handling/logs tabmake a tick for the Goods movements --Termination for the Incorrect Goods Movts.
    Termination of Confirmation if Incorrect Goods Movements Controls if the confirmation is terminated in the event of incorrect goods movements
    If these incorrect goods movements are determined by inventory management, then the option of correcting these errors is offered in the error handling
    If the correction is not successful, the confirmation is terminated
    Thanks,
    Rajanikanth

  • Material Availability Check in Process Order Issue

    Guys, I need some help in understanding the folowing issue:
    I have a FG and 2 components.I created a process order and tried to release the order. Automatic availability check is done and a dailog box appeared to list out the missing parts. Missing parts list shows both the components. But one of the componet has unrestricted stock to use in the storage location. why did the availabity check show missing part for that component?
    I checked pp checking rule and it says for business rule 2 "no check" is unchecked. so that means checking is done. and this pp checking rule is assigned in OPJJ and also assigne dto the material master of the component.
    please let me know if you need more information. Thx

    Dear you are absolutely correct if you uncheck No check box in material availability in Order control OPJK  per plant and order type that no automatic material availability check is to be executed for the specified business transaction (order creation or order release).
    But further please note that the option of calling up a material availibility check manually and also of executing a collective availability check is not affected by setting this indicator. This indicator is also ignored if you work with Assembly orders and you have defined in Customizing for Sales Orders that a material availability check is to be carried out.
    Cheers
    kK

  • Availability check during production order creation - Missing parts details

    Hai Gurus,
    I have one problem during Availability check when converting Planned order to production order.
    1) A- is the finished material, which has A1 to A7 components.
    2) A2 is the procured item with safety stock and it has safety stock also.
    3) When sale order is created , the material A2 is reserved against the planned order for finished material - A.
    4) so when availability is checked during planned order stage , system says no missing parts, when planned order
         is converted to production order system says missing parts for component A2, which is stock and reserved against
         planned order
    5) Checking rule for Production order is maintained as follows,
         a) Include safety stock.
         b) Include reservation.
         c) Include sales requirement
         d) Include deliveries.
         e) Include dependent reservations.(x)
         f) Include production orders.(X)
         g) Check release for stock transport orders only.( A)
    So now i don't know where I went wrong , so that the system could consider the safety stock of Component A2 which is in stock and already reserved against planned order and it does not show missing parts when planned order is checked.
    Waiting for your positive feed back.
    Regards,
    Sekar chand

    Dear,
    What checking rule you have maintained for planned order.???
    As what i can understand by your question that you have maintained to check reservation only in production order not in planned order. Or one important thing mostly people configure to reserve material only after release or creation of production order. Are you reserving material at planned order stage.?
    Check these things. you will automatically find the answer. Hope it will help you. Revert back for more clarification.
    Regards,
    Alok Tiwari

  • Production order release Material Availability check

    Gurus,
    I have a production problem where the order can be released when the component for the order is in a restricted status.  This is not allowed by the batch search strategy.
    <u>Here's Problem Description:</u>
    When running on version 4.6C, I have a work order created. I release the work order successfully.  However there is a component that has an invalid material/batch according to the batch search strategy  The material availability check shows all components available. 
    However, I remove the batch and the batch can not be entered because it is not correct according to the batch search strategy.  I try and release and the material is added to the missing parts list.
    I change the component so that it can be used.  
    Put the batch number back in the order. 
    Save the order.  
    Change the component material/batch so that it is no longer valid.  
    The order will release and it shouldn't because the material/batch is not valid.
    <u>I've looked at the following transactions and master data:</u>
    OPL8 - Order Type - Dependent Parameters Overview for my plant and order type and the check batch box is checked.
    MM03 - Material Master MRP 2 view for the component to get the availability check
    OVZ2 - Availability check control
    OPJK - Order Control to get the checking rule for order release
    OPJJ - Availability check control details with availability check and the checking rule for order release - I did not see anything here that would influence the checking based on if the batch was entered or not.
    I did double check the batch search strategy for production order - COB3. Everything looks OK there.
    Does anyone have any other places to check? I must be missing something. I tried OSS - there weren't any notes that I could find.
    Thank you!
    Michelle

    Hi,
    Check in order control opjk for order type pp01
    Batch assignment /release material
    Release despite missing batches
    no release if batches are missing
    Regards,
    nandha