How to post costs to the project?

Hello
I need to post costs to the project for testing purposes. Please tell me how as I am not PS consultant
Any costs to any period
Thanks

Hi Comandante,
Release Project first, then Execute MIGO transaction.
Selection Goods Issue, against Others.
select movement type 221 Q.
Check the availability of stock for any material in MMBE for same plant which is assigned in the WBSE/Project.
Enter material, qty, WBSE, Plant and storage location and then Issue material. Check the actual cost against WBSE in CJI3.
As suggested by robert, you can post actuals in the project but you have to run more transactions.
Hope this helps you !!
Br
Hari.

Similar Messages

  • How to post costs after project close?

    I wish to post costs to a project ( WBS/Network) after the status is set to close?
    Can you please tell me how we can do it.

    In the Closed status you can no longer make any changes to the project hierarchy. The status is passed on to subordinate WBS elements.
    The status allows
    You to post actual costs to orders and networks that are assigned to the WBS element, as long as their status permit this
    The status prohibits
    You from assigning networks, production orders or CO orders to the WBS element.
    You from posting actual costs to the WBS element
    The status deactivates assets in construction that are assigned to the WBS element.
    You can cancel the Closed status. In this case the system sets the Technically completed status.
    However, it is best not to post costs to the subordinate WBS/network either. If required, undo the CLSD status and post.

  • In warehouse management how to post stock in the warehouse by using physica

    hi
    in warehouse management how to post stock in the warehouse by using physical inventory method
    can anyone tell me the process in detail
    thanksin advance.

    HI ,
    In Ware house management you can block the stock for Physical Inventory purpose. You cannot post the stock to the warehouse using Physical Invenory.
    If there is a count going on so the concerned Warehouse bin is to be blocked during Inventory so that no further goods movement is possible during that period.
    Once the Physical Inventory ids done the block can be released so that the movement can again happen.
    The Inventory mangement initiates the transfer requirement. This transfer requirement is used for creating the transfer orders. The transfer order confirmation is done then which actually places the stock in the concerned bin mentioned in the order.
    The stock in WM can be checked in LX24/ LX26 which is same as theat of MMBE of MM.
    Hope this helps.
    Regards,
    Prasanna
    Award pls if helpful.

  • How to make and Burn the project to DVD

    Would you pleased advice me how to make and burn the Project to a DVD as I'm new user for the Adobe Premier Pro.
    Tks & B/regards,
    Handjojo

    As said before you need Adobe ENCORE to make dvd menu and burn to dvd.
    But first you need to download and install Adobe ENCORE.
    Follow the instrtuctions in the link below how do downlaod and install.
    Encore CS6 not installed with Creative Cloud
    Then go over to Adobe TV.
    How to make a DVD.
    AdobeTV Learn Encore CS4 
    Learn Encore CS5 | Adobe TV 
    Using Premiere Pro CC & Encore CS6 for Bluray, DVD, and Interactive Video for iPad,ATV, and Mobile HD | DAVTechTable | Adobe TV 

  • How can I programmably extract the project build information set in the project build specification. So I can then use the information in an 'About' dialog.

    Extracting Project information
    How can I programmably extract the project build information set in the project build specification.
    So I can then use the information in an ‘About’ dialog.
    Dave

    In the labview\resource\appbuild folder their are some VI's that can deal with build specs! They return a variant containing the data!
    It's the reason I build a variant probe.
    Be aware that the build info is not present in th lvproj file of the built executable!
    Ton
    Free Code Capture Tool! Version 2.1.3 with comments, web-upload, back-save and snippets!
    Nederlandse LabVIEW user groep www.lvug.nl
    My LabVIEW Ideas
    LabVIEW, programming like it should be!

  • Planned cost in the project

    Hi,
    I have created a project using Assembly processing with strategy 85. The planned cost of the project per month is say Rs 50,000/- The duration of the project/ internal activity is for 6 Months. The scenario is the planned cost is fixed for each month.i.e Rs 50,000/-. I have maintained 'Plan Price for the period' in the costing variant to get planned cost equally distributed over 6 months. But the report shows (S_ALR_87013532) the planned cost is divided over 6 months (Rs 8,333/- for each month)
    Could any one help me in resolving the issue.
    Rgds,
    Prasad

    Hai Shrikrishna
    Kindly check in the Costing Tab of the Workcenter which u are referring in the Network Activity.
    In the Costing u need to maintain the valid Controlling area , Cost center , Act.type.Int.Processing (Key identifying the activity type used in other types of internal processing in costing like networks) and Formula key for costing (Key which refers to the formula used to determine costs per activity type).
    Unless these are not maintained cannot get the Actual costs(not planned).
    Based on the hours (planned) mentioned in the workcenter , work to be confirmed(CJ20N/CN25/Cn27) to convert the planned hours into costs.
    ENJOY SAP PS.
    Regards
    PP

  • Cost of the project

    Hi,
    My client has delivered 100 bags of material to the customer and Client receive some (for e.g 70 bags)against delivery of material to a particular clientu2019s site as payment against deliver of goods to that project. In this case when Client calculate their Inventory at any particular date  the stock should be 100 bags but the value should be of 30 bags only(Because bill has been received for 70 bags).If client uses this stock for the project,how this value will be taken for cost of project.
    Thanks & Regards,

    HI,
    Pls. check it's thru' T-code CJI3.
    Change layout add material coloum.
    Regards,
    Vishal Kr. Sharma

  • Extraction of actual cost in the project

    hello all,
    Kindly suggest if any function module is available to extract actual cost incurred in the project? The actual cost includes the cost of material consumption, activity confirmation, Fi posting. The intention is to get the total actual cost on the WBS at one place.
    Regards,
    Sudhir

    RESOLVED

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • How To Post an Adobe 7 Project on a WordPress Web Site

    How do I go about publishing my Adobe 7 project on a WordPress web site RETAINING all the interactivity of the project?

    Hello Chaplain,
    You can add a new page in your website from the pages section and once a page gets added you can add media on that page by browsing to the location of your published output .
    Please see the screenshot below :
    As Suggested by Lilybiri you might need to install required plug-in as well .
    Hope this Helps
    Thanks and Regards
    Himanshu Satija

  • Does anybody know how much it costs in the UK to get the front screen of an iPhone4 replaced as it had smashed?

    I have an iPhone4 and I have just smashed the front screen. Does anybody know how much it costs to get this fixed/replaced in the UK??

    You can look this up yourself:
    http://www.apple.com/support/service/
    Out-of-Warranty Service
    If you own an iPhone that is ineligible for warranty service but is eligible for Out-of-Warranty (OOW) Service, Apple will service your iPhone for the Out-of-Warranty Service Fee listed below.
    Please note Out-of-Warranty Repair Service fees from your carrier may be different than those listed below.
    iPhone Model
    Out-of-Warranty Service
    iPhone 5
    £ 186.44
    iPhone 4S
    £ 146.44
    iPhone 4, iPhone 3GS,
    iPhone 3G, Original iPhone
    £ 126.44
    The Out-of-Warranty Service Fee includes a £ 7.44 shipping fee, which applies only if service is arranged through Apple and requires shipping. All fees are in British pound sterling and include VAT. iPhone Out-of-Warranty Service may also be available from your wireless carrier. Pricing may vary."

  • CIP Cost for the Project

    I want to write a query so that i can identify the CIP Cost related to the Projects.
    Can any one help me in this ?

    There is an already existing view PA_CAPITAL_PROJECTS_V , which provides summary information for a project. You can use that as a starting point.
    Thanks,
    Ram

  • How to display Issues for the projects which user can view in the Project Center View

    Hello All,
    In the project center view, at the bottom, we need to add one table, which can show the Issues for the projects that are displayed in the project center view.(Projects visible to the current user).
    Example: A resource 1  can see the Projects Project 1, Project 2,Project 3 in the project center view. So resource 1 should be able to see all the issues that are entered against the Project 1, Project 2, Project 3, irrespective of the issue that has
    been assigned to any resource.
    Please help.

    Hi,
    You could simply edit the page and add the risks and issues webparts. This will display risks and issues assigned to the user.
    Click on edit page, then add webpart. In the Project We App section, pick up the risk webpart and then the issue webpart. Finally drag them to the bottom of the page and close the page.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to transfer and use the project files from Premiere Pro cs6 MAC OS to Premiere Pro CS6 Windows

    Is there any plugin or tool that can help me to transfer my project files along data edited on adobe premiere cs6 MAC OS to the adobe premiere pro cs 6 on windows PC

    When transferring a project from one computer to another,to stop errors such as these, its essential to ensure that the project is copied with all the files and folders in exactly the same locations. Also before opening the project on the new computer, you need to set up a new project and set all the preferences to be exactly the same as on the first computer. Then when you open the project, premiere will find all the files in all the right places. Even then you may need to re-link some files. Just follow the prompts when Premiere asks "Where is file...."
    We use USB hard drives to store students projects on and they are used on many different computers without problems, as the preferences are all set to be the same.

  • How to program lpc2368 of the project in LabVIEW to hex file?

    is LabView 2008 with LabVIEW Microprocessor SDK. also is available microcontroller lpc2368. is there any example of creating a finished hex file, preferably a step by step
    thanks !
    Solved!
    Go to Solution.

    Hi Sergiv,
    I am not sure what you meant by "is LabView 2008 with LabVIEW Microprocessor SDK."
    The LPC2368 is what we call a Tier 2 device. Tier 2 devices provide processor support, but no specific palettes are provided, so this requires you to develop and integrate drivers. That being said, you might be able to use the palettes developed for the LPC2378.
    Were you able to follow the steps mentioned in the "How to CreateHexFile?" discussion forum post?
    Regards,
    Claire Reid
    National Instruments

Maybe you are looking for

  • Isqlplus with  oracle 8.1.7 on Solaris 9x86

    I installed oracle 8.1.7 on Solaris 9x86, all is fine. But I dont see any where that I could use isqlplus through nestcape. Is there any way that I could start isqlplus through my browser. Please help!!!

  • Can't Publish Project

    Periodically, something within Robohelp appears to get corrupt with a project. When that happens, the project compiles without any problems until you click Publish. At that point, a Webhelp dialog displays, saying "Publishing has been cancelled. Acce

  • Debugging in script for  F110 transaction

    Hi all, For bank transfer form i have created a vendor document in FB60 and the corresponding document was created in F110. Script name for this bank transfer form is f110_d_avis.When customizing the script i have taken a z-copy of this script. From

  • Annoying white line around artwork

    There's a strage thin white line around a black artwork, it's easier to see it with red background. It's hard to see it so i zoomed in. Here's the Appearance panel with this object selected: How do I get rid of it? Illustrator CS5 Windows 7

  • No Service message. Works fine with other SIM

    Hi everyone. Been having a really frustrating problem over the last few days. Hopefully someone has seen it before. On Sunday, my Iphone 6 suddenly got a 'no service' message where my signal used to be. I thought nothing of it until after driving 230