How to remove Batch Management in the Material

Hi All,
The Batch Management indicator for a Material was accidentally activated, thus upon goods movement the system required user to enter a Batch Number. The user, not knowing the implications, entered a Batch Number.
Now we want to remove the Batch Management indicator, I already asked the user to reverse the goods movement posted and have the Batch Number flagged for deletion at both Plant and Storage Location Level via MSC2N.
MM02 still won't allow the removal of the tick mark in the indicator.
There are options I have looked at:
1) Create a new Material Code in place of the old one.
2) Archive the Batch Number then try to remove the tick mark via MM02 - will this even work out?
But the priority is still to retain the same Material Code. Is there any other way/option?
Thanks a lot!!! =)

It is a little painful but here are the basic steps.
Remove all stock.
Cancel all demand, no requisitions, no purchase orders,
production orders etc. Transaction MD04 must be empty.
Use transaction MSC2N to place a deletion indicator on every
past batch for that material prior to the end of your fiscal period or
month.
Run transaction MM74 to archive the "flagged for deletion" batch
numbers.
In the next period or month go to transaction MM02 and remove
the batch flag from the material master.
hope it helps

Similar Messages

  • How to Remove batch mangement indicator from Material Master

    Hi
    I am trying to remove batch mangement indicator from Material master..but system does not allow
    Before this .. I have done all activities also ...clear open SD documnets ,deliveriy documents ,PO documents ,Process order teco and . reservations and activae deletion flag in  batch  ... and made current period  stock an previous period  stock zero... i have cleard all documnets ...still system does not allow remove indicator..could you please guide in this issue ..how to remove batch indicator.
    Regards
    Sasi

    Hi,
    Please refer the below links.
    Re: untick Batch Manegement Indicator on Material Master
    Remove batch management flag and deletion of material documents
    How to remove Batch Management in the Material
    Re: How to remove Batch Management Check in the Material
    Thanks.

  • How to remove Batch Management Check in the Material

    I have one requirement to remove batch management check in the materials which should not be deleted.
    I created a testing material with batch management check on and put in material through 561, then did good issue for
    scrapping to remove the stock out. So existing stock is zero in Material Master.
    Then deleted the batch in MSC2N by putting all the delete checks on. There was just one batch created for the material.
    Then ran transaction MM74 to archive, the spool request is as below:
    MCHB: 000000000010000498 2002 1002 D000000200 entry archived                             1 000000000010000498
    Archiving Session Number                                  000004
    Number of Written Data Objects                                1
    Size of Archiving Session in MB                           0,011
    Proportion of Header Data in %                             96,7
    Then in MMPV changed the closing period to may as all the postings were performed in april.
    Now still when I go and remove the batch management check in MM02 Purchasing view, still gives we DISPLAY ERROR message:
    The batch management requirement cannot
    be changed for the follow
    Batches already exist.
    ANY IDEAS why its not allowing me to remove the check as I guess I have performed all the steps required.

    Check whether the batch master is still exists in MSC3N .if it ia archived it should not be avialble in MSC3N
    Refer note:30656
    Reason and Prerequisites
    The message that stocks still exist refers not only to stocks in the current period, but also to stocks in the previous period.
    The reason for checking previous period stocks is that postings can also be made to the previous period when entering goods movements. This would result in inconsistencies if the base unit of measure had meanwhile been changed.
    Solution
    Check whether stocks still exist for the previous period by displaying; for example, the plant stock view or storage location stock view of the material. You do this by selecting "Extras -> Previous period -> Prev. pd SLoc. stock or Prev. pd plant stock".
    If previous period stocks exist, you can make a withdrawal posting as follows:
    1. Post the same amount to current period stock (for example, using movement type 561) so that previous period stock and current period stock are identical.
    2. Make a withdrawal posting in the previous period for the stock together with posting date (for example, using movement type 562).
    You can now try to change the base unit of measure or the batch management requirement indicator again.
    Since the posting of the previous period values to zero is identical with posting to the stocks of the current period, you should reverse the above stock postings (that is, the stock from the previous period should be booked in again) to make sure that the stock values from the previous and the current periods correspond to the state before the change. However, note that the postings are then carried out using the changed master data from the current period (for example, account determination and so on)

  • How to indicate batch managed item in material master

    Dear Frndz,
    where should I have to enable batch management for an item in item master.
    Regards,
    Srini

    Dear Srini,
    You can maintain batch management in Sales:General /Plant (FG),Purchasing view & work scheduling view of Material Master.
    Regards,
    Raja.
    Edited by: Raja on May 12, 2009 7:36 AM

  • Material forgot to tick the batch management but the GR and IR is done

    Hello,
    Material A should be in batch managed but the settings in the material master is forgot to ticked. PO is created as well as GR and IR is already completed. The invoice is posted and according to finance it is paid already and cannot cancel the invoice anymore. When trying to tick the batch management in the material master, an error is "Stocks already exist at plant level". Checking also MMBE, stocks showing in the Open Order quantity since the GR is cancelled.
    Is there anyway I can tick the batch managed in the material master?

    to set the indicator is less restrictiv than removing it. so just make the inventory in current and previous period zero.
    you can see how much inventory you have in thosee 2 periods in MM03  valuation view or plant stock view.
    follow instructions  given in oss note 30656

  • Removal of batch management indicator from material master

    I had removed all batch stock from material code but when trying to remove batch management indicator from material master system is giving the message "batches already exist"
    Please suggest the solution.

    Hi,
       The material is NEW and Batch Managed.  No stocks, orders, batches are existing.
       If the Batch Management indicator is removed in Material Master, is there any way *to see/track the batch/lot * of the product.
    Scenarios: Material is NOT Batch Managed
    1.     How to track a batch received for Purchase order.
    2.     How to track a Batch created in a Production order.
    3.     How to track a Batch in Sales Order.
    Thanks,
    VB

  • How to deactivate batch management at material master?

    Dear Sir/Madam,
    At the configuration,I have set "Batch Management" to be activated in plant level.  I have a problem which some of the plants do not use batch management.I understand that if you tick "Batch Management" field in material master, batch management is activated for the material in that plant.
    1. How do prevent user to tick "Batch Management" field in the material master which appears in the following views (depending on the material types):?
    - Sales: General/Plant
    - Purchasing
    - Plant data/Stor.1
    - Work Scheduling
    2. Is there any alternate way to prevent user to activate "Batch Management" in that material of their own plant despite it is activated at plant level in the configuration?
    Please advise.
    Thanks.
    Rgds,
    Esther Chong

    batch status management is just what its name says, you manage your batches with status (unreastricted use, restricted use).
    But his comes only into place after you have activated batch managment, it is not causing batch managment, it is only working with batch managment.
    Removing batch managment is almost impossible, you have to archive all batches first, to be able to archive the batches, you have to archive the production orders...creation of a new material is in most cases easier and quicker.
    Wit batch managment at plant level each plant can independently decide if a material is batch managed or not.
    if you want to restrict the entry of the batch management flag, then you have to customize your material master field selection at plant level.

  • How to Remeove Batch Management in Material Master

    hi!
    I want to remove the 'Batch management* for a material
    Made stock as 0 and reversed all its relating documents.
    but its display error as
    *The batch management requirement cannot   *
    be changed for the following reasons:
                                                                                    Batches already exist.
    how to remove the Batch management
    Regards,
    Kv

    Hi
    The error tells that some documents are stii pending in previous /current posting period.
    Pl.find that through Mb 51 ( Input only plant).
    Reverse these document also and proceed

  • Removal of batch management for a material in MM02

    Hi all,
      I Have a problem in removing the batch management in the purchasing view of a material.The error is 'Batch management requirement cannot be changed,Batch already exists'.
    PO is created on this material.GR is done and that GR is reversed.There is no stock in the previous period.In MSC2N batch is deleted.I tried even after deleting the item in the PO.Again system is giving the same error.
    Now how can i remove the batchmanagement for the material.
    Thanks,
    Rambhupal reddy

    your batch is probably only flagged for deletion. You have to run archiving, Transaction SARA for object MM_SPSTOCK to get rit of the batch record.

  • How to Setup Batch Management Level (Material vs Client)

    Hi Experts,
    I had a question about the level at which I should be setting up Batch Management. The requirements that we have are:
    - We want uniqueness in the batch being created.
    - We have split valuation active at the Batch Level.
    Hence, we have nailed down to the following 2 options: 1. Client level or 2. Material level. (I know that I will not be using Plant level because we do a lot of STO's and we do not want to lose the characteristics in the Batch at the plant level. So the plant level is out of scope.)
    Client Level: Although the client level gives us the uniqueness and supports most of our requirements, my fear with going at the client level is that it is too rigid and MAY cause problems in the future. Is that true? What would be issues/ concerns that you have faced when you have had Batch Management activated at the client level.
    Material Level: If I setup the system at this level, I would like to be able to create a Batch number for a material across the entire client only once. E.g. MAT1 can have BATCH 123 only once across the whole client. MAT 2 can have BATCH 123 but the Material# and the Batch # uniqueness should be maintained thoroughly.
    I would like to try out this level but my problem is I am unable to understand and setup this level completely. I have gone through some pretty good discussion on this topic but still am unable to understand it thoroughly. The link to this discussion is (http://www.sapfans.com/forums/viewtopic.php?f=27&t=80407). If you refer to this link, it says u2013 Client/ Material Level. What does client/material level mean? Can you please help me understand it. Also, if I setup Batch management at this level, I would like the system to auto-generate numbers for me exactly as I have mentioned above. Is there a way to do so? I was trying to setup the BATCH_MAT number range object with the batch level at Material level but the system seems to always default to the BATCH_CLT level and give us numbers. Is there a way to fix the system to check the BATCH_MAT number range object and give the batch numbering per my requirements. What happens if I use the Material Level Batch management with BATCH_CLT number range object?
    Your help is highly appreciated.
    Edited by: TV_SINR on Jul 16, 2010 8:52 PM

    Check following customizing:
    Logistics General --> Batch Management --> Specify Batch Level and Activate Status Management
    If you want to change the batch level, you have to start conversion to activate the change.
    Note that you cannot reset conversion from plant level to a higher level, read the documentation for customizing of
    "Specify Batch Level and Activate Status Management".
    If you want to work with same batches for different materials, you should use "Batch unique at material level".
    Logistics General --> Batch Management --> Batch Number Assignment
    Here you can define how the system should create batch numbers.
    Best Regards, Dirk

  • Wants to activate batch management for a material which already had a Stock

    hi,
    i want to activate batch management for a material which already has a stock and open Purchasing documents.
    is there any way by which we can do it without removing the same.
    please help.

    program name is RVBCONVMAT2BM
    but i am doubtfull it will be delivered with standard SAP, you need to request you from SAP as they charge for this.
    this program convert the material to batch and all relevant dependant documents will be updated with batch no.
    Regards,
    Pravin Mukkawar
    pasting  some description of the program
    REPORT rvbconvmat2bm.
    Report illustrates the call of function module VBZ0401_CONVERT_OBJECTS
    which sets the batch management flag for one material including
    depending objects. Function module VBZ0401_FILL_BUFFERS helps
    improving the performance.
    then logic......

  • Remove Batch Management and Split Valuation Dependencies

    Hi,
    I need to remove Batch Management Indicator and Split Valuation for a material. Which one should I do first? Are these dependent on one another?
    Thanks,
    Jograd

    You are correct. It did cause lots of error when i tried to do it in test client.
    I am trying to remove the valuation category of one right now. It has zero stock and no open documents.
    I saw in note Note 155874 - Change valuation category in material master that you need to do this:
    2. If you change from split to joint valuation, no valuation data must
    exist for a valuation type.
    I dont know where to start doing that? Because there is not data for the material. However i noticed that there is valuation for previous period. do i need to delete that too? But there are no stocks for the previous period.
    Please help.
    Thanks,
    Jograd

  • Changing Batch Management Level from Material to Plant

    Hi all,
    We are investigating changing our batch management level from material to plant to meet business requirements.
    SAP has pointed us to a note with a program to reset the batch level, as well as highlighting some things to look out for.
    I've conducted the change in a playpen system and so far it looks relatively straightforward, with complexities arising only when characteristics exist, or when a batch exists in multiple plants.
    Seems that batch master data is moved from MCH1 to MCHA, including the object link number to classification. Unfortunately it seems a limitation of the conversion is that the batch master data is copied to ONE plant only in MCHA, no doubt due to the fact the object number link to classification must be unique.
    My question is this: has anyone performed this change before, and if so can you offer me any advice on what to look out for, or potential problems that arose after the change?
    Any help or comments are appreciated.
    Mark.

    hi..
    first of all try this simple one...
    You will have to delete all the materials, remove stock and then switch the batch management flag.
    Or
    To convert the batch from plant level to material there is Conversion Program defind by the SAP...
    1. For all releases lower than Release 4.5B, implement the corrections and the modification in the report RM07CHDX as described in the correction instructions.
    2. Create the report ZCHTCUCH, which is specified in the attachment.
    3. Run this report in the clients for which you want to reset batch level to plant level.
    4. Call transaction OMCT.
    5. Check whether the batch level for "Batch unique at plant level" is set.
    6. Implement Notes 821891, 944278, 950540 and 1091613 if you have not already done so (or you have not imported the corresponding Support Package).
    7. Execute the function "Batch Level -> Conversion".
    8. Define a plant for a plant view that may be missing.
    9. Always execute the report in the test mode first. Analyze the error log.
    10. If no errors occur, you can execute the report in production mode.
    11. If you are working with batch long texts, first execute the report ZM07CHDX_TEXT in test mode.
    try this out..hope is works,,
    Thanks..

  • Is it possible to activate Batch Management for a material without Class?

    Dear Experts,
                           Is it possible to activate Batch Management for a material without having Class & Characteristics maintained. As my requirement is to procure Fuels in Batches only with external no. assignment without any parameters to be checked at the time of Goods Receipt? Batches are needed for Accountability purpose.
    Regards

    >
    Chandan H N wrote:
    > Dear Experts,
    >
    >                        Is it possible to activate Batch Management for a material without having Class & Characteristics maintained. As my requirement is to procure Fuels in Batches only with external no. assignment without any parameters to be checked at the time of Goods Receipt? Batches are needed for Accountability purpose.
    >
    > Regards
    Please check this answered link:
    Batch-classification view
    If you want classify a batch, then you should have maintained the batch classification in material master which is either class 022 or class 023 (depends on your batch level set in cusotmizing). The material class 001 has no impact on the batch classifcition, it is what it is: a classification for the material.
    Edited by: Afshad Irani on Jun 20, 2010 4:40 PM

  • How to setup batch management in sap and how batch work?

    Hi
    I hope to check how batch managment work in sap?
    If we setup batch management in mm03 for one matieral,
    Will the batch number be created automatically or the number should be created first then we scan it?
    when we do goods movement for this mateiral, will system automatically select which batch number is smallest then move that one, or we select one mateiral and scan its batch?
    How batch management control the first in and fisrt out (FIFO) ?
    Thanks
    alice

    Hi
    I think that you have had your question answered so if you are happy with this can you please award points if you want to but mainly can you please mark your question as answered so that it is easier to navigate around the open questions in the forum as the number of pages are growing and growing and it takes too long to go through everything especially if a satisfactory answer has already been given and people like me who want to help will give up and so some people may not get any help.
    Thanks for this
    Frenchy.

Maybe you are looking for

  • Install of Data Services as active/passive behind F5 load balancers

    I currently have two RedHat 5.5 x86_64 hosts, SAP_DS1 and SAP_DS2, and 1 database, Oracle RAC 11g and 1 F5 LTM load balancer sitting in front of the two hosts. The F5 load balancer VIP is set up as active/passive (fail-over) for the two hosts. Will I

  • Get error message when attempting Photoshop CC Update

    I am trying to update Photoshop CC get error message Photoshop Camera Raw 9.0(CC) There was an error installing this update. Please quit and try again later. Error Code: U44M1I210 Can anyone help. Michael

  • Unlocked Original iPhone

    Ok so I used to have tmobile and last summer I bought a hacked original iPhone off of eBay. After 2 months of having it the keyboard stopped working. Well just the last row where the space bar is. I didn't even attempt to restore it I just ended up g

  • Ordinary Depreciation Error

    Hi, I am performing a depreciation run in AFAB and for one asset, I am getting an error that a/c for ordinary depreciation for area 01 could not be found for this asset. I checked the configuration and all required a/c's relating to depreciation are

  • X-Fi I/O Console (upgrade opti

    Where do you find this ? I have searched all over Creative's site and cannot find it. Thanks for any help you can give. Steve