HI BW gurus,
I have 1 process chain which loads data to ZFIGL_01 infocube.But by mistake the process chain got deleted from the meta chain as well as main chain.
Is there any step to recreate the process chain.And will it affect my main process chain which will run tomorrow at 3.30
Please guide.
Regards,
Shailja kaul.

You can go ahead and create the process chain and add it to your main process chain also. After you have done that. Make sure that you activate and schedule it.
After scheduling the Process chain you can go ahead and check for the scheduled job by right click on the start process.
Let me know if you face any problems
Regards,
Abhishek

Similar Messages

  • How to find deleted process chain and query

    Hi All
    Some body has deleted one process chain and one query from development system
    how can i know who has deleted these?
    is there any table where deleted process chain and queries will maintain????
    Thanks & Regards,
    Krishna
    Edited by: krishnamurthy g on Sep 1, 2008 5:33 PM

    Hi,
    Usually its totally in tractable to find a deleted chain :
    But you can try out with the following options:
    1> T-code SLG2 .
    2> T-code SLG1 - find out who was logged on to the system on that particular client at that time.
    3> Try out the following tables in se16 :
    RSPCLOGS           --- Application Logs for the Process Chains
    RSPCLOGCHAIN    --- Cross-Table Log ID / Chain ID
    RSPCCOMMANDLOG --- System Command Execution Logs (Process Chains) .
    Hope it will be expedite.
    Thax & Regards.
    Vaibhave Sharma

  • H how to find  if the psa table is included in psa deletion process chain

    Hi all
    can anybody tell me .
    I have a psa table it's technical name is /BIC/B*
    h how to find  the  above psa table is included in psa deletion process chain or not
    please help me

    Hi
    Ope the PC in RSPC1 -->go to planning view of process chain
    in left side you will find different types of process types.
    under other BW process types folder -->you will find process type "Delete request from PSA"
    drag this into your process chain planning view and customize it based on your requirements.
    check the below article for step by step procedure
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/a02ba9e7-bb6f-2c10-09b4-e86b9fcbad41?QuickLink=index&overridelayout=true
    Regards,
    Venkatesh

  • How to reuse the process chain which has been deleted?

    hi
    guys
                  how to reuse the process chain which has been deleted?
    your regards
    suresh

    if you want to "recover" the deleted process chain, try to check DEV / QAS / PRD. Maybe there is a copy still available
    Or check the following tables in SE11: RSPCCHAIN / RSPCCHAINATTR
    Good luck !

  • How to Delete Process Chain?

    How to Delete Process Chain?

    When in the change mode of a process chain, choose the menu entry 'Process Chain --> Delete' (Only available on change mode).
      Cheers
       SAP NetWeaver 2004s Ramp-Up BI Back Office Team

  • How to collect and move the deleted process chain to Prod.

    Hi,
    I have a process chain (BI 7)that is already in D,Q and P and now I want to delete a Process Chain under "Display Component" and my question is how to collect the deleted process chain to move all the way to Q and P.
    Waiting for your response
    Regards,
    Sunil

    Hi Srinivas,
    Thank You ,I was scared that i dont get any request to collect and my problem is resolved.
    Regards,
    Sunil

  • How to get back deleted Process chain?

    Could some one aid me in getting back the deleted process chain, in production?
    Thanks in advance....

    Hi..................
    It is not possible to get it back...........Since generally we don't create Pc in Production Server.......
    If it exist in you Development or Quality Server.............again transport it from there....
    Regards,
    Debjani..........

  • How to activate the deleted Process chain

    Hello Experts,
    Unfortuantely we have deleted few process chain by in RSPC .But we are in need of this Process chain . Could you please let us know whether there is any possibilties to get back the deleted process chain .
    Please let us know where the deleted process chains are stored in the system.
    Many Thanks for your Help.
    Regards,
    Kumar

    Hi,
    you can restore it from a backup or in case the chain was transported from one of the target systems or the development system. No other way.
    regards
    Siggi

  • How to delete Process Chains

    Hi Experts,
    I created Process chain for Deliveries in D sys and transported to P sys. Here we have six source systems so  first we created 6 process chains for each  source systems. Later we decide to add all those variants in one Process chain and we deleted individual process chain and transported to P sys.
    So Process chains are deleted in D system and P system but changes are not effected in P system. Process Chains are not invisible both D & P systems.
    But when we run the Deliveries Process chain, deleted Process chains are also running. And getting Error due to both are scheduled at same time. Because deleted Process chains are still showing in where used list....
    Can any one help me guys!!!!
    Thank you,
    Suresh

    Hi Suresh,
    Can you please let us know what type of scheduling option you have used in the start variant.
    Also please have a check if the start variant in all the chains are the same?
    As per my understanding unless the start variant is triggered the chains will not get scheduled.
    Also there is a bug in Bi7.0, that once the process chain transport has been completed to other environemt its starts getting executed if the start variant hold tha option as Direct scheduling - > Immediate.
    Prathish

  • How to delete Process Chain Variant

    Hi  all~
    I'd like to delete Process Chain Variant .
    But I can't find delete menu from RSPC.
    It could be easy, but... I can't find it~ ^^;;
    Thank you in advance~ ^^;;

    Hello,
    1. Select the necessary process type from the menu.
    2. Type in the technical name of the variant and click change button.
    3. When maintenance screen is opened you can delete the variant by clicking delete button.
    or
    chk the tables for your variants :
    RSPCVARIANTATTR
    RSPCVARIANT
    RSPCVARIANTT
    RSPCTRIGGER
    Or you can go to maintain variant for any existing variant and choose your variant form the list, delete it.
    Regards,

  • How to kill a process chain in an intermediate step...?

    How to kill a process chain in an intermediate step...?
    I have tried doing it using SM37... but still the chain is hanging....
    Please help ASAP...
    Regards
    Sneha

    Hi Sneha,
    If its a loading process then:
    1. Go to monitor & make its overall status RED.
    2. Go to the target & make the QM status RED.
    3. Since its loading data to BW, its R/3 will be active even if you make any status RED in BW.
    4. Cancel its corresponding R/3 job. U'll get its R/3 job from monitor>Header tab>Job name. Copy that job name& go to R/3 side>sm37>in Job name add B*followed by the job name copied & then delete the Active job.
    Once this is done then your loading process will anyhow stop further stopping the Process chian.
    If your job is other than loading, then simply go to that process chain & remove the link between the active process nad the next process after cancelling the active job (as mentioned in the various replies for your question).
    Give some time to update the staus of that cancelled job in Db, because even if you cancel any active job, it requires some time to refresh it updated status. Once it is cancelled you can rejoin the link between the proceses and reactivate & schedule your process chain.
    hope it'll help

  • How to schedule the process chain fr the report

    hai experts,
    i have a query which i need to generate for every five hours? i know that we can generate the report thr process chain but i dont know how to build that..
    my question is how to schedule the report,how to build the process chain,....
    can any one plz tell me how to start this generating report for every five hours
    thanks in advance..points will be alloted surely ,i need this urgently..
    Suri

    First of all you need to Identify the InfoObjects if you want to take up Master Data Loads, and if you want take up transaction loads then select the Data Targets to which the data has to be updated. Then plan the dataflow accordingly.
    You want to create a Process Chain, Go to RSPC, and then select the create option and from the Process categories available on the left handside drag and drop the Start process, then define the Variant for the same. In the same way you need to identify the other Process Types available on the lefthand side. For Eg: Start Process>Load to ODS>Activation of ODS Data>Delete Indexes for the InfoCube>Load to InfoCube>Create Indexes>Delete Overlapping Req-->Agg. Rollup.
    This is how you need to specify the dataflow, several other Process Types also included based on the requirement For Eg: Sending Mail Alerts when the Job is Success or Terminated.
    Also, have a look at this links to make urself clear about the steps in creating Process Chain.
    http://help.sap.com/saphelp_nw04/helpdata/en/67/13843b74f7be0fe10000000a114084/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    Hope it helps.
    Regards,
    Archna

  • How to Improve Delete Process

    How to Improve Delete Process for File Reloads of Same Month of Data on Cubes.We currently use a SAP generated program for selective deletion to do this.  It would be more efficient to delete by InfoPackage request (or packet) and use delivered processes in process chains to do this.How can we use the more efficient delete processes in the process chains to perform the task.Could u explain me with steps as it would be more clear

    How to Improve Delete Process for File Reloads of Same Month of Data on Cubes.We currently use a SAP generated program for selective deletion to do this.  It would be more efficient to delete by InfoPackage request (or packet) and use delivered processes in process chains to do this.How can we use the more efficient delete processes in the process chains to perform the task.Could u explain me with steps as it would be more clear

  • Deleting process chain

    Hello,
    How to delete process chain?

    Hi Roy,
    You will save the chain to reflect changes however when you schedule the process chain you will click on Activate and Schedule(F8) to run the chain..
    Activation will be done when you schedule the chain..
    Thanks,
    Sudhakar.

  • HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING IN THE PRODUCTION?

    HI ALL,
    CAN ANYONE TELL ME HOW TO STOP THE PROCESS CHAIN WHICH IS RUNNING DAILY AT 5.00 PM. I NEED TO STOP THE PROCESS CHAIN FOR COUPLE OF DAYS AND THEN RESTART IT AGAIN.
    cAN ANYONE TELL ME THE PROCEDURE TO STOP THE ENTIRE PROCESS CHAIN RUNNING IN THE PRODUCTION.
    THANKS
    HARITHA

    Hi,
    First and foremost let me advice you to be very careful while doing this.
    For Rescheduling
    RSPC> chain > Goto > Planning view and
    click on Execution tab > select > Remove from Schedule and then in Maintain variant of start process reschedule for the day you require it to run.
    For terminating active chain
    You can start from SM37, find the process WID/PID then go to SM50 or SM51 and kill it. Once its done come back to RSMO and check the request, it should be red but again manually force to red and save by clicking on the total status button in the status tab. This shuld ensure that the process is killed properly.
    The next step will be to go to targets that you were loading and remove the red requests from those targets.
    Note: For source system loads you may have to check if the request is running in the source system and kill if needed and pull it again.