How to reverse network cost

Hi All,
Can someone tell me how to how to reverse network cost
done thru cj9k
to bring back the project to its originall status
Thanks,
Regards,
Mercy

Hi Mercy,
The CJ9K do the plan costs calculation,  the FI posting and purchase cause the actual costs and commitment. They have nothing to do with each othter.
To reserve the plan costs is somehow strange requirement. To remove the costing reporting information, the CJEN (with delete flag set) may the right one.  But there is no transaction to reserve the plan costs.  You can initialize the costs relevant information, e.g. planned work = 0, then re-calculate the network.
Kind regards,
Zhenbo

Similar Messages

  • How to Reverse Landed Cost

    Hi,
    How ro Reverse Landed

    hi,
    choose Data from the menu bar and choose Cancel. After you cancel the landed costs document, it is impossible to create a journal entry for it or to make any changes.
    The status Cancelled appears in the Journal Remarks field.
    Jeyakanthan

  • How to reverse landed cost on open A/P Invoice

    Dear Support
    Please be so kind to assist wiht the following issue: I need to reverse landed cost from a open A/R Invoice #  72223
    Purchase Order #  125025
    Goods Receipt # 16426
    Landed Cost 15332
    A/P 72223
    If i select the A/P invoice and copy to A/P Credit memo and preview the journal remarks first, the following error occurs
    "Quantiy falls into a negative inventory"
    My Question however are if I do proceed with this function, will this rectify the landed cost?
    Please view the screen shots attached for investigation as well as the journal remarks on each document
    Inventory Posting List:
    The reason for not posting to the stock account is because the AR Invoice was been done before the landed cost has been processed:
    At the time of landed cost there were no stock on hand, this has been the reason why the amount has been posted to the Price difference ledger account  and not the stock account.
    Your response will be much appreciated
    Kind regards,
    Ilze Fourie

    Dear Nagarajan
    Thank you for your response, much appreciated!
    Attached please find the screen shots
    Kind regards,
    Ilze Fourie

  • Reverse Planned Costs

    Can someone tell me how to how to reverse Planned Costs by the transaction CJ46. I need reverse planned costs, but can not by transaction CJ46.
    If there is any way to launch a negative cost estimate also serves.
    Thanks
    António Pinho

    Not work
    But thanks
    Edited by: FPinho on Feb 8, 2010 5:25 PM

  • Reversal of cost from the  WBSE & posting same into assigned network

    Hi,
    There is requirment of reversal of cost from WBSE & posting the same into assigned network of WBSE. The scenario is like this. actual cost will get posted into WBSE during PGI of materials during delivery in VL02N transaction. Whereas we don't want cost posting into WBSE & sam cost should be posted into network / acitivty.
    Please advise me on this.
    Thanks

    Hi,
    Reverse the document & put account assignment Network/Activity instead of WBS.
    Regards,
    Vishal Kr. Sharma

  • How to reverse payment scheme request line which has origin as RO

    Hi Experts,
    I have a requirement to reverse the payment scheme request line.
    need help on this how to reverse this line item.
    Regards,
    Lalit

    Hi Praveen,
    Thank you very much for your reply. I appreciate your time and efforts.
    Ok, these are the steps how I have executed the process.
    - I have created a service contract for an equipment. In the service contract, I have maintained the service material in the line item, maintained price and assigned equipment in the technical objects.
    - I created service notification, which automatically picked up contract.
    - When I create service order, from notification screen, system automatically picked up correct order type SM01 (Service order with contract).
    - Then I planned operations and spare parts in the service order.
    - Checked settlement rule in the service order is SDI.
    - released and saved service order.
    - Using IW42, in SAP ECC6, you can perform  both time confirmation and material consumption using the same screen and also TECO service order. System issues message to say, goods issue have been posted.
    - when you check the document flow of service order, you can see operations posted, and also goods issue posted.
    - check cost tab to see actual costs. (if I want to settle costs from service order to service contract, I can do so w/o a problem in KO88)
    - Use DP90, enter service order number and create billing request. System takes to billing request screen but it is blank. No line items.
    - So, since there is a contract, in this case, am I meant to be creating the billing request from Service contract? instead of from Service order?
    I hope I have clarified myself better this time.
    Best regards,
    Abdul Rafey

  • Network costing stored in CO version 1 or 2

    Hi All,
    Can we use the CO version 1 or 2 for network cost planning otherthan 0 and how?
    I want to store the network cost planning in CO Version 1 or 2 and not in version 0.
    Regards
    Muzmail

    Hi Amit.Amerash,
    Actually the problem with my client is that they are planning materials/services to the project from time to time.There is no single time material planning so it will create problem while running RA because system will post wrong COS to the project.
    So i was thinking that if possible to store network costing in version 1 and i can do manual cost planning in 0 for system to post exact COS .otherwise i have to tick off the addititive indicator for order cat 20 in OPSV.
    I want to see both network cost planning and manual cost planning in the system.
    Regards
    Muzamil

  • Reversal of Cost Price Update and Price Change MR21

    Dear SAP experts
    Recently (on 1st of this month) i did cost price update for all my FIG items. Later i realized that some of FG items cost price was not accurate. So i want to delete cost price of those items and update price by using T code MR 21 
    When i try to cancel these items cost price by using T code CKR1, i am getting error message that particular material current or future standard price is avialable and i am unable to move further
    Please guide how to delete current cost price of these items and update cost price by using MR21. Please note these items does not have any BOM and basically are contract manufacturing items
    Thanks in advance

    Hi Vedsai
    When you use CKR1, it does not give error.. It just gives a warning message
    Enter your Plant / Mat in CKr1 and select "Current cost estimate" or "Future Cost Estimate" as the case may be
    If any warning comes, ignore it and press enter.... It should reverse the cost estimate
    Now update from MR21 or preferably use CK11N again
    Note: If at all it gives any error in CKR1, check in T code OPR4_CK if this msg can be converted into warning message
    Regards
    Ajay M

  • How much does this cost? & I still can't understand how this work

    How much does this cost? & I still can't understand how this work

    Hello mkopti,
    ePrint is a free feature include on most of our wireless printers that are e-all-in-one enabled. It allows you to register your printer on HP's website http://www.eprintcenter.com and create an account. Once an account has been created you can enable the web services feature, after connecting to a valid network with internet access, which will print off a registration code you can use to add the printer to your account and customize an email address for the printer. This allows you to print to the printer from virtually anywhere simply by sending an email to the printers email address and when it is received it will print.
    Most of these printers are also Airprint enabled meaning you can print locally from the same network on the iPad, iPod, and iPhone (version 4.3.2 and higher) by using the built in "Print" command in the idevices.
    If you have any other questions or need clarification feel free to reply to this post and I will try to answer any questions you have.
    If I have solved your issue, please feel free to provide kudos and make sure you mark this thread as solution provided!
    Although I work for HP, my posts and replies are my own opinion and not those of HP.

  • Re : How to reverse Depreciation documents for assets

    Any body please tell me. How to reverse the Depreciation documents for Asset accounting.

    Hello Ramu,
    Asset transactions have to be reversed using the reversal transaction of the application in which the original transaction was posted (for example, invoice receipt). You automatically go to the appropriate reversal transaction when you choose Postings-> Reverse document.
    In addition to the reversal transactions for documents created in Asset Accounting, there are also the following reversal transactions in the applications integrated with FI-AA:
    Reversal of external acquisition with vendor (Accounts Payable)
    Reversal of acquisition with purchase order reference (goods/invoice receipt)
    Reversal of retirement with customer (Accounts Receivable)
    Procedure
    Choose Postings ® Reverse document ® Other asset document.
    Enter the asset.
    Press Enter
    Select the document to be reversed.
    Choose the Reverse function.
    Below mentioned is the procedure for reversing Settlement of an Asset Under Construction
    Choose Postings->Reverse document->Cap. asset u. const.
    Enter the asset under construction that was settled.
    Press Enter
    The system then reverses all documents that were posted during the last settlement.
    If you want to reverse a settlement that was posted before the most recent one, you first have to reverse all the settlements, which were posted after the one you want, in chronological order.
    You cannot use this transaction to reverse the settlement of assets under construction that were only managed for cost accounting.
    Reward points if i had been of help to you.
    Rgds
    manish

  • How to calculate the costs of every item categary in costing run

    Hello Experts,
    Could anyone explain how to calculate the costs of every item categary when I carry out the costing run. For example, item categary: M, E, G.
    Thank you in advance.
    Maria

    This Applesctipt will add comma's to the file count:
    (Copy into Applescript Editor, and Save as File Format: App, then just click the App to run)
    set x to choose folder with prompt "Choose Folder to Count Files" default location alias (the path to pictures folder as text)
    set filecount to do shell script "find " & POSIX path of x & " ! -type d ! \\( -name \".*\" -or -name \"Icon*\" \\) | wc -l"
    display dialog "File Count: " & comma_delimit(trim(filecount))
    on trim(someText)
              repeat until someText does not start with " "
                        set someText to text 2 thru -1 of someText
              end repeat
              repeat until someText does not end with " "
                        set someText to text 1 thru -2 of someText
              end repeat
              return someText
    end trim
    on comma_delimit(this_number)
              set this_number to this_number as string
              if this_number contains "E" then set this_number to number_to_text(this_number)
              set the num_length to the length of this_number
              set the this_number to (the reverse of every character of this_number) as string
              set the new_num to ""
              repeat with i from 1 to the num_length
                        if i is the num_length or (i mod 3) is not 0 then
                                  set the new_num to (character i of this_number & the new_num) as string
                        else
                                  set the new_num to ("," & character i of this_number & the new_num) as string
                        end if
              end repeat
              return the new_num
    end comma_delimit

  • How much will it cost for an out of warranty repair for a water damaged iPhone 4S in the UK?

    How much will it cost for an out of warranty repair for a water damaged iPhone 4S in the UK?
    I got water in my iPhone 4S (not drenched as it was within a LifeStyle waterproof case).
    I dried it out in a bowl of rice, but the phone no longer charges, will not allow wifi, cannot locate network.

    You have to get a refurbished iPhone. As your phone is out of warranty, you will have to pay £139 at an Apple Store in order to get it > http://support.apple.com/kb/index?page=servicefaq&geo=United_States&product=ipho ne

  • How much does it cost to replace iPad USB port, How much does it cost to replace iPad USB port

    How much does it cost to replace the USB jack inside my iPad because it won't connect to the computer

    Istvan1 wrote:
    How much does it cost to replace the USB jack inside my iPad because it won't connect to the computer
    Have you tried going to Reset/General/Reset/Reset All Network Connections?

  • How do I network my desktop printer with my other MAC laptops? I forgot how to do it in the settings

    How do I network my laptops to my printer? I forget what steps to use in Settings.

    You posted in the iMac (PPC) community.
    You would do better by posting in the "laptop" forum of the model "laptop" that you have.   Your questions has nothing to do w/iMacs (PPC).

  • Hi, I was just wondering how much it would cost to repair the rear camera of my iPhone 4s. I dropped it and it won't work and I hear something rattling inside when I shake it. How much would it cost to fix?

    Hi, I was just wondering how much it would cost to repair the rear camera of my iPhone 4s. I dropped it and it won't work and I hear something rattling inside when I shake it. How much would it cost to fix?

    If you have a tool, try removing the battery cover and chech out. Some times the camera pin may have been misplaced. If so, you can fix it yourself.

Maybe you are looking for