How to track/check on which production orders are not confirmed yet?

Dear Experts,
Is there any transaction or processes to check,only those production orders which are not confirmed yet?
Besides the transaction code, I would kindly like to request you to provide me a small overview of it. Your support will be really  appreciated.
Thank you in advance!
wishes,
jeevan

Hi,
Please refer the below screen for COOIS report. Please check on Sys status as CNF Excl. It will show you all the orders which is not with CNF.
COOIS/COOISPI (For process industries) is very useful report where you can see entire details of orders. You can see report both on planned order and production/process order. As well the report can be seen in several level like header, component, operations etc..
Different layout for display is also possible for different users.
Please try it by different options. You will find the functionality of the Transaction.
Regards,
Krishnendu.

Similar Messages

  • STOs and Productions order are not lined up. Dates are off

    Hi Experts
    I have a production order and STO with different dates. I would expect no gap between Prod order and the STO. I have checked Planned delivery time,GR/GI at both supplying and receiving plant . Everything looks fine. Please Advice

    Ganpath,
    In general, both of those objects are executables.  In most applications, the relationship between the dates of STOs and the dates of Production Orders is not directly determined by the software,  It is only through careful design and execution of the overall process that you achieve dates that line up; assuming, of course, that is your business requirement (not everyone wants dates to line up).
    So, it depends upon how these two objects were created.  Can you please describe how they were created?
    Best Regards,
    DB49

  • How to restrict the GR for Production Order when Goods Issue is not done

    Hi Gurus
    How to restrict the GR for Production Order when all the required components for production order are not issued with all required quantity. Even for partial issue system should not allow GR with 101. The user status with RMWA, RMWF & CGFB is not working.
    Pls suggest best solution.
    Abhijit.

    Hi,
    You can club together the GI nad GR at the time of confirmation..
    I.e Backflush for the components and auto GR for the Product.
    So that you can stream line the Process.
    The best Option would be to use the User Exit:
    Enhancement - MBCF0002
    Functional Module - EXIT_SAPMM07M_001
    Include - ZXMBCU02
    Refer below link for further details..
    How to stop the goods receipt before issueing the goods for production orde
    Regards,
    Siva

  • Production order number not consecutive

    Hi,
        Under the same order under the same number range the numbers generated for production order are not consecutive .
    For eg: A production order 10000351
    the next production order number generated is 10000451 etc...
    why is it jumping ..It would be greatly helpful if anyone can answer..

    Hello,
    Yes, this is a critical problem..
    The Production Order numbers jump from one number to the next number without any logic.
    As you sais, for eg. after XXXX1234 it will jump to XXX1241, and for the very next order tha order number may be XXX1452..
    This is because of the Number range buffer which we maintain in "SNRO" (Prod. Order - AUFTRAG)..
    Edit --> set Buffer -- > Main Memory.
    Reduce this buffer to the Minimum and test this in your Test System.
    For further details carefully gothrough the Links below.
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/b4/185f28179c4f3cb8d00988cd139500/frameset.htm
    How the Number Range Buffer Works:
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/95/3d5540b8cdcd01e10000000a155106/content.htm
    Administration of the Number Range Buffer
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/aa/dbc9b4b56143bb8f2ae909d7d040fa/content.htm
    Hope this helps..
    Regards,
    Siva

  • How do we Prevent Creation of Production Orders for Phantom materials.

    Dear Experts;
    We have some materials which are Phantoms.
    We have set "special procurement type" as 50 in MRP2 and "Strategy Group" as 59 in MRP3
    These are non stchable items, but have BOMS.
    We dont create orders for them, however at the mement the system allows order creation. How do we prevent creation of production orders for these items in the system.
    Thanks in Advance
    Richard.

    Dear Richard,
    Check using this BADI - WORKORDER_UPDATE using method IN_UPDATE or Release by including a check if MATNR and for
    WERKS combination if SOBSL = 50 from table MARC,then do not allow to save.
    Check whether this works or else you have to set a plant specific status using OMS4  for not allowing production order
    creation and assign this value in the material master of the phantom assemblies.
    Check and revert
    Regards
    Mangalraj.S

  • How to get change date in Production Order ?

    Dear Friends,
    I want to know it, how to get change date in Production Order "Administration-TAB".
    F1-Help, It is displayed with "Change date for Order Master". and Structure table "CAUFVD".
    But, CAUFVD is not Transp. Table.
    Which table should I read ?
    Thanks in advance
    Yamazaki-H

    Dear Friend
    Thank you for an answer.
    It was settled.
    Best regards.

  • How we can Reverse the closed Production Order (REVERSAL)

    Dear All
    How we can Reverse the Closed  Production Order Which one is confirmed before 5 or 6 month ..Actually i want to reverse the production order  with old pricing.Not with present pricing.
    Rgds
    Pankaj Agarwal

    You can reverse a production order using fucntions --> Restricit Processing --> Revoke Closing.
    But if you want to reverse the materials consumed with the older pricing it is not posible as per my knowledge, as the periods would be closed and you can only reverse in the present period and also that all the settlements would have affected on the order and material.

  • How to output serial number from production order in GLM ?

    how to pull serial number from production order in wwi template for GLM ?

    Hi,
    Please have a look to this thread:
    BAPI/RFC to get serial numbers for a production order
    Hope it helps,
    Kr,
    m.

  • How to find system status for production orders?

    How to find system status for production orders?
    looked into table AUFK, AFKO and AFVC but none of these tables, carry
    system status as part of the fields(STTXT)
    I tried to filter in COOIS, but not much help
    Able to find system status information in COHV,Is there any other way where
    I can find system status information for production orders
    Kindly guide

    Hi,
    Look into table, JEST, JSTO, AFPO & AFKO. CAUFV filed OBJNR, TJ02T filed ISTAT.
    But, it is very difficult to combine the details like Order and System status.
    Take the help of your ABAPer to generate Report for you.
    Regards,
    Siva

  • How can i check my iphone production details by any site?

    how can i check my iphone production details by any site?

    Exactly what do you mean by production details...manufacturing, hardware?
    Try http://www.everymac.com
    They have listings for just about eveything made by Apple.

  • How to track materials shipped by the Vendor but not received

    Hi,
    Can anyone explain how to track materials shipped by the Vendor but not received at the customer plant?
    Thanks in advance

    You can use confirmation control in PO for tracking
    1. OMGZ to Configure Confirmation control.
        Here  you can specify the order in which you expect confirmations from your vendors.
    2. MK02 - to assign Confirmation Control to Vendor in Purchasing View.
    3. To view acknowledgments that have been received,
        in PO choose Item --> Confirmations --> Overview
    Check this out-
    http://www.sap-img.com/materials/explain-about-the-po-confirmation-control-key-in-detail.htm

  • Production order should be confirmed before in-process inspection UD

    We guys,
    I have activated the In-process inspection for one Finished goods and inspection lot is getting created when Production order released. This production order can be confirmed without UD for In-process inspection lot.
    Please let know How can I control that Production order should not be able confirm before UD of Inspection lot for in-process inspection.
    When production order released it means an production has just starded. Then What is the meaning in getting the inspection lot created on release of production. I think it is supposed to be on completion of each opration.
    Please give your inputs.
    Thanks
    Dhanu

    Hello
    inprocess inspection are used to assisst you to record results , defect , rework, during the production operation. It is defined to get created during the release of the order. It gives QM personnel a control over the quantity confirmation. You can do the result recording based on time and quantity.
    Operation confirmation and UD are independent and it will not be possible to do confirmation once you do the UD.
    The controls that can be brought in 03 inspection for a better usage
    1) Result recording mandatory for all inspection points
    2) QM operation can be confirmed only by QM personnel
    3) At the time of GR of the order check whether UD for the lot is given. Make UD mandatory for GR of the order
    4) Only after QM operation confirmation the next operation can be confirmed
    5) make use of Rework to capture rework cost and First Pass Yield
    Hope this gives some picture to you
    Regards
    gajesh

  • How to control goods receipt for order by mb31 if order is not confirmed

    Hello friends,
    I want to restrict the goods receipt for process order if order is not confirmed or partially confirmed.
    Through user status i can control that if order is confirmed than whether to allow goods reciept or not.
    But how to achieve my above requirement.
    Thanking you guys in advance.

    Dear Jitendra,
    Check this link
    How to stop the goods receipt before issueing the goods for production orde
    Regards
    Mangalraj.S

  • Are AUR packages signed? How do I check the signature if they are?

    Hi,
    Are AUR packages signed? How do I check the signature if they are?
    Thank you!

    andreicristianpetcu wrote:Thank you for your answers! Some Aur packages basically wget some tar.gz and uncompress it and I wanted to know if there is a way to test if this is the same archive that I wanted to install.
    Archives downloaded by PKGBUILDs are never the same as the archive you want to install. Are you referring to PKGBUILDs which just repackage .deb or .rpm archives? As mentioned, there's checksums (typically of zero benefit to security), and sometimes GPG signatures provided by upstream. But, this is only a part of the process. The attack surface is wider than just the source tarball and the PKGBUILD. Consider that you don't even need a PKGBUILD to create a package which pacman understands.
    andreicristianpetcu wrote:I told him that this cannot be done on most packages on most GNU/Linux distros.
    No, it absolutely can. All operating systems are prone to attack by social engineering and can fall victim to lax system administration. The "Linux doesn't get virii" mantra is a falsehood propagated by people relying on statistics rather than actual operating system features and security practices.
    andreicristianpetcu wrote:Since I am a Arch user I wanted to find out if there is a way (except for reading the pkgbuild) from which I can check the validity of the package.
    Given an arbitrary archive foo-1-1-x86_64.pkg.tar.xz, there is absolutely no way to determine what PKGBUILD was used to build it. This is a key reason why signing binary packages in the repositories is important!
    andreicristianpetcu wrote:From what I know the files from the other repos are signed (correct me if I'm wrong).
    Right, in order to assert provenance of a package. If the signature for a package is valid, you can assume that you have a copy of the package which a developer or TU built.

  • Production order status - Finally Confirmed

    Dear Team,
    I would like to know the date on which the production order has got the status 'Confimed' (no more confirmations are possible on this order). In which table the final confirmation (last confirmation for this order) date is stored?
    Also i would like to know for a given production order, weather goods movement is allowed or not? In which table this info is stored?
    your input required
    regards
    psk
    Edited by: psk.psg on Jan 18, 2012 11:22 AM

    HI PSK
    All confirmations of production orders are stored in table AFRU - details fields are - AUFNR- order no, BUDAT- posting date, RUECK- confirmation no & all activities etc.
    Goods movement allowed or not is controlled through order status ( say if the order is not released it wont be allowed) , further if the order is locked no goods movmt, then if the orders are TECO goods movment may be allowed or not depending on config setting. If order status is business completed no movment alloed
    shakti

Maybe you are looking for

  • Down Loading ALV Output to Excel Sheet

    Hi All, I am working on Vendor Line Items Report which have both Header details as well as line item details. So i developed Heirarical ALV to display the output and it is working fine.But my problem is Downloading output to Excel sheet functionality

  • First Try with JE BDB - Indexes and Inheritance troubles... (FIXED)

    Hi Mark, Mark wrote: Hi, I'm a newbie here trying some stuff on JE BDB. And now I'm having I am happy to help you with this, but I'll have to ask you to re-post this question to the BDB JE forum, which is... Sorry for the mistake. I know now that her

  • Useing With An External Display

    Is there anyway that you can plug a macbook into a projector or monitor and close the screen. for example, watching a movie. I have already bought the mini-DVI to VGA adapter works great but cant figure out out to close screen

  • Asset Number in As01

    Dear Expert,     Can I generate asset number externally in AS01? Please confirm. Regards, David

  • How to create a sequence of flashes ...

    hey i'm trying to create a simple version of a simon says game. where the applet will have (some image) and it will flash (some image) in differnent sequences. i want it to randomly choose a sequence - that's the first part... then I would like to ha