Factory calenders are downloaded to CRM from ECC, using adapter object DNL_CUST_CAL_C in Initial load (R3AS).  My doubt is, whenever a new holiday is added to Factory calender in ECC, how the particular added holiday will be downloaded to update the same in CRM system?
Please help me.
Regards,
Maddy

Hello Maddy,
In my system download object DNL_CUST_CAL_C is for the download from the CRM (online) database to the old consolidated database (CDB, for the offline Mobile Sales scenario). You could see this in transaction R3AC3.
For your scenario I don't know how to download. This thread here speaks of a manual adjustment in transaction SCAL.
http://scn.sap.com/thread/274825
Best regards,
Thomas Wagner

Similar Messages

  • How to Transfer factory calendar to APO from ECC

    Dear friends,
    I came across the statement in SCM210 material that factory calendar can be transferd from ECC to APO. If anyone knows about it can you please explain me with steps?
    Sree

    Sree,
    you can transfer the factory calendars from ECC to PAO following these steps:
    in APO:
    Transaction RSA1
    Select Source systems>SAP>your R/3 client.
    Right click on the client>Select Transfer Global Settings.
    Select Factory Calendars
    Select Rebuild tables
    Cheers!
    Abhi

  • How to extend factory calender to a plant ?

    Hi Ranga:
    How to extend factory calender to a plant ? ( Tcode: SCAL, The calender is not client specific)
    I check marked US factory calender, where after can you tell how to extend factory calender to plant
    Note: I am using IDES ( International Demonstration & Education System)
    Thanks

    Hi Sandeep,
    you need to use the following path
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Here you need to assign the factory calendar. The assignment in work center will only applicable for capacity not for MRP and others.
    <b>For information how to create a factory calendar</b>
    Pl follow the steps
    1.Go to SCAL transaction
    2.there will be three options.
    Click first public holidays and go in change mode.
    Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)
    3.Now click Holiday calendar and go in change mode.
    Click create and give holdiay cal id and description.
    Click assign public holiday and add your holidays one by one and save
    Now holiday cal is created.
    4.Now come out and choose fact calendar and go in change mode
    Click create and give Factory calendar id and description, and validity period.
    Give the holiday calendar ID.
    If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define)
    and save.
    5.You have to assign factory calendar to PLANT
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Choose your plant and go to details-
    You have to define factory calendar there
    Hope this will help you
    Regards
    Ranga

  • How to update my mac book pro from 10.5.8 to the leatest version

    how to update my mac book pro from 10.5.8 to the leatest version

    Upgrading to Snow Leopard, Lion, or Mountain Lion
    Upgrading to Snow Leopard
    You can purchase Snow Leopard by contacting Customer Service: Contacting Apple for support and service - this includes international calling numbers. The price is $19.99 plus tax. You will receive physical media - DVD - by mail.
    Third-party sources for Snow Leopard are:
    Snow Leopard from Amazon.com
    Snow Leopard from eBay
    After you install Snow Leopard you will have to download and install the Mac OS X 10.6.8 Update Combo v1.1 to update Snow Leopard to 10.6.8 and give you access to the App Store.
    Before upgrading check that you computer meets the minimum requirements:
    Snow Leopard General requirements
      1. Mac computer with an Intel processor
      2. 1GB of memory
      3. 5GB of available disk space
      4. DVD drive for installation
      5. Some features require a compatible Internet service provider; fees may
          apply.
      6. Some features require Apple’s MobileMe service; fees and terms apply.
    Upgrading to Lion
    First, you need to upgrade to Snow Leopard 10.6.8 as stated above.
    You can purchase Lion by contacting Customer Service: Contacting Apple for support and service - this includes international calling numbers. The cost is $19.99 (as it was before) plus tax.  It's a download. You will get an email containing a redemption code that you then use at the Mac App Store to download Lion. Save a copy of that installer to your Downloads folder because the installer deletes itself at the end of the installation.
    Before upgrading check that you computer meets the minimum requirements:
    Lion System Requirements
      1. Mac computer with an Intel Core 2 Duo, Core i3, Core i5, Core i7, or
          Xeon processor
      2. 2GB of memory
      3. OS X v10.6.6 or later (v10.6.8 recommended)
      4. 7GB of available space
      5. Some features require an Apple ID; terms apply.
    Upgrading to Mountain Lion
    Be sure your computer meets the minimum requirements:
    Apple - OS X Mountain Lion - Read the technical specifications.
    Macs that can be upgraded to OS X Mountain Lion
      1. iMac (Mid 2007 or newer)
      2. MacBook (Late 2008 Aluminum, or Early 2009 or newer)
      3. MacBook Pro (Mid/Late 2007 or newer)
      4. MacBook Air (Late 2008 or newer)
      5. Mac mini (Early 2009 or newer)
      6. Mac Pro (Early 2008 or newer)
      7. Xserve (Early 2009)
    Are my applications compatible?
    See App Compatibility Table - RoaringApps - App compatibility and feature support for OS X & iOS.
    Am I eligible for the free upgrade?
    See Apple - Free OS X Mountain Lion upgrade Program.
    For a complete How-To introduction from Apple see Apple - Upgrade your Mac to OS X Mountain Lion.

  • Urgent    how to change factory calender to normal calender  in bw report

    Hi
    how to change factory calender to normal calender  in bw report give me step by step
    prasanth.k

    Prasanth,
    the calenders are maintained in the source system and not in BW - if you have to change the calendar coming into BW - do the needful change for the related transaction in the source system.
    Arun

  • HT5824 how to update contact info to icloud from my iphone

    how to update contact info to icloud from my iphone?

    If you are syncing contacts with iCloud on your phone, just edit the contact in the contacts app.  That edits it in iCoud.

  • How to update Factory Calendar in SRM

    Do we need to have Factory Calendar updated in SRM as currently it shows valid to 2010?
    My understanding is that this is only for ECC. What is Factory Calendar used for in SRM? How do I update/ extend it?

    Hi Jagdish, How are you? I'm sorry to trouble you,
                   Let me introduce, I'm Daniel, and I saw your fantastic asnwer in
    the topic "How to update Factory Calendar in SRM", and might I have the same
    problem. It's with the "factory calendar".
    In transaction va02 when I choose a Delivery Date, and I sent it to process, as
    a result in the "shipping tab" it calculated to the first item one date, and to
    the rest one date different.  I don't know What it happen?
    I debugged the program and I saw that to the first item use to calculate the
    date is the function  'APO_SCHEDULING', and to the rest item use
    'SD_SCHEDULING', and until here I come.
    How can I do to what the dates calculated are the same? or What would be the problem?
    I need the dates calculated are equal.
    I looked at it's using two "factory calendar" which are "J4" and "C2". Is this
    correct?
    Thanks In Advance,
    My best regards,

  • Postcode can't replicate to CRM from ECC

    hi,guys,
       I found the postcode field and city field could not replicate to CRM from ECC,but other fields can replicate conrrectly.why?Our CRM system is 7.0 EHP1.

    Hi Raymond,
    Are you able to solve your problem. As I am facing the same issue. But I am trying to replicate from ECC TO CRM.
    When I am changing Address like City in R3 and checking BDOC in crm its green and showing change city. But when I am checkign Business partner master date change city is not reflecting.
    Regards
    Nishith

  • When trying to update and install Mountain Lion's 10.8.3 update from 10.8.2, the App Store will restart my computer but not install the update.  Any ideas on how to update my Macbook Pro 15" from 2008?

    I was wondering, does anyone have an idea on how to update my Macbook Pro 15" to Mountain Lion's 10.8.3 from Mountain Lion's 10.8.2 version?  When I attempt to use the App Store, it will restart my computer but it will not install the update.  The update also still shows up in the App Store as available and when going to "About my Mac," it still shows the current version being 10.8.2.
    Computer:
    Macbook Pro 15" Aluminum Body
    Purchased Late 2008
    Current OS: Mountain Lion 10.8.2
    Original OS: Leopard

    I will be attempting this fix this fix tonight:
    https://discussions.apple.com/message/21529499#21529499

  • How to use factory calender in BPM (NWDS 7.1 environement )

    hi guys,
    I have requirement to send u201Cnotification of missed deadlineu201D using factory calendar.
    The time to send notification is in hours and its is less than a day. So a task created on Friday 5u2019o clock should send missed alert on Monday 9 AM (assuming business run from 9 to 5).
    this need to be achieve using BPM workflow can any suggest me how to use factory calendar in BPM .

    Hi,
    You can use "BUSINESS_DATE_CREATE" function module in the ECC system for your requirement.
    This will calculate exact date and time and return next business day.
    You need to some datetime convertions on the BPM side to get it working
    Regards, Anil

  • How does delivery info flow back to CRM from ECC ?

    Hi Experts,
    How does the delivery info (Quantity Delivered present in the table CRMD_CUMULATED_I) get replicated from ECC to CRM ?
    Is it through the middleware ? If not, how ?
    Any pointers would be of great help.
    Regards,
    Kris.

    hie kris,
    did u have any answer?
    regards,
    marry.

  • How to activate delta download for BP from ECC to CRM

    Hi,
    i have completed BP initial download from ECC 6.0 to  CRM 5.0.
    i dont know how to activate the Delta download?.
    Plz anyone tell me the procedure.
    regards
    geetha.g

    Hi Geetha
    Synchronization download allows you to synchronize inconsistent datasets on various databases. This can be controlled in time slots or can be triggered manually.
    1. Creating a Request
    Choose Middleware -->Data Exchange --> Synchronization --> Define Requests.
    To define a new data request, choose Display --> Change and New Entries.
    Enter data for the request.
    In object name enter CUSTOMER_MAIN
    2. Starting the Request
    Choose Middleware --> Data Exchange -->Synchronization --> Synchronize Objects.
    A selection screen appears. Enter the objects to be synchronized or use F4 input help to select objects. Choose Execute to start synchronizing the data.
    3. Monitoring Request
    Choose Middleware --> Data exchange --> Synchronization --> Monitor requests
    Enter an object name or a range of object names. Use the input help or of you want to display all the objects, do not enter an object name at all. Choose Execute.
    Further help is available on http://help.sap.com/saphelp_crm50/helpdata/en/c7/95fc381478ab6fe10000000a11402f/frameset.htm
    Hope this would help.
    Regards,
    Rekha Dadwal
    <b>You gain a point for every point that you reward. So reward helpful answers generously</b>

  • How to update Final Cut Pro 5 from 5.0.4 to 5.1.4. I'm having trouble doin

    I will appreciate any help. I'm trying to update my final cut siftware from 5.0.4 to 5.1.4, but I'm having trouble. When I tried a dialogue box appears saying that I need to use The Software Update in order to update my software. But when I go to the Software Update, there's nothing.
    Thanks;
    Ricky
    Power Mac G5   Mac OS X (10.4.8)  

    The upgrade from 5.0 to 5.1 is not free.
    You can find information about it here:
    http://www.apple.com/universal/crossgrade/
    If you have the full 5.0 Studio, it should be only $49US to get 5.1
    Time is running out on the deal, so don't wait if you are going to do the move.
    good luck.
    x

  • How to update to 10.6.4 from 10.5.8 macv=book (for trackpad?)

    Hi
    Can anyone please tell me how to update my OSX so i can use the new trackpad?
    I just spent 80 EUR's on a new apple trackpad and its a nightmare to upload which i never thought would happen with Apple.
    I am on 10.5.8 on a macbook and cannot update to 10.6.4 which is required. My system cannot see any updates. I have backed up and need to install the new OSX just to pair my trackpad with my mac.
    Please help!
    Macbook Mac OS X (10.5.8)

    Hi
    First purchase the Snow Leopard Installer DVD:
    http://store.apple.com/fr/product/MC573F/A?fnode=MTY1NDAzOA&mco=MTc1MTEzNjY
    Then install it.
    Tony

  • How to transfer Material Master data information from ECC to CRM

    Hi ,
      Changes to the Classification data of Material master for the class type-001 and Custom
    ZFIELDS on mara will trigger the Interface functionality. Any changes to the
    custom zfields and  classes or characteristic values on Material Master must transfer the information from ECC to CRM. By using RFC .
    Regards,
    Pavan

    Hi,
    You need to use change pointer to do this. Go to transaction SALE,
    expand MODELLING AND IMPLEMENTING...
    expand MASTER DATA DIST...
    expand REPLICATION OF MODIFIED DATA
    You may need to maintain distribution model in SALE.
    Cheers.
    Reward if useful

Maybe you are looking for