How UWL support substitution in multiple backend scenario?

Hello experts,
We are using UWL with multiple backend - 3 ERPs. If I define a substitution rule in portal, I think this rule will be replicated in all the 3 ERPs otherwise my substitute in the backend could not get my work items in UWL. Is it correct? Do you have more information about this topic?
thank you for your help in advance!
Best Regards,
Huaiyang

Dear Huaiyang,
You are right, if you have multiple systems connected to UWL , then substitution set via UWL has been entered in all systems.
However it is not possible to restrict substition settings to a particular system. If the user set a substitution via UWL, then it will be set in all connected system as well. UWL set the substitution at backend level in the normal substituion table HRUS_D2.
Hope this helps.
BR
Richard

Similar Messages

  • SAP CRM Multiple Backend Scenario with Solution Manager

    Dear Experts,
    We are implementing CRM Middleware - Multiple Backend Scenario (MEP / MBE Concept) in our client landscape for SAP CRM on HANA (Ehp3)
    set-up.
    And If any one of you have already implemented MEP Scenario in the SAP CRM Landscape, Could you please help us to provide with the Configuration Steps / Documents, so that we can proceed further.
    Below are the following Queries:
    For Customizing Adapter Object:
    1) Does MEP Concept support the Customizing Adapter object to download from more than one ECC System to single CRM System.
        If Yes, Could you please provide the Configuration steps or Procedure to download the customizing data.
    For Master Adapter Object:
    2) The Adapter objects for Master Data like Customer and Materials are technically supported under MEP for the data exchange.
         However, is it possible to download the Equipments Master Data from more than one ECC System to single CRM System?
         If Yes, Could you please provide the steps or Procedure to download the Equipments Master Data.
    And please provide if you have done the Solution Manager Configuration mapping for MEP Scenario, which is required for the maintenance and transfer of customizing mappings to CRM and Mapbox.
    Thanks,
    Mohanram.

    Hi Alagammai,
        We are also implementing CRM Middleware - Multiple Backend Scenario (MEP / MBE Concept) in our client landscape for SAP CRM on HANA (Ehp3) set-up.
    Required some Information on the below Query.
    For Customizing Adapter Object:
    1) Does MEP Concept support the Customizing Adapter object to download from more than one ECC System to single CRM System.
        If Yes, Could you please provide the Configuration steps or Procedure to download the customizing data.
    For Master Adapter Object:
    2) The Adapter objects for Master Data like Customer and Materials are technically supported under MEP for the data exchange.
         However, is it possible to download the Equipments Master Data from more than one ECC System to single CRM System?
         If Yes, Could you please provide the steps or Procedure to download the Equipments Master Data.
    And please provide if you have done the Solution Manager Configuration mapping for MEP Scenario, which is required for the maintenance and transfer of customizing mappings to CRM and Mapbox.
    Thanks,
    Mohanram.
    7829055537

  • Multiple Backend Scenario with SolMan

    Hi Gurus,
    i need the information about the multiple backend scenarios implementation with SolMan. In the Note 1084315 - Consulting: Information about the multiple backend scenario,  there is the Way decribed:
    You can find documentation about this in Solution Manager under 'Basic Settings for SAP CRM' -> 'Multiple Systems Exchange Projects: Multiple Backends'.
    But i can not find it in Solution Manager, where can it be?
    Thanks and Regards,
    Stefan

    Hi Alagammai,
        We are also implementing CRM Middleware - Multiple Backend Scenario (MEP / MBE Concept) in our client landscape for SAP CRM on HANA (Ehp3) set-up.
    Required some Information on the below Query.
    For Customizing Adapter Object:
    1) Does MEP Concept support the Customizing Adapter object to download from more than one ECC System to single CRM System.
        If Yes, Could you please provide the Configuration steps or Procedure to download the customizing data.
    For Master Adapter Object:
    2) The Adapter objects for Master Data like Customer and Materials are technically supported under MEP for the data exchange.
         However, is it possible to download the Equipments Master Data from more than one ECC System to single CRM System?
         If Yes, Could you please provide the steps or Procedure to download the Equipments Master Data.
    And please provide if you have done the Solution Manager Configuration mapping for MEP Scenario, which is required for the maintenance and transfer of customizing mappings to CRM and Mapbox.
    Thanks,
    Mohanram.
    7829055537

  • Role of clients in CRM Multiple Backend Scenario

    Does the CRM Multiple Backend Scenario only apply to a single client pointed to multiple CRM or ERP systems.
    All the relevant tables are client dependent in CRM 2007 and the client independent ones use logical destinations which can easily be pointed todifferent clients.
    We want to point different clients on a CRM or ERP system to multiple back ends, but each client will only have a single client that it points to.
    For example
    CRM (dev) client 100 is connected to ERP (sandbox) client 100
    CRM (dev) client 200 is connected to ERP (dev) client 100
    CRM (test) client 100 is connected to ERP (qa) client 100
    CRM (qa) client 100 is connected to ERP (qa) client 200
    This will only be in the development and qa systems. Production will be a single system and client on each side.
    Regards,
    Aubrey Smith

    Aubrey,
    Development will happen in only one client system. This can later be moved to Quality and further to production. All customization will also be moved same way. It may also happen that your development is cross client so if you do development on 100 , it will be available on 200 client as well.
    Regards,
    Harshit

  • ABAP Mapbox CRM 7.0 for a Multiple Backend Scenario

    Dear SDN community members,
      In our project we have one CRM system connected to three ERPs. For this reason we try to use the ABAP MAPBOX functionality for the customizing and master data mapping. In the process of the initial download of CUSTOMER_MAIN object we take the following error :No table entry found: 'CUST_REL'/'CRTCLNT100', Service that caused the error: SMW3_OUTBOUNDADP_CALLADAPTERS. As we have read on the CRM 7.0 the ABAP MAPBOX is part of the ABAP stack of CRM and for this reason we do not create RFC connection for the MAPBOX. Is this correct ?
      Does anyone have any idea about the problem above ? Also is there any technical documentation for the customizing steps that are needed for the scenario of multiple backend systems ?
      Thanks in advance,
         John Syrigos

    Hi John, our project is facing the same requirement, multiple ECC 5.0/6.0 back ends. Were you successful in the integration and MapBox activation and can you give me any lessons learned in your experience?
    thanks
    Glenn
    Edited by: glstover on Apr 18, 2011 7:59 PM

  • Multiple backend scenario

    HI,
    could anyone send me the notes 640570 and 853430 as pdf because i have no access to those notes. Thanks.
    Regards,
    Thomas Strehle

    Hi
    i will forward to your email id provided  your email adresss to me
    Regards
    Rao

  • SRM 7.0 extended classic possible for multiple backends?

    Hi all,
    I know that SRM 7.0 can be set up for multiple backends in the classic scenario.
    And i assume it is also possible to do so in the EXTENDED classic scenario.
    Could somebody please confrim that this is possible?
    Has somesone already set up this landscape and any recommendations, advice, hits, do's and dont's?
    Cheers
    Ulrike

    Hi Ulrike,
    SRM 7.0 supports ECS for multiple backends. We are using it now.

  • Multiple Backends, e-Sourcing

    Hi all, we have positioned e-Sourcing at a client that now intends to integrate to multiple backends.  With the SAP Consulting Note (OSS), we can interface e-Sourcing to a single backend.  Does anyone have any experience with integrating to multiple backends?  Some of our initial white board sessions to resolve this include:
    1.  Writing some code/scripts or mapping with PI/XI to mimic the SRM BADI "determine logical system" to route the contract back to the appropriate R3.
    2.  Using the Portal function "Composite Application Framework" to facilitate the selection of appropriate backend systems. 
    If anyone has experience or comments, please provide details or point me to some documentation to support this effort.  I assume someone has addressed this previously.  thank you.
    regards,
    gary

    Hi Gary
    We are also looking at implementing the Multiple Backend scenarios for SAp E-Sourcing integration with SAP R/3
    We understand that SAP will offer this as an interface from version 6.0 onwards, however this release as of now has been cancelled and are now looking at SAp E-Sourcing version 5.1 that will have the Multiple Backend integration
    Just to add to your views, we can still looking at using the splitter functionality in SAP XI to help push the messages to the respective multiple backends, however we need to create fresh Interfaces that will be used to Push from SAP E-Sourcing to SAP R/3 XML messages routed through XI
    We have to take these as development initiatives and address the multiple backend integration
    However, if you are able to hold on till version 5.1 is released in Q2, 2008, you need not develop these interfaces, incase its the project requirement at the moment, then you can go ahead and develop these interfaces in XI
    Incase you can share some information on the Single Backend integration, please feel free to send them to [email protected]
    Let me know if you need more information on your subject,and the decision you finally take to address your issue
    Regards
    Tridip
    SAP SRM Consultant
    +91 9902764700

  • Programmatic access to multiple backend systems using adaptive RFC

    Hello,
    The following  link http://help.sap.com/saphelp_nw04/helpdata/en/af/84a34098022a54e10000000a1550b0/content.htm talks about the support to map multiple backend systems by specifying the backend system as URL parameters in a webdynpro application.
    For example:
    http://<hostname>:<port>/webdynpro/dispatcher/local/ESSProject/ESSApp?
    sap.wdarfc.useSys=WD_MODELDATA_DEST:ABC&
    sap.wdarfc.useSys=WD_RFC_METADATA_DEST:ABC
    Is it possible to programmatically change the backend systems the application connects to? in other words can a single application while executing connect to different backend systems by dynamically changing the model parameters?
    (This should be possible without the portal in the picture)
    Cheers,
    Praveen

    Hi,
       [This|JCO connection to multiple R/3 Back end system; might help especially the reply from Bertram Ganz.
    Regards,
    Satyajit.

  • How to connect to multiple backend systems to IMS

    Hi,
    I want to connect multiple backend system to SRM IMS.How to connect multiple backend system.
    Thanks in advance
    Regards
    Nitin Amritkar

    Hi
    see page 63. it is possible.
    define backend systems in spro and record all your ecc systems and create a distribution model fpr bbpiv message in srm and distibute to all backend systems.
    http://www.portal.state.pa.us/portal/server.pt/gateway/PTARGS_0_160867_305341_0_0_18/2006_05_26_srm_007.pdf
    br
    muthu

  • How to Implement a Single Folder - Multiple Authors Scenario für NW 7.3?

    Hello,
    is a version "How to Implement a Single Folder - Multiple Authors Scenario" for NetWeaver 7.3 planned?
    Best regards,
    Arnold Gallemann

    Hi Detlev,
    thanks a lot for sharing your work!
    Due to the reason we need a different configuration in KM, I changed e.g. some values in the .cc.xml and .co.xml files. I rebuild the project and checked the created EAR file. I noticed that the ConfigArchive file in EAR file still has the old values. It seems that SAP NetWeaver Developer Studio 7.3 is not recognizing in a portal application project the configuration of the src.config folder anymore. To test this, I removed the initial provided ConfigArchive in the folder dist\PORTAL-INF\config\ from your project. I rebuild it and the ConfigArchive in the EAR file wasnu2019t included.
    I found in the documentation (http://help.sap.com/saphelp_nw73/helpdata/de/42/60aec0032c1422e10000000a114cbd/frameset.htm) the SAP Note 1572813, which would describe how to use KMC wizards in SAP NetWeaver Developer Studio 7.3. But the article is currently not released to public.
    In addition I have discovered, that it is possible to include the src.config folder in the build process if the project is set up as a development component (see for details bullet point Optionally of http://help.sap.com/saphelp_nw73/helpdata/de/42/60aec0032c1422e10000000a114cbd/frameset.htm). This works. But later on I am facing another problem: I am missing the entry KMC-CM to add it as a dependency for the development component.
    Best regards
    Mario

  • How java support multiple inheritance by the use of interface.

    As per my understanding, Interface is just having the signatures of the methods not the implementation.
    So How java support multiple inheritance by the use of interface?
    Answer 1: we can institate interface reference by its implemented
    class.
              ����� interface inf...
              ����� class aa implements inf..
              ����� class bb implements inf....
               Now, inf i = new aa();
               inf i = new bb();
    Answer 2: We can extends as many interface as we want in the
    single
               interface.
               i.e. interface infFirst....
               interface infSecond....
               interface infThird....
               Now ,
               interface ingMulti extends infFrist, infThird...
    By above two answers its not prity clear as per the multiple inheritance in C or C++.
               i.e.
               class first{
               method abc();....}
               class second{
               method bbc()......}
               class multi::first::second{
               we can call to abc();.....as well as bbc();
    -Please give your important suggstion on the same.(Hope I explain it well.)
    -Jeff

    The keyword implement is used only for interfaces not
    for abstract class. If i am wrong correct me.I believe your right, but I will double check.
    As for the multiple inheritence think about the following code:
    class Animal {
        //  Animal generic stuff in this class
    interface Eat {
        //  Generic stuff that models eating behavior
    interface Runs {
        //  generic methods that model running behavior
    public class Horse extends Animal implements Eat, Runs {
        //  Stuff specific to a horse
    }The Animal class is generic but has stuff in it common to all animals.
    The Eat interface models behavior that is generic to eating, all living things have to eat something to survive. Herbavore are different from carnivores.
    The Runs interface models generic behavior to running, such as speed. A cheeta definately runs faster than a human.
    This brings us to the Horse class. It extends the Animal class because it "is-a" animal, and it implements the eat and runs interface because they are behaviors a horse has.
    I hope that helps.
    Extending an abstract class is the same as extending a regular class with the exception you MUST override all abstract methods in the abstract class. Thats not too difficult but I believe when designing classes, designing an abstract can be more diffecult than modeling the base class, and generic behaviors in interfaces. JMO.
    JJ

  • ESS + JCO + Multiple backend support

    XSS with multiple backends
    Hi All, we have a portal running with the standard ESS business package u2013 we use the system for demo purposes, and would like to be able to connect to different backend systems u2013 depending on the user.
    IE, user XX connects to system DP4 and user YY connects to system ID4 u2013 is this possible?
    My own approach was:
    I made 2 delta copies of the of the standard ESS role to two folders u2013 XX and YY
    XX I didnu2019t change, and therefore it used the standard SAP_R3_HumanResources JCO connection, which points to system DP4.
    Then in the folder YY, I changed the WebDynpro iView parameter to:
    sap-wd-arfc-useSys=SAP_R3_HumanResources_MetaData:ID4&sap-wd-arfc-useSys=SAP_R3_HumanResources:ID4
    and in the Webdynpro Content administrator I created these systems and called them:
    SAP_R3_HumanResources_MetaDataID4 u2013 as the guide from sap descripes.
    This did however not seem to work, as metadata was still readout from DP4 while application data was Read out from ID4.
    Then I noticed that the application eg. WhoIsWho also refers to som additional applications, such as
    Xssfpmutil and so on u2013 and they use the JCO: SAP_R3_SelfServiceGenerics, so I created a
    SAP_R3_SelfServiceGenericsID4, and added this to the parameter string, so I know looks like:
    sap-wd-arfc-useSys=SAP_R3_HumanResources_MetaData:ID4&sap-wd-arfc-useSys=SAP_R3_HumanResources:ID4&sap-wd-arfc-useSys=SAP_R3_SelfServiceGenerics:ID4&sap-wd-arfc-useSys=SAP_R3_SelfServiceGenerics_MetaData:ID4
    But this doesnu2019t work, some of the data is still read from Dp4 instead of ID4
    So my question is u2013 is it possible to use ESS with two backends, or is this not supported?
    Help is MUCH appreciated
    Br Ronni

    Hi stuart!
    I made two copies of the standard ESS role
    ESS_XX and ESS_YY, and then i changed i iview parameters for each iview
    (by breaking the deltalink in both roles),
    giving them the following application parameter:
    sap-wd-arfc-useSys=SAP_R3_HumanResources_MetaData:ID4&sap-wd-arfc-useSys=SAP_R3_HumanResources:ID4&sap-wd-arfc-useSys=SAP_R3_SelfServiceGenerics:ID4&sap-wd-arfc-useSys=SAP_R3_SelfServiceGenerics_MetaData:ID4
    But the problem is that while the user YY gets modeldata form system YY the user gets metadata from system XX
    (assuming he is created on system XX, if not we get an error).
    so i guess the parameters somehow dont match.
    Has anyone used the same portal for different backends with sucess?
    Br Ronni

  • How to maintain EOIO for JMS to multiple webservices scenario

    Hi,
    I have a requirement that
    how to maintain EOIO for JMS to multiple webservices scenario.
    JMS queue has multiple messages, each message has to be sent to either of 2 receivers.
    How to maintain EOIO in case, when there are 2 receivers.
    Regards
    Sekhar

    Hi,
    since messages are split between 2 webservices receivers, each would have its own SOAP adapter.
    So if order of messages in the JMS queues is M1, M2, M3 and M4 . There is a field based on which split happens.
    Say, if M1 and M3 have to go Webservice1 (will have its own mapping)
    and M2 and M4 have to go Webservice2. (will have its own mapping)
    we'll have two receivers in the receiver determination and hence two Interface determinations.
    The result should be
    M1 delivered to Webservice1
    M2 delivered to Webservice2
    M3 delivered to Webservice1
    M4 delivered to Webservice2
    How will we maintain EOIO in this case?
    Regards,
    Balaji.M

  • How to support multiple languages on logon screen (Using EP)?

    Hi Everyone,
       Just i want to know, how to support multiple languages in Logon Screen Using EP?
    Thanks & regards,
    Venkatesh.K.

    Hi,
    Transac SMLT :
    http://help.sap.com/saphelp_nw2004s/helpdata/en/62/163d38c2113265e10000009b38f889/frameset.htm
    Import de language:
    http://help.sap.com/saphelp_nw2004s/helpdata/en/62/163d38c2113265e10000009b38f889/frameset.htm
    Hope it help's

Maybe you are looking for

  • Error- while assigng FF-Owners to FF-Id's in GRC-10 AC

    Hi Experts, Iam  facing  issue as below.. while configuring Super user assignment (while assigning owners to FF Ids) Please let me konow if nay one of you encountered same issue and how you resolved.. Error while processing your query What has happen

  • Preventing the deletion of a PO with IR but no GR

    Hello guys, I am facing a requirement to prevent the deletion of non-GR related Purchase Orders. The POs are still marked as complete since an invoice has been released. When trying to delete complete GR related POs, we are getting the following mess

  • "number of items in all folders" setting keeps changing

    Hello I have the problem, that a customer wants to see the number of mails in an outlook folder (exchange). When I set the option "number of items in all folders" it works - but only as long, as Outlook is running...  As soon as I close Outlook, it c

  • Weird Pacman Error! [solved]

    Since last night, I've been getting this weird error when I run 'pacman -Syu' as root. What's going on? :: Synchronizing package databases... current 71.2K 143.5K/s 00:00:00 [#####################] 100% extra is up to date community 274.6K 339.7K/s 0

  • BPF Questions

    Hello All, I have a BPF Instance with 2011.TOTAL, PLN with driver dimension to be Cost center. I have 3 steps in my BPF. I have different values for my drive dimension in creating the BPF Instance. If a Planner is done with all 3 steps, it does not l