I have a question about Schedule Ship Date

Q1:How is this date calculated?
In some cases, when I booked the order, Schedule ship date is defaulted to 23:59:00 of that day.But in another case there are several days between the request date and schedule ship date.
Q2:So now we work out the schedule ship date, where can we use it? In another word, what's it usage?
Can anyone help me?

Sheduled Ship Date :
In business terms : This is basically for shippable item's lead time defined in the system. ie. transit time from invoiing unit to customer location with a particular shiiping method.
if this is not defined that meand lead time = 0 so sheduled shipment dat will be system date by default.
this is used to auto compute the available planning dates in planning so that producton priortiy can be defined to arrive at sheduled date.
i hope this information will help you in your understanding for same.
regards, ravi Malhotra

Similar Messages

  • I have a question about my iPhone data usage

    Is there a way to check my data usage on my iPhone in the setting app?

    settings - cellular - scroll down to cellular data usage

  • Hello am using ios 7.0.4 I have a question about messages that it does not show the time of a particular message after first message that I recive form a paricular person so please in the next version change this and with every message show time and date

    hello am using ios 7.0.4 I have a question about messages that it does not show the time of a particular message after first message that I recive form a paricular person so please in the next version change this and with every message show time and date

    Hi,
    How is everything going? Have you checked this issue from OWA? If so, please let me know the result.
    In adition, please also try to use the following powershell commands to check if the assistant has right permissions:
    Get-MailboxFolderPermission -Identity
    CEO’s email address:\Calendar -User assistant’s email address
    Also check with:
    Get-Mailbox -Identity CEO’s mailbox
    | fl *GrantSendOnBehalfTo
    Please let me know the result.
    Best Regards,
    Steve Fan
    Forum Support
    Come back and mark the replies as answers if they help and unmark them if they provide no help.
    If you have any feedback on our support, please click
    here

  • Question about Rescheduling Start Date of a Task

    Question about Rescheduling Start Date of a Task
    I'm trying to determine whether the 'Reschedule' action is appropriate to my situation...
    I have a service that consists of 4 tasks.  The first 3 tasks will be completed immediately and then the request's 4th task will sit in a queue for about a month so that all of these requests can be grouped together and fulfilled during a few overnight work sessions.
    While the 4th task is waiting to be fulfilled, the technician will be contacting the requestor to schedule the work to be done sometime during a 3 day window.  The technician needs to specify which of the 3 days each request will be worked on.  I'm not sure if I should store the date in a service form field or have the technician reschedule the task so that the start date of the task is set to one of the 3 days.  If I use the reschedule feature, are there any downsides?
    The advantage of using the reschedule feature is that the scheduled start date can be displayed in ServiceManager's task list and can therefore be sorted on and queried.  This wouldn't be possible if I stored the date in a dictionary field on the service form.  In that case, I'd have to use custom reports to group the tasks by start date.
    Please let me know your thoughts...
    Thanks,
    Scott

    This strikes me as a very good use of this feature, since your need to to have the date for this task rescheduled/reflected in ServiceManager. This is the specific effect of using this feature.
    For the benefit of others reading this post, remember: this rescheduled date will not change the due date for the service.

  • Question about Scheduled Task

    Question about Scheduled Task
    RequestCenter 2008.3
    Oracle 10g
    Websphere 6.1.27
    IE 7
    Hi:
    I have tried to get a scheduled task to work without any luck.  I am referencing a date/time field on the form and the task goes to "Scheduled", but never moves to "Ongoing".
    I've opened a case with support, but was wondering if anyone has gotten this to work.
    Thank you
    Daniel
    Safeway Inc.

    We just went through this too. If the plan is fairly complex, and has allot of conditional tasks you will have difficulty.
    The explanation I got from Shweta is that the calculation that determines the OLAs before my scheduled task was to start looks at ALL the potential tasks and combines them, essentially saying the duration is much longer than what you think it should be, ie the sum of all potential task OLAs, not just the tasks that became active.
    Bottom line if your scheduled date is with

  • Scheduled ship date not taking PO need by date

    1. Please consider following case -
    a. Sales order is created for org UK for item A for 10000 qty 24-Mar-2011 with order request date as 29-Mar-2011.
    a1. There is no on-hand in UK for item A.
    a2. The item lead time for item A, as defined in UK org in item attributes’ Lead times tab, is as following -
    a21. Pre-processing time - 4 days
    a22. Processing time - 20 days
    a23. Post-Processing time - 1 day
    a3. A standard purchase order for item A is created for 15000 quantity on 25-Mar-2011 with Need by date as 10-Apr-2011.
    a4. The ATP rule that is attached to the item, is having Purchase orders checked, under supply sources.
    Observation : Before purchase order creation, the scheduled ship date on SO was 28-Apr-2011 (item lead time of 25 days).
    Then the PO is created as in point a3 and ASCP plan was run. The sales order line for item A is unscheduled and Rescheduled, the scheduled ship date becomes 25-Apr-2011.
    Questions :
    1.     Why did the scheduled ship date change to 25-Apr-2011?
    2.     What all things it is taking into consideration?
    3.     As per our understanding, the scheduled ship date should have been changed to PO Need by date. But this didn’t happen. Is our understanding flawed?

    Hi Sandeep,
    when we try to Rescheduled out the PO and the request is errored out the with the error:-
    Start of log messages from FND_FILE
    reschedule fails
    old date in planner workbench: 19-MAY-11
    new date: 07-JUN-11
    header: 417474
    line: 605652
    po number: 2049031859
    shipment no: 1
    The need by date/promised date in the source instance is not the same as the need by date/promised date in the destination instance.
    In the source instance,
    The need by date is 19-MAY-11, and the promised date is 19-MAY-11
    End of log messages from FND_FILE
    ---------------------------------------------------------------------------

  • I have a question about extracting pages.  When I do the function, adobe saves the individual files as " file name space page number ", so the files look like this "filename 1.pdf", "filename 2.pdf", "filename 3.pdf".  Without too many gory details, I a

    I have a question about extracting pages.  When I do the function, adobe saves the individual files as "<file name><space><page number>", so the files look like this "filename 1.pdf", "filename 2.pdf", "filename 3.pdf".  Without too many gory details, I am using excel to concatenate some data to dynamically build a hyperlink to these extraced files.  It casues me problems, however, for the space to be the the file name.  Is there any way to change the default behavoir of this function to perhaps use a dash or underscore instead of a space?

    No, you can't change the default naming scheme. You can do it yourself if you extract the pages using a script instead of using the built-in command.

  • How to stop scheduled ship date and scheduled arrival date from defaulting to sysdate

    Hello,
    We have a business scenario where we are deriving scheduled ship date and scheduled arrival date outside and then imported in the instance with the order. However we find that the scheduled ship date and scheduled arrival date are defaulting to sysdate. The atp flag is set to N for these items. I have checked the defaulting rules, there is no such defaulting rule set for scheduled ship date or arrival date ( screenshot attached) Please share your thoughts on how can I stop scheduled ship date and arrival date date from defaulting to sysdate ?
    Thanks
    Rajesh

    Hi
    Please visit following link. It may be useful.
    How to prevent auto default of schedule ship date in sales order form
    HTH
    sd

  • Drop Ship SO Schedule Ship Date to Purchasing NeedBy Date

    Has anyone found a solution to resolve the fact that the Sch Ship Date defined on a sales order becomes the Need By Date on a Purchase Release document sent to a Supplier to fulfill a Drop Ship Order Line? This is confusing to the Supplier as the term NeedBy implies this is when the customer will need the product on site. If the supplier has the product there by the Need By Date transmitted from OM, then the product will arrive too early.
    Thoughts?...

    Let's assume the Customer Service person does not know whether the item is a drop ship item or not. The problem we have is that the Customer Service person normally uses the Scheduled Ship Date as the date Shipping must send out the product on product sourced internally. We are trying to keep things consistent for the end user.
    We hope to use the Scheduled Ship Date as the date the product must be shipped regardless of whether the product is sourced internally or externally. Again, this is to keep order entry consistent for the end user and they do not have to think differently when entering the sales order.
    Thanks for any feedback.

  • I have a question about weblogic RMI , how can I resolve it.Thank you

    I have a question about the weblogic RMI .
    I have a program.web services+weblogic RMI +Data Sources When I run the program in the console application.it is ok.But When i run it with the web services(it 'is mean Get some parameter and run the different program).it's fail.The Exception is
    cannot assign instance of yype weblogic.rmi.RMIServices_1033_WLStub to field demo.RMIServer_1033_WLStub.stubinfo of type weblogic.rmi.internal.StubInfo in instance of demo.RMIEsrver_1033_WLStub
    how to resolve .Thank you.

    Hi Charles,
    Parental Controls has always had problems with https sites, no idea if it's fixed in 10.9.x or not.
    When you setup your Mac it shouldv'e made an admin account, are you not running from that account, or did you somehow change it to a Managed account???

  • Question about exporting FBL3N data in Pivot table format

    Dear all
    I have a question about the "exporting file" function of ECC 6.0.
    We started to use ECC 6.0 system, and it appears that we are no longer able to export "FBL3N data" to a local PC in pivot table format.
    Is there a way to do it?
    We used to be able to do so when the system is 4.6.
    I appreciate your support!
    Kind regards

    Dear:
                 You can do that. Execute report FBL3N with desired GL account in it. After when report has been executed right click on it. There will be an option Spread Sheet. Select all available format. In drill down select 08 (Excel in existing XXL format) and press OK. There you will get pivot table option for downloading., Hope this will help you resolve your query.
    Regards

  • Updating schedule ship date and arrival date in SO

    Hello all,
    I want to update the sales orderline based on supplier PO changes.
    Can anyone let me know if I can use process order API to update the schedule ship date and arrival date.I have created a seperate procedure inorder to achieve the same which will inturn call oe_order_pub.Process_Line.Now am getting the following error:
    SQL_PLSQL_ERROR: N, ROUTINE, MO_GLOBAL.VALIDATE_ORGID_PUB_API, N, ERRNO, -20001, N, REASON, ORA-20001
    Any pointers to this is highly appreciated.
    Regards,
    Sumi.

    Hi all,
    Can anyone let me know if I can use process order API to update the schedule ship date and arrival date.Because sometimes am getting the above mentioned error but now am unable to see any error message but the status is error.
    Regards,
    Sumi.

  • Schedule Ship Date/ATP in OM.

    Hi Champs,
    would like to know how system calculates automatic schedule ship date for an order.
    also pls let me know if ATP and schedule ship date are same.
    Thanks.
    -Arif.

    Hi Arif
    Schedule ship date is populated by ATP when you book or schedule the order. If the item is ATP enabled, ATP calculates the schedule ship date and populates on the order.
    When ATP runs, it considers lot of modules like , purchasing supply, open order for demand etc. ATP calculation is complex calculation and can be dependent on lot of parameters like if you have Global Order Promising installed or not.
    I hope you get the answer.
    Regards
    Yogesh

  • Schedule ship date

    hi all;
    when i book a sales order; the schedule ship date is same as request date:
    where is this setup done?
    i dont have any scheduling activities.
    i dont have any defaulting rule for that.
    i dont have any ATP setup done:
    pl help;
    regards;
    prasad

    Hi,
    SSD will default to request date at the time of Order entry.Change the SSD manually while entering the Sale order and book the Sale order.
    Arumugam S.

  • Scheduled ship date

    Hi ,
    Our client has a requirement that schedule ship date should be
    Sysdate+2.
    I created a defaulting rule schedule ship date = sysdate+2.
    When i create a sales order the schedule ship date comes as
    sydate+2
    eg : sysdate : 29 jan 2008 13:55:25 (the time stamp)
    schedule ship date 31 jan 2008 13:55:25
    But when i save the line the schedule ship date becomes
    31 jan 2008 23:59:00 automatically.
    The system is changing the time stamp to end of the day.
    But our client has a requirement where they do pick release 2 times based on time stamp in 1 day .
    eg : Pick release for schedule 1
    From scheduled ship date :31 jan 2008 00:00:00
    To scedule ship date: 31 jan 2008 11:59:00
    Pick release for schedule 2
    From scheduled ship date :31 jan 2008 12:00:00
    To scedule ship date: 31 jan 2008 23:59:00
    if above is the case then Always pick release for schedule 2 will create move orders for the sales orders.
    -->Want to know Setting. how System calculates the schedule ship date
    How can i make system to calculate the schedule ship date as sysdate+2
    every time i create a sales order instead of using defaulting rule.
    Rgds,
    Raj

    Sounds to me like a calendar issue we have had in the past. If your working calendar excludes weekends, 35 days / 5 days per week would be 7 weeks. If it includes weekends, 35 days/ 7 days per week would be 5 weeks. This has been a big deal for us on a lot of dates calculated by ASCP.