I need to review the existing process chain

Hi Folks,
I need to review the existing hte process Chain which is running in the live system since 1 year.
My intention is what i need to considear while reviewing the process chain and i need to provide the some suggestion after review of the all chains.
Can any one have SAP Notes or SAP help info on this,
Thanks,
Ven.

Hi,
Check in the following tables for Process Chaibn logs
RSEVENTCHAIN ----Event Chain Processing Event Table
RSEVENTHEAD -----Header for the event chain
RSEVENTHEADT -----Header for the event chain
RSPCCHAIN---------- Process chain details
RSPCCHAINATTR------- Attributes for a Process Chain
RSPCCHAINEVENTS------- Multiple Events with Process Chains
RSPCCHAINT--------------- Texts for Chain
RSPCCOMMANDLOG--------- System Command Execution Logs (Process Chains)
RSPCLOGCHAIN---------- Cross-Table Log ID / Chain ID
RSPCLOGS------------- Application Logs for the Process Chains
RSPCPROCESSLOG------------- Logs for the Chain Runs
RSPCRUNVARIABLES---------- Variables for Process Chains for Runtime
RSPC_MONITOR----------- Monitor individual process chains
Thanks
Reddy

Similar Messages

  • How to copy a existing process chain

    hi
    i am a SAP BW learner.
    i created a process chain for inital load and i want to create a process chain by copying first created process chain and tell me in what situation we delete the indexes of InfoCube.
    Can any one provide me the solution to how can i copy the existing process chain and tell me in what situation we delete the indexes of InfoCube.
    Thanks in Advance.

    Hi Kiran:
    Thats correct, you can copy an existing process chain and you will get all the variants in it.
    well, the best practice to manually do the INIT loads and let the delta loads be in process chain.
    we delete indexes and re create them when we are loading an infocube and the reason  is performance
    Assign points if helpful
    kalyan

  • Not able to open existing process chains in BW development

    Hello Experts,
      I am not able to open my existing process chains in development, actually I would like to schedule the process chain but I couldnt do that becoz of above reason. While opneing I am getting pop-up message as " Choose a change request with target system/CONSOL/". I reported this issue to Basis but they told it is not an issue at all
    I need to resolve this asap.
    Thanks in advance,
    Andy

    Roger,
    For the time being you can create a transport, but indicate that it shouldn't be transported.
    Then you will be able to work with the process chain.
    Just be sure to delete the transport so it doesn't get moved to production on accident.
    Nick

  • What would the best process chain look like for this MD data load scenario?

    Hi there,
    I have the following setup. SAP BW connection to external system via DBConnect (DB2 database).
    We have 73 master data text data sources to load either once a week or everyday through process chain. We have not decided on the exact schedule yet.
    All the master data text DataSources pull data from the SAME VIEW created on the DB2 external system:
    VWDEDMASTERDATA
    The structure of the view is the following:
    DEDNAME
    DEDNAMETYPE
    DEDNAMECODE
    DEDNAMEDESC
    DEDNAMELONGDESC
    So, everytime master data text is extracted for all the 73 objects it queries the same view over and over again VWDEDMASTERDATA. We only differentiate in the datasource on the FIELDS tab which InfoObject should DEDNAME map to and then in InfoPackage we filter on the exact object/field to query.
    So essentially, every time we run InfoPackage for master data text object the external system gets queried in the following way:
    SELECT * from VWDEDMASTERDATA where DEDNAME = [FIELD/InfoObject specified in InfoPackage]
    So, if I have to have all 73 objects loaded, essentially the same SQL statement has to execute 73 times. In this scenario, what would be the proper process chain setup that has perfomance in mind? How should the InfoPackages be arranged, in parallel, sequentially, how many in a row, etc?
    Let me know if you need more information.
    thanks

    They would like to send the letters to me
    Depending upon how they send the letters to you and how they expect Acrobat to convert them you could be bordering on a license violation that prohibits you from using your version of Acrobat as a server-based product.
    Adobe offers server based products to convert rtf files into pdf files. Some require your company to run a server, but one seams exactly what they may want. The createpdf service is run by Adobe and seems capable of doing what your company wants.
    https://www.acrobat.com/createpdf/en/home.html

  • How to activate the deleted Process chain

    Hello Experts,
    Unfortuantely we have deleted few process chain by in RSPC .But we are in need of this Process chain . Could you please let us know whether there is any possibilties to get back the deleted process chain .
    Please let us know where the deleted process chains are stored in the system.
    Many Thanks for your Help.
    Regards,
    Kumar

    Hi,
    you can restore it from a backup or in case the chain was transported from one of the target systems or the development system. No other way.
    regards
    Siggi

  • BI 7.0 Stats - Is it supposed to install us the Standard Process Chain?

    Hi All,
    We understand that Virtual Cubes would obtain the real-time based on what is there in the basic cubes, underlying the Technical Content Multicubes.
    We did install all the technical content. Is it supposed to install us the Standard Process Chain for BI Statistics as well to transfer the stats data into the Basic Cubes.?
    If not, how do we setup the stats loads to the basic cubes easily....?
    Thanks in advance.
    Best Regards,
    - Shashi

    Hi,
    When you install the BI 7.0 stats from teh BI content all the process chains related to it automatically gets installed.  But you can see teh correct report only if the DB Stats is uptodate for all the info providers in your system. I mean to say that if all the dataloads to the cube is followed by the DB Stats process only then the coressponding Technical Stats cube gets the correct data. After which you can see teh correct report.
    There is no need to create a process chain separately for them. Just you need to keep updating the DB stats for your info providers.
    Navesh

  • How to stop the running process chain

    How to stop the running process chains or infopackges...just qm status change is enought?

    BI - SM 37 - Kill the Job
    ECC - SM 50 - Kill the job

  • Creating the New Process Chains in BW System

    Hi SDN,
    What is the best practice of creating the New Process Chain?
    1. Whether to create the Process Chain in BW Development first and trasferring it through transfer request
    OR
    2. Create directly the Process Chain in the BW Production and schedule it
    Please provide the views.........
    Kind regards,
    Rajesh Giribuwa

    hI rAJESH,
    Ya,we must create any development in development system and then subsequesntly to test and then production system.
    but my exp was differnt in one of my project .
    i have developed the pc in dev first and then trasported to test and then prod,
    it worked fine in dev and test but in prod it was not running ,due to some system resources.
    so i did the change direclty in prod and then it worked .
    but it was risk .
    hope this is helpful
    Jimmy
    dont hesitate to move u r cursor towards the max point

  • How to identify who ran the last process chain?

    Hi all,
    How to identify, who ran the last process chain for a PROCESS CHAIN NAME xyz in the production system?
    Thanks

    Hello,
    Go To RSPC1 give your process chain name (Go to  LOG View ) there  you will get Date selectin screen (give This Month and last Month or as per your reqirement) there you can see who ran the process chain with ID.
    Regards,
    Edited by: Subbu_Amar on Oct 13, 2010 5:01 AM

  • How do i cancel iTunes match? i am trying to change the country details as i am now in germany, but keep getting a message saying i first need to dance the existing iTunes match

    how do i cancel iTunes match? i am trying to change the country details as i am now in germany, but keep getting a message saying i first need to dance the existing iTunes match

    When you try to change your county, you might see one of these messages:
    You have an active iTunes Match subscription; you must cancel it before you can change stores.
    You have at least one incomplete pass. Passes must be complete before you can change stores.
    You have rentals that have not expired; they must expire before you can change stores.
    You have a store credit balance; you must spend your balance before you can change stores.
    You have one or more pending store credit refunds. You must wait a few hours for these to complete before you can change stores.
    You are part of a family. You must leave the family before you change stores.
    From
    Can't change the country of your iTunes Store, App Store, iBooks Store, or Mac App Store account - Apple Support

  • How to check the parent process chain of a meta chain

    Hello Friends,
    Recently I joined a new project, which is of environment BW 3.0. I am trying to find the dependent process chain's parent, but could'nt able to find them. I went through all the process chains manually to check whther the dependent process chain is mentioned in them, but could'nt find any......
    Can any of you help me to know how to find the parent process chain of a meta chain ?
    I really appreciate your time, will be awarding points to any answers.......
    Thanks,

    Hello Radhan,
    thanks for your quick reply. I searched the table based on your advice, but i could'nt get the parent process chain's name. Can you throw some more ideas please..........
    Thanks,

  • How to collect and move the deleted process chain to Prod.

    Hi,
    I have a process chain (BI 7)that is already in D,Q and P and now I want to delete a Process Chain under "Display Component" and my question is how to collect the deleted process chain to move all the way to Q and P.
    Waiting for your response
    Regards,
    Sunil

    Hi Srinivas,
    Thank You ,I was scared that i dont get any request to collect and my problem is resolved.
    Regards,
    Sunil

  • Event triggering fails to start the next process chain

    Hi
    I have two process chains A & B
    At the end of process chain A i am triggerring the an event which is the start condition for process chain B.( periodic )
    Now when i debug my process chain A , i see the event is triggered successfully but inspite of that the next process chain does not start.
    Does anyone faced similar problem? Its little urgent. Any clue would be useful.
    Regards
    Purva

    HI,
    In addition to the above comment also see if you have given the event name correctly and try to see if you can run the PC by triggering the event manually (Tcode: SM64)
    Assign points if helpful.
    Rgds,
    Kalyan

  • How to download Acrobat Standard X from a CD? Do I need to uninstall the existing Acrobat software?

    How to download Acrobat Standard X from a CD? Do I need to uninstall the existing Acrobat software?

    You download from the internet, not from a CD... you might install or copy things from a CD.
    But to answer your question properly:
    1. What is your existing Acrobat software, exactly, including version number?
    2. Are you trying to install and getting an error? If so please give full details.

  • Need help to terminate the local process chain

    hi
    Master DATA attribute local process chain was triggered twice in our daily master process chain. it is showing twice in the logs.
    Can any one help us to terminate the one replica of the running master data attribute local process chain.
    Thanks much in advance
    Raj
    Edited by: Gangaraju Eegu on Dec 10, 2008 3:03 PM

    Hi,
    Please check in execution selection any periodic job is running twice, so remove there.Double click on first node i.e. start and > Chamge Selections> Periodic Values.
    Or
    Find any event is triggering twice in a day?. and tehn cancle it.
    Thanks
    Reddy

Maybe you are looking for

  • T60P cannot download drivers / connect to proper wireless

    I got a new hard drive for my T60P, so I am trying to install Windows XP on it. I got the computer through govconnection, so it never came with a recovery disk; now I am trying to install a clean version and install all the drivers manually, and it i

  • Oracle EE 11.2.0.2 RMAN Duplicate interesting issue - is it a bug?

    Hi, Oracle EE 11.2.0.2 RHEL 5.7 x86 64-bit RACOne Node database (3 - nodes). I was working on a process to refresh out test environment with prod database backup from tape and i have done it many times. Most of our environment is in 10gR2 and have fe

  • Custom Function

    I am trying to create a custom function to include in the Functions, and under the Custom Function I want to have the currency format: "cdCurrencyScalerChoice" which I found in the Crystal Report sample: "Order PRocessing Efficiency" Jack..

  • CS4 Gradients   / how to make previous grads load?

    In CS4 past gradients I have made and used since Photoshop CS2 do not load. CS4 sees them as corrupt or incompatible. I think this is a crock. They are nothing but numbers. I don't know, maybe they really are incompatible. I can't help but think that

  • Unable to refresh webi report in live office

    I have a webi report and using live office, i want to create a dashboard, i can able to refresh this webi report in infoview but can't in live office, giving an error not sufficient rights. what are the rights to be modified to refresh this report in