I want change my cost center in Cost element (Urgent)

HI gurus
I posted some amount in cost center.. i wrongly posted another cost center, how change my coster...
Ex: G/L=709060002 Cost center : 10009000
i want put Cost center : 10005024.. is it possible... very urgent..
please
Thank you.
Ashok kumar

Hi,
U can either reverse the doc which u have posted wrongly. or if u want u can manually repost the cost in controlling to the correct cost center but by this the change will be reflected only in controlling and not in FI.
Thanks,
Ankur

Similar Messages

  • Mass change of Profit center in Cost collector

    Hi
    On FERT materials profit center was and i have created cost collectors for all fert materials.
    How I can correct mass change of profit center on Cost collector.
    ty

    Hi,
    You can use the MASS transaction code for changing of Profit Center for your FERT Materials.
    Sateesh

  • Cost Center and Cost Element Hierarchy and Actual Cost Center

    In Bex - Right now I am displaying Cost Center and Cost Element hierarchy with 12 months of data. I want to display the actual Cost center number next to cost element hierarchy - Can I display in Bex?
    Tried to with Structure creating formula variable for Cost Center using replacement path - didn't work. Can you please suggest me how i can achieve this?
    The format should be
    CostCenter H1   CostElement H1   CostCenter   Jan  Feb ...
    Thanks in advance and appreciate for any help...

    Let me explain it clearly and hope it is clear now...
    Designed the report as like this - Cost Center Hierarchy by Cost Element Hierarchy for 12 months of data. But Business agian search in R/3 for actual cost center numbers based on above two hierarchy nodes.
    I am trying to achieve this Bex instead of going back to R/3 - so that they can understand how the dollar amount is summed up on which major cost centers.
    If I remove the hierarchy on Cost Center - it will display all the cost centers. They want to see the Cost center numbers based on CC and CE hierarchy node so that you are displaying only those cost centers. That's the reason I am trying to design the  report with CC Hier, CE hier, Cost Center number and 12 months of data.
    In my data model - have only one Cost Center, if i can create another ZCOSTCENTER same as 0COSTCENTER - May be I can achieve this. still looking for options with out changing the design.

  • Cost center/work cost center

    What is the difference between work cost cneter and cost center(cost center capture the cost via cost elements).but what abour work cost centers,

    Dear Madhu,
    COST CENTER INFORMATION:
    Cost Center (KS01 - Create, KS02 - Change, KS03 - Display)
    Definition of a Cost Center:
    Master data and Configuration settings found in Controlling...
    "An organizational unit within a controlling area that represents a defined location of cost incurrence."
    The definition can be based on:
    Functional requirements
    Allocation criteria
    Physical location
    Responsibility for costs
    WORK CENTER INFORMATION:
    The following is information on how to create a work center and use it. If you need further information simply hit F1 Help in the application to explain the use of the main fields.
    Work Center (CR01 - Create, CR02 - Change, CR03 - Display)
    Using the data maintained for a work center, you can
    - Determine which machines or people are to be used in the operations
    - Calculate costs, capacities and dates for the operations
    Transaction: OP42 - Allows you to Configure the default value for Work Center during the initial creation.
    After creating many work center in the Routing, the users might want to check what materials and components allocation have been updated with this work center.  You can used this program [Work Center in Routing - Search through all the routing for the material and component allocation used (|http://www.sap-basis-abap.com/abap008.htm]).
    The standard program transaction CA80, checks where the work center was used in the routing.  However, it did not list the components allocation for the work center.
    Pooled Capacity field - When a production order 1234567 has the capacity requirement on its work center Wxxxxx. It means it has the requirement on pooled capacity Pxxxxx.  If more than one work center shared this pooled capacity, the requirement (transaction CM01) will be shown on all the work center with the SAME shared pooled capacity.
    I hope this helps to clarify the purpose of the Cost Center  and Work Center and how they can be used.
    Kind Regards,
    Brendan

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • COPA derivation for thecombination of Cost center and Cost element/GL accou

    Hi Gurus,
    In COPA derivation using KEDR i am trying to make a derivation for the
    combination of Cost center and Cost element. Here i got following problems
    • While posting FI document using t.code FB50 system not automatically
    updating the fields Cost center and cost element in Profitability
    segment. Hence system not posting COPA document. How can i make this
    derivation? Is there any note should i apply regarding these.
    • How can i create cost element as characteristic.
    • If i configure derivation for the combination of Cost center and cost
    element will it be posted with copa document for postings or automatic
    postings from MM,HR and FI
    Pls provide me solution at the earliest.
    Thanks and Best regards,
    Dhanumjaya.Ranga
    Mobile: - 919940093579
    Mail : [email protected]

    Hi Murali
    Thanks for update
    I explain my req clearly
    For me segment is Distribution channel field (EXPORT and DOMESTIC)
    If GL account is 1000-2000     always                      Export
    If GL account is 2001-3000    and Cost center is     X then Export.
    If GL account is 2001-3000    and Cost center is     Y then Domestic.
    Based on above REQ i am making derivation using KEDR T.code.
    These postings should work for all modules postings such as MM, HR also.
    Actually this should work automatically and after saving the transaction we should have copa document also.
    But problem is in source fields of derivation we have GL account (HKONT) and Cost element (KSTAR). I am making derivation using either of these.
    But after posting document system not giving COPA document.
    I found the reason is  at GL postings we are giving input to GL account (HKONT) but we took in KEDR source field as GL account (SAKNR). GL account (HKONT) is not updating GL account (SAKNR) field in PSEG screen in Fb50. Even i try with cost element (KSTAR), GL account (HKONT) is not updating this in PSEG screen in fb50.
    If GL account (HKONT) updates either GL account (SAKNR) or cost element (KSTAR) at the time of posting FB50
    Or
    If we have the field GL account (HKONT) as source field in KEDR i hope my problem
    Get solved.
    If you want further info pls give me your mobile number then i ll call you

  • Difference between cost center & Responsible cost center in asset master

    I want to know difference between cost center & responsible cost center in asset master on following perspective.
    1. Financial accounting veiw -
    2. Business & report veiw.
    I have read through F1 help
    Cost Center
    Key uniquely identifying a cost center.
    Use
    The SAP system uses the cost center assignment in the asset master record to determine the cost center affected when the following types of asset posting are made:
    Fixed asset depreciation
    Gain/loss from asset sales
    Cost center responsible for asset
    Cost center that is responsible for the asset, but which does not carry the depreciation for the asset.
    Example
    For example, the cost center "vehicles" can be responsible for all vehicles, while other cost centers carry the depreciation for the vehicles
    I can understand from F1 what will be the impact on finance accounting.  My question is how it helps in reporting etc & business logic for using responsible cost center. Which report will be usefull to see data at responsible cost center.
    Regards
    T

    Closed

  • Cost center and cost center group

    hi,
    how can i create cost center and cost center group?

    hi,
    after u enter in to sap easy access
    goto Extras menu-settings->select display technical names
    you can see the T.codes for each transaction
    for example:create cost center
    accounting>controling->cost center>master data>cost center>individual processing-->KS01-create

  • How to assign cost center to cost element.

    Hello,
    Can any one please guide how to assign cost center to cost element.
    Thanks in Advance..
    Have a nice day...

    Hi ,
    There are 3 ways :
    1. Default the cost center in cost element - Ka02 - account assingment tab enter cost center .
    2. Use OKB9 for diffrent combinations as per your requirement .
    3. Use GGB1 for substituting the cost center based on some conditions .
    Regards ,
    Dewang T.

  • How do i fetch workcenter ,cost center and cost elem using plant ,material

    Hi.
    i have plant and material in my sleection screen..
    how do i get corresponding workcenter,cost center and coste elements..
    i need to find total quanity(total hours per cost center) in terms of huors corresponding to each costcenter

    Start with VAPMA and then go to VBAP. You can use the information here to go to BSEG if necessary.
    Rob

  • Responsible cost center vs Cost Center

    I was wondering what cost center takes prevalence over the other when creating a maintenance order the Responsible cost center vs Cost Center. The Functional location has its own Cost center “Responsible cost center” as well as the Work Centers that are assigned to people “Cost Center”. When creating Maintenance orders I have orders that use the FL work center sometimes and other times it uses the Work Center. I really need the FL to take priority over the WC if that is possible. Any suggestions?

    Hi Lynn,
    There is a bit confusion in your query.
    To make it clear, Responsible cost centre comes from work centre for operations, where the cost is calculated based on the activity / cost centre assignment in KP26.
    Cost centre in Technical object will be responsible for settlement. When the settlement rule is created, it will be assigned as receiver object and work order cost is settled to this cost centre.
    Hope this helps.
    Thanks
    Terence

  • Cost center and Cost element.

    Hi all,
    I am in an urgent need to understand the relation between cost center and cost element. Please provide me with their individual information as well as the link they share. An existing relationship table between the two, if any, ...then plz mention.
    Thanks & Regards,
    Naresh

    Cost Element: cost element is an individual which carry cost like salaries, wages, power expenses, etc.. These Cost Elements are Two types
    1. Primary Cost Element
    2. Secondary Cost Elements
    Primary Cost Element will carry cost form FI to CO (Cost Centers, Internal Orders, Cost Objects, etc…)
    Seconday Cost Elements carry cost with in CO to different Cost Centers, Internal Orders, Cost Objects, etc…
    Cost Center: Cost Center is an individual which contain collection of costs. For example “Admin is a cost center, it contain costs like Salaries, Power, Rent, Stationary etc,
    With this following report you can retrieve  cost elements given a cost center “controlling – cost center accounting – information systems – reports for cost center accounting – plan/actual comparisons  ”
    Thank you

  • Cost center and cost element display through report painter/writer

    Hi
    Can any one suggest me how to display both cost center and cost element in the output of a report painter.
    Presently --- I am able to display cost center and its cost elements in the same leading coloumn and its periodical values for 16 consecutive col.s.
    Help Needed --- Suggest how to display cost center and cost element in the output of the report along the periodic values.
    Thanks
    Tangudu

    Can any one share some advice on this above query.
    Thanks
    Tangudu

  • Cost Center Assessment - cost element type 42

    Hi dear All,
    I got issues running KSU5 to allocate planned costs under cost element type 42. we were expecting that all planned costs (primary and secondary(cost element type 42)) could be allocated by credit cost center (actual). only primary costs are being allocated.
    Scenario:
    cost center planning (kp06) 1000 currencies in primary cost element in cost center A
    running planning assessment - KSUB: cycle uses assessment cost element (type 42): sender cost center A, receiver cost center B (all planned values). assessment cyles posts 1000 currencies from CC A to cost center B
    planning in cost center B (primary cost elements through kp06, 500 currencies) total planning 1000 from previous assessment  with CE type 42, and 500 from cc planning in a primari CE.
    by the period end closing, tcode KSU5 (allocation actual) is running. new cycle created, based on planned values (origini not actual, but planned amounts).
    we were expecting to allocate 1500 currencies from cost center B to cost center C (using 100% and through assessment cost element)).
    result: credit actual cost center B = 500 currencies debit actual cost center C = 500 currencies.
    1000 currencies pending on cost center B (planned).
    do you know why SAP is not allocating the 1000? even if those 1000 were planned in cost center B by assessement, a new allocation cycle should be able to post them or not?
    thank you for your outcome.

    Hi dear Ajay, thank you for your answer.
    first, I understand the difference between KSUB and KSU5, in the defined scenario, we have both. planned values, become actual with the MEC activities. business definition.
    regarding the cycle, I have setup assessment cost element so we can get all planned lines posted as 1.
    On sender tab I have only the cost center. no cost element defined.
    receiver its cost center.
    furthermore, i've not setup allocation structure, so all cost elements should be allow, there is no restriction on this.
    the only difference is: planned costs which their origin is already an assessment are not being assessed again.
    I can show you the print screens with cycles setup if it helps
    best regards
    MF

  • Cost Center Budget-Cost element wise

    Dear SAP Gurus,
    My client needs to create cost center budgets cost element wise. For e.g. Salary paid (code 430000) in Development Cost center (code 9901).
    We now use KPZ2 to create cost center budgets and KP06 for cost element planning. Kindly guide.
    Regards,
    Siva

    Hi Ramesh,
    Thank you for the reply. I did suggest them to use KP06 but they require some sort of validation when posting an expense (cost element) to and cost center.
    For e.g. If the travel budget for Marketing cost center is $1000, they need the system to prevent posting once that amount is exceeded.
    Any help in this regard would be appreciated.
    Regards,
    Siva

  • Cost center Vs cost elements

    can any body give examples for Cost center groups, cost centers and cost elements..
    Assigned poits..

    hi
    Cost Center Group
    Definition
    You can collect cost centers according to various criteria into groups. This enables you to use cost centers to depict the structure of the organization in the SAP System.
    Use
    You can use the groups to build cost center hierarchies, which summarize the decision-making, responsibility, and control areas according to the particular requirements of the organization. The individual cost centers form the lowest hierarchical level.
    There must be at least one group that contains all cost centers and represents the entire business organization. This cost center group is described as the standard hierarchy. You can assign more cost center groups to the standard hierarchy.
    You can also create any number of alternative groups. You can structure these, for example, according to organizational and/or functional viewpoints. Cost center groups enable you to perform evaluations for each decision-making, responsibility, or control area. They also support the processes during planning and internal allocations.
    You can assign each cost center to only one group in the standard hierarchy, but to as many alternative groups as you require.
    cost element  
    Classification of the organization's valuated consumption of production factors within a controlling area.
    Each cost element corresponds to a cost-relevant item in the chart of accounts.
    Cost centre:
    You receive an overview of the actual and plan values, or the actual and target values with the corresponding absolute and percentage variances. The reports also display the fixed and variable portions of the actual, target, and plan costs as well as the actual and planned.
    The Cost centers: Actual/Target/Variance report is structured by cost centers. The posted cost elements are listed for the selected cost center group or cost center.
    The Area: Cost Elements report is structured by cost elements. For each cost element selected, the system displays the corresponding cost centers.
    nagesh