IDOC staus 64 Processed By RBDAPP01 Ended in Idoc staus 51 How to Proceed?

Hi All ,
I had set of IDOCS in Staus 64 i processed them using the report RBDAPP01. i scheduled the back ground Job all iDocs ended in status 51 Please assist what need to be done next to process the IDocs further or to post the documents..
Thanks in Advance
Badarinarayan Patil

Hi,
Go to WE02..Give the IDOC number..
Press F8..
Expand the status..
Under the status 51..Check what is the error message you are getting while posting the IDOC..
THanks,
Naren

Similar Messages

  • Idocs not processed automatically in BW

    Dear Experts,
    I have a scenario here where I extract data from source system via process chains.
    The source system job completed and in BW, the outbound idocs resulted in the following Status (02).
    02  Error passing data to port 1
    In the infopackage message dialog, I got the message as
    Could not find code page for receiving system
    Errors have been reported in Business Information Warehouse during the IDoc update:
    In order to resolve this, I'm manually processing the idoc using program RBDAGAIN.
    Note: This issue occurs only when I trigger the infopackage via process chains.
    How do I rectify this error so that the idocs are processed automatically in BW?
    Br, Harish

    Hi,
    how much time your ecc job takes to finish job.
    Is this process chain newly created one or old one?
    if its old one, any changes were applied on this process chain recently?
    is it showing any idoc numbers at below status bar.
    if yes then try to pull them by using t code BD87.
    Can you share info pack error message screen shot.
    Thanks

  • IDOC - Delete unwanted segments and reprocess the IDOC by WE19

    HI all,
    I have an issue and wanted your help at this point of time.
    Case - Assume that an Idoc has been rejected by system due to few bad segments. Later i dentfied that in the Idoc few segments were bad and rest are good.
    If i use transaction WE19 for copying the Idoc and during selection of the segment if i delete the bad segments and copy the rest which are good. Will the Idoc be processed sucessfully with a new Idoc number so that the Bad segments i will fix it up manually in ERP. Kindly suggest. If possible let me know if any implication behind that or anything you like to add in the process to help me out.
    Kindly advice me.
    Regards,
    Pratap
    Edited by: pratap kumar on Dec 20, 2007 5:02 AM

    Hi Pratap,
    Which Idoc did you process. For each message type certain segments are Mandatory.
    for example in WPUBON01 -->following segments are mandatory
    Control Record --- Message type / Partner Type / Port / Server ID etc.....
    E1WPB01        --- Date / Time / Partner Number etc...
    E1WPB02        --- Article type / Article Number / Quantity etc...
    E1WPB03        --- Condition Type / Amount etc...
    E1WPB06        --- Payment method / Total Amount / card number etc...
    In control record we will have the  port / System ID etc.
    If other segments are not there leave it....it will process successfully.....
    To find out error segment refer  Table  EDID4 and correct the segment and post it.
    Regards,
    ManiKumaar

  • Parallel processing of the IDOCs through the program RBDAPP01

    Hello All,
    We are prcoessing the inbound IDOCS using the program RBDAPP01 by scheduling but this processing is taking lot of time to process the IDOCs.
    Please let me know how do we improove the performance of this program RBDAPP01 by making use of
    parallel processing of IDOCS?I read some documentation in this forum but not understand clearly.
    Please give some info regarding this who have already done this requirement earlier.
    Regards
    Mahesh

    Hi,
    Thanks a lot for your quick reply just by giving the package size it will initiate parallel processing?
    in our partner profiles we have setting to trigger through back ground only.
    How to use parallel processing tab in the selection screen of the program RBDAPP01?
    Regards
    Mahesh

  • Delay in the Inbound Idoc Posting Process

    Dear Friends,
    We have an scenario in the Inbound Idoc Posting Process, when we process the Idocs through the standard Inbound Program - RBDAPP01, we face the delay of 3hrs to 12 hrs, approx.
    When we try to re-process the same through the manual process, we could successfully post the Idocs, immediately.
    When the same happens, through the background job - the delay is happening.
    As we see, there is no problem with the program - RBDAPP01, but can't able to trace the delay in the process.
    Any suggestions / advises are welcome.
    Thanks in advance.

    Hi Prasanna,
    The update will happen only if a value already exists with the same unit of measure in the system. If the quantity is left blank in the system and if you are trying to update, the update might not happen. Even if the value is Zero in the system, provide the same unit of measure as the data used in the BAPI.
    Regards,
    Yogesh

  • IDoc Inbound Processing for CREMDM & DEBMDM

    Hi experts,
    I'd like to gather some feedback from you regarding the topic ERP IDoc Inbound Processing for CREMDM & DEBMDM. As you all know, there's currently no option to directly process CREMDM/DEBMDM IDocs in ERP. Currently you have to use PI for splitting the CREMDM/DEBMDM message into its related ADRMAS and CREMAS/DEBMAS IDocs.
    My areas of interest are:
    1) How satisfied are you with the current situation? Does the split work? Are there issues or problems in the current message handling? What are the Pro's and Con's from your point of view?
    2) What would be the requirements for a CREMDM/DEBMDM handler? What would you expect? Maybe you have implemented  something similar on project basis and could post some feedback?
    One painpoint I'd see with a CREMDM/DEBMDM inbound is that you'll lose the IDoc Monitoring capabilities. The message split allows a single record tracing in the IDoc Monitor (as there is a 1:1 relation between IDocs and records). This changes for the mass processing. The monitor would display only the status of the IDoc and you'd need some other monitoring capabilities to check the results on record level. What are your thoughts about that? Is the monitoring important? Would the application log be a feasible solution for that challenge?
    Additional comments are welcome, of course.
    Best regards
    Michael
    PS: @ Matt, please contact me by mail. thanks.

    Hello ,
    Here are some other pain areas regarding the message split :
    1. Complicated monitoring proess & reprocessing error idocs : We have to monitor ADRMAS & CREMAS or ADRMAS & DEBMAS during inbound processing. Also we could not find any best practices to reprocess error idocs. E.g. If ADRMAS fails & CREMAS succeeds what is the impact . Also the impact if it is reveresed. We know for sure that if CREMAS fails , vendor will not be created / updated. But we could not find specific pointers for ADRMAS failures.
    2. It is a tedious process to link CREMAS with corresponding ADRMAS idoc specially when SAP maintains internal number range for vendors.
    3 . The process is complicated if you are managing customer or vendor contact information with contact address . We could succesfully implement the integration but it took us a while to reach end-point.
    4. Splitting really does not seem to support if ERP maintains internal number range.
    5. Another major issue we observed is , if ADRMAS is under process & corresponding DEBMAS or CREMAS is posted , it fails raising the message that Account is locked. Default serialization does work in ERP system . But overlap of few microseconds also cause this error.
    Hope this helps !!
    Please let me know if you need any other specific details since we have used MDM - ECC integration using PI to its maximum extent .
    Regards
    Yogesh

  • Idoc collective processing

    Hi We have a custom idoc(Inbound) for posting goods movements...Actually it does goods movements through two seperate BDC calls and returns the material document number in the status.When we process two or more idocs through a batch processing at a same time..the first idoc goes through do the posting corretly but the second and third doesnt do anything but gets 53 status and also picks up the material doc number of the first idoc in status...
    Each idoc goes through correctly when processed individually...What might be the problem....?and how it could be corrected...?
    Thanks,
    Larry

    Hi,
    As Manohar said ,the problem is due to variables refresh. One of the variables is setting to success status after processing of the first idoc , i think the same status is transfered to next idoc's also.
    follow below steps to identify the problem.
    1.Change the partner profile settings to 'Collective method' , then idoc's will be created with 64 status.
    2.then put a break point at processing function module.
    3.use BD87 or program : RBDAPP01 to process 64 status idoc's , while processing idoc's take more than one 64 status idoc. then you will know the exact problem.due to break point, program will go to debug mode, after processing of the first idoc then start debugging the program with second idoc processing.
    Regards
    Appana

  • Idocs parallel processing

    Hi,
    We have some goods movement idocs(MBGMCR/MBGMCR03)getting posted simultaneosly.(Std ALE idocs no customization)We dont want to collect it and process it(timing issue).When we allow it to process immediately material batch combination gets locked out and one idoc goes through and others fail...i know we can collect it and process it through a batch prog setting RBDAPP01 variant with no prallel processing but is there any way i can switch on immediately and allow each idocs to process one by one avoiding parallel processing..?
    Thanks,
    Larry

    Hi Larry,
    Please check your partner profile (WE20) and set to trigger immediately under processing by function module area.
    Regards,
    Ferry Lianto

  • File to IDoc ( sequential processing )

    Hi All,
       I need a clarification for one of  my scenario..
    The scenario is about PO create, PO change and PO del. We receive a flat file with all the above mentioned in the same file in any order.. But we need to ensure that we <b>post and process all of them in sequence as we receive from the file</b>..
    We need to consider the performance even. Please suggest on how to go ahead with this..
    Thanks in advance..
    Rgds,
    Yuva.

    thanks for reply.
    Am not clear in the concept you are saying.
    Let me give more details abt the scenario.
    XI gets the flatfile form the legacy with PO create/change/delete, were it maybe in any order.
    Maintaining the order in XI for pickup and sending the IDOC is not a problem, but in R/3 how to confirm processing order as it receives.
    plz help.

  • Error : Pre Settings for IDoc inbound processing are missing error

    Hi Experts,
    There is a CRM job which executes LSMW and I am facing a strange problem during the IDOC posting the error "Pre Settings for IDoc inbound processing are missing error". Can anyone please tell me how to correct this error?
    Thanks in advance.
    Madhurima.

    I'd start with the following document, with one modification. At step 12 after typing GEARAspiWDM press the Enter/Return key once prior to clicking OK. (Pressing Return adds a carriage return in the field and is important.)
    [iTunes for Windows: "Registry settings" warning when opening iTunes|http://support.apple.com/kb/TS3299]

  • #'s coming up in IDOC when IDOC flatfile processed with RSEINB00

    Hi,
    We have given IDOCs in flatfile structure which are needed to be loaded in backend SAP R/3 through XI and it needs some transformation,so we are using XI for mapping in between,otherwise we would have processed directly into R3.
    Basically we are placing IDOC Flatfile in a folder and we are running RSEINB00 program on XI through a file port in XI and IDOCS are getting created in Backend SAP R/3.
    When we place IDOC flatfile in Windows folder and process the file we are getting #s in IDOC fileds(many fields) ,but we don't see any #s when we process the IDOC flatfile when placing IDOC flatfile on UNIX .Our XI/PI is running on UNIX.
    please help,what causing the problem?
    Thank you,
    Regards,
    Sathish

    Hi Ravi kanth,
    I see them (#s)in IDOC fields in backend SAP R/3 once the IDOC flatfile got processed.
    as we are running RSEINB00 report on XI ,we noticed that empty tags are coming (from Windows OS Folder)in SXMB_MONI even before my mapping execution ,I think they are being populated as # in IDOC.but dont see this problem when IDOC file processed from UNIX folder.
    You think ,if we save file in UTF-8 format or Binary might help rather than ANSI format and process it.
    Thank you,
    Sathish

  • LSMW idoc Inbound Processing settings

    Hi,
    We have done LSMW with BAPI method to create Bank master.
    In Idoc Inbound Processing settings -
    We created partner type as 'B' i.e, for BANK
    While creating Partner Number it is not allowing to create Partner Number. The error is  "Enter a permissible partner number"
    Please let me know what would be the problem.
    Regards,
    Hari
    Edited by: Bhatlapenumarthy Hari Krishna on Sep 12, 2008 9:31 AM

    Hi,
    Use patner type as US only and LSMW as Patner number.
    this will surely solve your problem .
    plz do this way :
    The first requirement is a file port for the file transfer. If required, create a port of the file type via Maintain ports. To do this, position the cursor on "File" and press Create. You should be in change mode. SAP recommends:
    Port: LSMW
    Name: Legacy System Migration Workbench
    Version: 3 (IDoc record types SAP Release 4.x)
    Outbound file Please enter a (dummy) physical directory and a file name, i.e. u2018filelsmwu2019 ·
    As an addition, you can specify a tRFC port. This port is required, if you do not want to create a file during data conversion but submit the data in packages directly to function module IDoc_Inbound_Asynchronous.
    SAP recommends:
    Port: assigned by the system
    Version: 3 (IDoc record types SAP Release 4.x)
    RFC destination: Name of R/3 System
    Name of port: Legacy System Migration Workbench.
    Then the partner type should be defined or selected. SAP recommends:
    Partner type: "US" (User)
    As of release 4.5A, this partner type is available in the standard system. Up to release 4.0B inclusive, this partner type is not available in the standard program and should be added. SAP recommends:
    Partner type: Create US
    Report name: /SAPDMC/SAP_LSMW_PARTNERTYPES
    Form routine: READ_USER
    Short description: any.
    Finally a partner number should be defined or selected. SAP recommends:
    Partner number: LSMW
    Partner type: US
    Partner status: A (active)
    Type: US
    Language: DE or EN
    Person in charge: Your user ID.
    Activate IDoc inbound processing
    reference : help.sap
    thanx.
    Edited by: Dhanashri Pawar on Sep 12, 2008 7:10 AM

  • IDOC getting processed in reverse order

    Hello All,
    In our system whenever changes are made in the customer master an IDOC is generated.
    In my scenario i have created a ship to party for which an IDOC got generated as say 10.
    Now i add this ship to the sold to party due to which another IDOC got generated Say 20.
    Now in the partner profile settings we ahve the customization setting to process the IDOC immedialtely.
    So on saving a customer master automatically a IDOC with status '03' got generated.
    At night program RBMOIND is executed to process the IDOC in status 03 to send to the subsystem and change the status to 12.
    In this program data is retreived from the table EDIDS for the IDOC with status '03'.
    We are selecting the field TID from the table EDIDS.
    And then this field is split in the fields of structure arfctid.
    Now a sort is done on the retrieved data.
    In our scernario the value that got updated in TID field for the IDOC 20 is smaller as compared to IDOC 10.
    So due to which the IDOC 20 got processed earlier than IDOC 10.
    Can anybody please let me now why this particular problem is occuring.
    At the same time can anybody tell me how the entry in the field TID of table EDIDS got updated.Is there any logic in program RSEOUT00 that change the status of IDOC from 30 to 03 written based on which it gets updated.
    Thanks,
    Mohit

    Hello
    Can anybody provide any input on this....
    Mohit

  • IDOC Inboun processing success but no record posted to table

    Hi,
       We are performing ALE refresh in RCD221 (development system). The ALE IDOCS are extracted for HR area with Message class as HRMD_A, the IDOCS are processed successfully from the sending system (RCB) and reaches the receving system RCD221. While we process the inbound IDOCS in RCD221 records are not getting posted in the table, however the IDOC status is shown as successful (53). This is happening when we are processing the data for object type 'P'.
    Regards,
    Bharath Mohan B.

    RFC destinations, Logical systems, and then Partner profiles needs to be maintained. and You need to create the Distribution model  in sender system.
    Partner profiles maintained in both the systems, soure Outbound properties
    Target Inbound properties.
    if you have two clients in system it will be easily you can check.

  • RFC For IDoc outbound processing

    I am creating an RFC for BDC for call transaction we19
    input as : idoc number
    and output:-.. iDoc Outbound processing done
    so:-
    I go to we19> give iDoc Number (say, some number for ALEREQ01), and execute> click on Outbound processing-->click enter -->enter
    in this way, I can process any iDoc from SAP system to outbound.
    I want  to create RFC for the same.
    Problem:-
    when i am executing that RFC, and when I check the iDoc status in we05, that iDoc shows status as Idoc ready to dispatch( its in yellow color).. Its not showing green color and not saying that IDoc passed OK
    when I try manually ,I see the status green..OK..successfully
    Any idea why I am getting this problem??
    Is there any problem in my BDC recording?..but when I run that recording for Process, i dont see any problem,it executes successfully.. but when I copy the Code from BDC and make a RFC using that code, its giving problem as mentioned.

    Hi Ankit,
    Theorotically it should work.... but I'll suggest not to use BDC here. What you can do is,
    1. You have Idoc number..Right?
    2. Read control record from EDIDC and data record from EDID4.
    3. Then call Master_idoc_distribute.
    4. This will again distribute the same IDoc with same control and data record as a new one. It will be same as WE19 , but without WE19.
    Please check and confirm.
    Regards,
    Audy.