Hi all,
Can someone help me confirm the following?
I'm implementing Investment Management module and use appropriation request (AR) to approve budgets where AR statuses can be approved only by certain authorization groups, and we do not use Workflow. The problem is that we want the status change not only based on authorization but combined with the budget value. For example, for budget <50,000 then Superintendants can approve the AR but if it's >50,000 then only Managers can approve the AR.
As far as I've looked, IM module does not provide this functionality where authorization can be restricted based on budget value. Can someone confirm this?
Thx very much in advance!
cheers,
-Ri-

The standard AR workflow sends a notification (document once approved) to the applicant and workflow to the approver (for approval). For details refer the link below:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f542493111d182b70000e829fbfe/content.htm
Standard reports under Investment Management>Appropriation Requests>Reports on Appropriation Requests>Master Data Lists ex.,T Code IMR5 - Appropriation Request Without Distribution Without Variants with changed layout to include system status would show you the required information.
Regards
Sreenivas

Similar Messages

  • Appropriation Request Flag - Ordinary/Extra-ordinary budget

    I want to identify which Appropriation Request will erode a budget of type ordinary or extra-ordinary. Instead of creating a separate level in my investment structure, I want to flag my Appropriation Request with a tag which I can identify in reports.
    Which transaction/component in SAP IM will let me do this?
    I have tried without luck with STRGTFLG.... Any help....
    Thanks,
    Veronica

    Do you want to use some of the standard fields available in the master data of the appropriation request like Appropriation Request Type?
    If none of the standard fields provided by SAP are suitable for User Fields can also be added. Attached screen shot will expalin what I meant.
    Please see this documentation Functions of the Appropriation Request Type - Investment Management (IM) - SAP Library especially the paragraph "Master Data".

  • Appropriation Request , Approval

    Hi All,
    required help in mapping 1 senario.
    1. AR passes from the approval phases depending upon the value and the data entered..
    2. When the AR is approved the Approval will  differ from the planed value , how to map this senario
    with the Approval amount.
    Regards
    Hemant

    Hi Hemant,
    You'll need to take help from workflow consultant for this. This cannot be done in Standard.
    WF can read plan values of the AR from relevant tables and choose the approval path accordingly.
    pass IMAK-POSNR in IMAV. Read IMAV-OBJNR and pass its value in BPGE or BPJA to get the plan value for the AR.
    Without overhead cost is value type 40, and with oH cost is 39
    with regards,
    Ravi Shrivastav

  • BI Reporting Authorization  Based on Characteristic Value  Level Error

    Dear ALL,
    i had create one authorization on sap bi and given to one user on plant level , it will work on fine RSRT,
    But when i am used it on webi report through this user then i am getting below error
    Database Error : Error in MDDataSetBW.GetCellData. You do not have Sufficient Authorization (IES 10901).
    But in repor if other than user is login and report will work fine.
    If in this report i removed key figure and only show plant then it will work with authorization.
    Please help me out from here....
    Thank You,
    Haresh

    Hi,
    "If in this report i removed key figure and only show plant then it will work with authorization."
    even afterremoving keyfigures you should  not get the records, if it is the issue with Authorization object that you have created. Check for some other authorization issues also.
    I dont know SU53 marks Authorization error, if you run from WEBI, but try that also once.
    Hope you have seen this thread,
    https://scn.sap.com/thread/1136359
    so, there is no single reason for this error
    try posting this thread in BOBJ Integration kit forum also, there some experts can help you quickly
    -Sriram
    Message was edited by: Sriramvijay R

  • Appropriation Request authorizations

    How can I manage my Appropriation Request if one of the steps requires a project to determine its outcome (approval/refusal)?
    My setup is as follows:
    Appropriation Request 1 approval:
    Step 1: Approve (y/n)
    y
    Step 2: Approve (y/n)
    y
    Step 3: Approve (y/n)
    >>>> Create additional Appropriation Request
    >>>> Appropriation Request outcome (if y then y, else n)
    Step 4: Approve (y/n)
    y
    Step 5: Approve (y/n)
    Appropriation Request approved >>> Investment Measure creation.
    The reason for having this set up is because the authorizor might require a team of resources to analyze some factors to determine the outcome.
    Is this possible to set up in SAP Investment Mangament?
    If so how?
    Kindest Regards,
    Vero

    Hi Veronica,
    If you are not using user status, then you can built different user status approval as user status.
    These status can be activated at created between released, once the final status is reached, it can be released.
    But you need to restrict the same with roles and authorization and requires security resource to complete the activity.
    Another way is my using Person Involved, you can maintain the partner function and determine the list of approvers and you can also trigger email based on this. May be bit of Abap work is required.
    Regards
    Terence

  • Budget Supplement using Appropriation Request.

    Dear Friends,
    As per our business scenario, we have to create project thru Appropriation Request. In case the budget needs Supplement, that same is also needs to be mapped using Appropriation Request.
    The system is restricting creation of further ARs for WBSE once it is assigned to IM Position.
    Technically, system dose not seem to have provision of budget supplement to an already assigned project (to IM Position) using Appropriation Request.
    My Question: Is there any setting or Workaround thru which we can Use Appropriation Requests to request for Budget Supplements for a Project thats already assigned to an IM Postion( after replacing Initial AR). ?
    Regards,
    Seemant

    I feel that after replacing AR , as your project is assigned to IM postion. you can  distribute the budget to project by  IM postion only  via IM52. 
    Because AR is made for management of the planning and approval phase of investments and other types of measures
    And IMProgram & postion is made for cyclical planning and management of investment budgets for a number of measures, throughout your whole enterprise
    If you knew that  you want extra budget you can take care the same via planning additional cost on AR.
    If IM Postion itself is not having sufficient budget than you can supplement there as well via IM32.
    please refer this link
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/2a/f9f405493111d182b70000e829fbfe/frameset.htm
    Regards
    Nitin

  • Approval of appropriation request BUS2104

    Hello,
    i have a problem with workflow of  appropriation request  approval. The problem is with background jobs. Are there any other settings about applicant and responsible person, because when the messsage for approval, rejection, posponding is triggered the system status is Error and no agent assigned. In the log file have errors WL821 and SO023.
    Work item 000000394366: Object 000000394366 method SWW_BI_EXECUTE_S cannot be executed
    Document <Appropriation request 4000000008 is rejected> could not be sent
    Work item 000000394298: Object SELFITEM method SENDTASKDESCRIPTION cannot be executed
    Object element 'RECEIVERS' has invalid internal state
    Method container for work item cannot be created
    Can anybody help me.
    Thank's in advance!

    Hi,  -->> "Work item 000000394298: Object SELFITEM method SENDTASKDESCRIPTION cannot be executed
    Object element 'RECEIVERS' has invalid internal state"
    It seems, there is a binding issue in your email step. Just check in the workflow log for the correpsonding workitem

  • Workflow approval appropriation request by value

    Hi,
    my customer wants for the appropriation request various workflow dependent from the value.
    For example, if the value is less 100K euro, then the workflow have two step of approval, if the value of investment is more than 100K the workflow must to have 4 step of approval,
    Is there anyway for do this?
    Thanks in advance
    Regards

    Hi,
    Pl try Substitution and this is the only option. If you need some more inputs, please revert back.
    Trust this helps much!
    Cheers,

  • Currency conversion based on budget rate

    Hi All,
    I want to do the currency translation from GBP to EUR,EUR to USD and GBP to USD.there is no table maintained in the BW system.Currency conversion should be based on budget values and they are asked me to do on reporting level.I have gone thru the documents and blogs but not able to follow them.Could you pls share any one knowledge and step by step process.
    Thanks

    Use RSCUR transaction to create currency translation type.
    Here under "Time Ref" tab use "Variable Time Ref" and special infoobject.
    You should be able to choose Posting period or posting date here.
    Now in query designer maintain the currency conversion based on this currency translation type.
    Hope this helps.

  • Fix authorizations for the budget approval flow (internal orders)

    Hi,
    I need to fix the authorizations for the budget approval flow.
    What do I need to take into account?
    Thank you.
    Kind regards,
    Linda

    (1) Each appropriation request should be attached to an investment program (leaf) position. To update the approved budget on the investment program from time to time, you should
        -  make a plan rollup from the appropriation requests to the program positions via IM34 (use an appropriate status selection profile on the initial screen of IM34 and select appropriation requests only to make sure that
           >  only appropriation requests
           >  with status 'Approved' are taken into account),
        -  To budget the investment program via IM32, set view 'Planned total' (Menu: 'Views -> Planned total') and copy this view, which contains the latest approved budget amounts, to the "real" budget (Menu: 'Edit -> Select -> Select all' and then 'Edit -> Copy view').
    (2) You can even generate an order from the appropriation request that enherits the appropriation requests plan value. For details see SAP Library (Menu: 'Help -> SAP Library'), path 'Financials -> IM Investment Management -> Appropriation Requests -> Replacement by a measure for implementation'.  Analogously to step (1), you can also take over the orders 'Planned total' view into the orders budget via txn IM52.
    If you strictly limit the authorisations to execute IM34, IM32 and IM52 as pointed out in steps (1) and (2) to a handful of people who execute these functions as pointed out above (withoud adding or removing budget arbitrarily, of course), the budgeting process
    really focusses on planning/approving appropriation requests which is fully accompanied by the approval workflow.
    Hope above helps you.
    Regards
    Siva

  • Workflow approval appropriation request

    Hi guru,
    is it possible to creta a workflow for approval appropriation request based on amount of the investment?
    For example:
    if amount of appropriation request is less of 100k euro then approver is A
    if amount of appropriation request is more of 100k euro then approver is B
    Could you help me?
    Thanks in advance
    Regards

    Hi,
    Pl try Substitution and this is the only option. If you need some more inputs, please revert back.
    Trust this helps much!
    Cheers,

  • Approval levels appropriation request

    Hi guru,
    for my appropriation request, I have 3 levels of approval.
    I want to know, which is the level of approval in every time.
    For example, I set my appropriation request with status " For approval" and the workflow starts.
    If i see the appropriation request the day after, I want to know if the appropriation request is to 1st level, 2nd level o 3rd level.
    Is it possible to know this information?
    Thanks in advance
    Regards

    Hi Raffael,
         There is no report for exact use your mentioning. But yes you can develop a quick report based on SWWWIHEAD and SWWUSERWI. Where as SWWWIHEAD will give you details of workitem and SWWUSERWI wil give you details about possible or actual agents for a given work item.
        Theer are some standard transactions as mentioned by other forum members. But by my experience users need to be more advanced than basic level users to understand it. if it is for your self then thos might be ok. But still if you need a report for regular monitoring i would recommend a bespoke report.
    Warm Regards,
    Anuj Nagpal

  • Re: Approving two plan variants in an appropriation request

    Hi All
    I have created a variant 01 for appropriation request and approved it. I want to supplement the same appropriation request with a new budget. So , I created a new variant , and assigned it to a new plan version...But the problem here is I was unable to approve the new variant...The approval button is grayed out...Can anyone help me out please...Why the system is not letting me to approve the new plan variant.

    Hi ,
    as I said variants are like quotations, so you have to maintain it...........
    in case of rolling up plan values you have to select respective status profile before rolling up respective variant version or variant version range.......  (IM34)
    1. approved status profile...
    2. created status profile..
    3. released status profile...... like that
    - give both CRTD & APPRD versions  in IM34... select status profile for approved & roll up
    then check in IM36 ...
    Regards,
    Venkatesh

  • RE: Approving supplement to an appropriation request which was already appr

    Hi All
    we will create an apropriation request with an initial budget and we will approve one of the different variants of the appropriation request....But in our business process we have to add supplements to the current appropriation requests every quarter ....And the supplements also have to go through the approval process( It is a requirement).....Can any one help me telling the different solutions. Pleaseeeee

    Hi Ravi,
    I saw your post and scenario 2 that you mentioned in your reply to Steve, is the scenario I am faced with. I would really like your input...
    I want to be able to create a budget supplement using AR process and workflow, but instead of replacing the approver AR with WBS(measure) I want to allocate the approved funds to an existing WBS as supplement...
    then do rollup and budget distribution...
    can you please advice me?
    thank you

  • BAPI/Function Module for approve Appropriation Request?

    Hi Friends,
    Please guide me for
    BAPI/Function Module for approve Appropriation Request?
    Regards
    Ricky

    Hello
    Check these BAPI
    BAPI_APPREQUEST_ADDVARIANT     Add a Variant to an Appropriation Request
    BAPI_APPREQUEST_CHANGE         Change an Appropriation Request
    BAPI_APPREQUEST_CHANGEVARIANT  Change Appropriation Request Variant
    BAPI_APPREQUEST_CREATE         Create Appropriation Request
    BAPI_APPREQUEST_DELETE         Deletion of an Appropriation Request
    BAPI_APPREQUEST_GETDETAIL      Display of an Appropriation Request
    BAPI_APPREQUEST_GETSTATUS      Display Status of an Appropriation Request
    BAPI_APPREQUEST_REMOVEVARIANT  Delete an Appropriation Request Variant
    BAPI_APPREQUEST_SETSTATUS      Setting System and User Status of Appropriation Request
    BAPI_APPREQUEST_SETSTATUSVARNT Setting of User and System Status on Variants