In correct period in control record

hi sap experts
1. posting only possible in period 2002-11 &2002-10 in co. xyxy
as i was sugested by u i have tried mmpv
now the problem is msg comming incorrect period in control record for co cd xyxy. so no conversion  the current period of the control record is 12-2002
pls throw some light on this
thanks in advance

hi,
Firstly check the open periods for the compnay code in OMSY...
If its not open then try in the MMPV to open it...
You can also open it in OB52..which is FI trasaction...it open/close the two periods consicutively...
You can reopen the periods but its not recomended...you can use MMRV..for back posting allowed...
or else check this
goto SU3
select user profile
in parameter ID give MMPI_READ_NOTE , and in parameterr value enter todays yyyymmdd and save.
and goto MMPI intialise the periods to present one at a strech.

Similar Messages

  • Control records - Payroll Period

    Hi Expert,
    Can anyone help me with following situations?
    I am creating control records...I am facing problem what should I enter in "Payroll Period" when I have defined period parameter, monthly..
    Looking forward to your prompt reply.
    Regards,
    XXX

    Hi,
    First you have to understand the concept of payroll period. Payroll period is generated using period parameter and date modifier. Payroll period defines the exact start and end date of a period and the pay day. Here it defines the period number, which is very important to identify for which payroll period you are currently with. To make it clear let us have an example. A company is paying a group of employees monthly. In a year there are twelve months, so every payroll period is given a number. If the payroll period is for jan 01 to jan 31, 2011. It would be indicated as payroll period 01 in the year 2011. It should be generated before using it in control record. Based on your start and end date of the period, you have to enter those values. Check the table v_t549q to check whether the required payroll periods exists or not. If available use the relevant payroll period. Note that the payroll period used to create the payroll control records must be one period before the period in which you want to go live. Eg. If you are to go live in period 05,2011. You must enter period 04,2005 in the control record. To generate payroll period use the tcode OG00
    regards,
    praveen.

  • Issue : Regarding Control Record

    Greetings Guru's,
    We are going to be running our first payroll of the year in SAP at the end of this month. However the employees have been hired as of 01/03/2010. The payroll control record is in period 3 (01/03/2010 - 31/03/2010) and it is in correction mode.
    What do I do with this record when we want to run the payroll for period 04/2010 ? Do I just delete the 03/2010 record (as there has been no payroll run at all) and then recreate it for 04/2010 with the earliest retro date set as 03/2010 ??
    Any help will be appreciated...

    Hi
    If you want to run payroll for 01 - Apr - 2010 to 31 - Apr - 2010 the exit payroll for march 2010 if there is no employee left for payroll run and then Release payroll for April 2010. it will help you.
    After this if any retro will perform for March 2010 and you don't want this then set Arely Per. Retro date  as 01 04 2010  in Infotype 0003 for the employee.
    Regards
    Swapnil

  • Closed period for Material Record

    Hi,
    I did MIGO: 101
    -document day: 26.09.2010
    -posting day: 26.09.2010
    everything is ok and i verify ,  I get this message :Only possible to post  periods 2010/09 and 2010/08 for company 0211
    So i Checked
    1. - MMPV   (LOG) : seems to be ok
    -Incorrect period in control rec. of CoCd 0002; no conversion
    -The current period (month/year) of the control record is092010
    - Period closing complete; log issued.u201D
    2.- OMSY, seems to be ok
    Co     Co name     year     Pe     Fyr     M     Fyr     LM     ABp
    0002     xxxxx     2010     9     2010     8     2009     12     x 
    3.- OB52 : seems to be ok
    0002     +              1     2010     12     2010     13     2010     16     2010
    0002     A ZZZZZZ     1     2010     12     2010     13     2010     16     2010
    0002     D ZZZZZZ     1     2010     12     2010     13     2010     16     2010
    0002     K ZZZZZZ     1     2010     12     2010     13     2010     16     2010
    0002     M ZZZZZZ     1     2010     12     2010     13     2010     16     2010
    4.-  OB37 seems to be ok but i have a doubt in V6 if it is causing the problem?  but V6 is the correct selection
    0002     XXXXXXXXX      V6     July-June, 4 períods spec.
    5.- Table MARV seems to be OK
    0002     2010            09             2010           08           2009           12            X
    Regards,
    Edited by: buck485821 on Sep 26, 2010 12:47 PM
    Edited by: buck485821 on Sep 26, 2010 1:48 PM
    Edited by: buck485821 on Sep 26, 2010 2:01 PM

    I found the problem
    Fiscal year variant is V6  (oby6) and actual material period is 9 and should be 3 (MMRV)
    I am in Development enviorement. Anyone can help me to fix this. , thanks and regards

  • Offcycle error and payroll control record

    hi experts,
    i faced a error in offcycle payroll processing.
    i did exit payroll for april 2008 and maintained a data in infotype 267 for bonus in 15.05.2008 for 50 employees in bulk.
    i want to run offcycle payroll thro normal payroll driver on 15.05.2008  using HINCALCO and selected the required parameters in off cycle reason and facing error while doing update run.
    simulation run is showing offcycle results correctly and system not allowing to run update run and showing  error related to payroll control record .
    how to recify this ?
    nataraj s

    dear expert,
    offcycle payroll program will work only when the payroll control record is in exit status for past payroll  period
    i cannot change the payroll status to release for payroll status
    i tried earlier and it didnt work
    i tried to run offcycle for 15th may 2008 by keeping payroll control record release for payroll in may 2008 and it didnt work at all
    what i wanted is the save button in the offcycle program is not in active mode when i am able to default the wage type values from infotype 267
    regards
    nataraj

  • Unable to delete period from Periods in Control tables

    I am trying to delete period 'Sep' from Periods in Control Tables.
    But getting msg as 'FDM was unable to find the Record to delete'.
    Not sure whether the record got deleted internally.But I can still see it in my Period list in Control tables.
    Cud anyone suggest how shud I delete period from Control tables and where these periods are stored internally in FDM??
    Waiting for Reply!!!!!!

    Hi,
    There is also a note in Metalink which suggests the record be deleted from workbench client. I did that and it worked. The cause is stated as the record not being entered correctly, and hence the application is unable to find it.
    Thanks
    Ramya

  • Control record issue !

    Hi All,
    I am handling UK Payroll and got an issues related to payroll run and control record,
    Issue 1: The payroll driver (RPCALCG0) has skipped around 1500 Employees against payroll run for particular period
    Issue 2: How control record allowed user to Exit control record for period in which EE's skipped in payroll
    Please provide your valuable suggesting in regard to resolve the above two issues,
    Thanks in advance.
    Regards,
    Devendra Reddy D.

    Hi,
    Issue 1: The payroll driver (RPCALCG0) has skipped around 1500 Employees against payroll run for particular period
    Say you want to run payroll for FEB..
    But payroll control record may not be in FEB... It may be in March..
    Issue 2: How control record allowed user to Exit control record for period in which EE's skipped in payroll
    Payroll control record may have been deleted on the month of Jan..& been set in Release mode in March month directly...
    So feb month gets skipped & Exit mode in Feb is skipped too...
    For detailed info.. Go to PA03 enter payroll ares & click display option..
    Under Go To tab.. look for Control Record Log..
    Regards,
    Veeram

  • HIRE Employee prev to the retro accounting period in payroll record

    Hi All,
    I have an issue when I try to hire an employee in the system. The system doesn't allow me to hire any employee before Nov 2009 as the retro accounting period for that payroll area is dated to 11 2009.
    The retro accounting period changed from 10 2005 to 11 2009, when it did not change for any other payroll area.
    Can anyone suggest a solution as how to hire an employee beyond this date?

    in one case we can perform this activity why the user will forget to hire an employee who got hired for the previous months
    U have to change the Retro date in the control record as per the isssue
    ask the client to use the system accurately  other wise deleting the control record is not good practice  in some cases we can do and we have to do
    but this above said shd not be the reason

  • Error during creating a control record

    Hi Experts,
    we are using  EEC6.03 version.
    system error..
    Change before earliest retro. date 01.03.2010 acc. to control rec. to py area CO
    Error-
    While creating Control Record, system takes advance period.
    example-
    We have given present payroll period as 12.2009, and  earliest retro active accounting peroid  as 10.2009,
    then system takes the date 01.03.2010.
    Actually System should take present payroll period as 01.12.2009, But is shows as 01.03.2010. I am unable to understand.
    Please Help me out Guys.

    Hi,
    It seems that your payroll periods are screwed up. To check that please check table V_T549Q (SM30) and see if period corresponds to dates. Period parameter is assigned to payroll area in table V_T549A.
    Then if it is wrong you can regenerate them using transaction OG00. Please read report help thoroughly.
    Cheers

  • Transaction mmpv incorrect period in control rec

    transaction mmpv close period for material master record
    i enter company code 4000 period 07 fy 2004
    check and close period
    i get specified year is not the current year when i execute
    in the log i get
    incorrect period in control rec cocd 4000current period of the control record is 07 2004.
    what am i doing wrong?

    Hi Janice,
    Check this thread.. It has ur answer..
    Quarry in Posting period
    cheers,
    Prashanth
    P.S Please mark helpful answers

  • How to handle the control records in case of file to idoc scenario.

    Hi All,
    can you please clarify me how to handle the control records in case of file to idoc scenario.

    Hi,
    In File to Idoc scenario even though you selected apply control record values from payload and you are not getting those correct values which you have provided in the mapping.
    Also check the checkboxes Take sender from payload and Take receiver from payload along with the Apply control record values from payload checkbox
    Regards
    Seshagiri

  • Sender port in control record

    Hey guys
    i m trying to test my IDOC to FIle scenario and in WE19 i m getting an error with status 37 saying that sender port in control records is invalid.
    i have created the Sender port correctly in WE21,what might the problem be?
    thanx
    ahmad

    HI,
    As you said you have created the port with WE21.
    Did you checked , RFC destination which was configured in Port creation , what was the user ,pwd you used,does that user has the proper authorization , did you checked remote login for RFC destination,generally SAPxxx for port name, did you selected the version which was selected.
    let me know what is the correct error.
    Regards
    Chilla..

  • Receiver partner type in control record is default"

    Hi all,
    I am Getting 56 Error"Receiver partner type in control record is default".
    When I go to that perticular IDoc under control record under parter tab I am providing "PARTNER TYP" AND PORT.When I save these details th idoc is getting posted.
    The  port ifo is present in we21.I checked RFC Destination,It is fine.
    Now where to give this information centrally since I have to manually enter this every time.
    Thanks,
    SrinivasaP

    Hi,
    If error is 56.
    Check the partner profile is created or not, if not create partner profile, restart the process by TA.BD87.
    If partner profile is exist then check the control information in the IDoc file is incorrect. Correct the IDoc file and restart the process
    Please check receiver IDoc Adapter is configured with the said details are not.
    And if possible map the values in EDI_DC40 control record.then you need not to give these details every time.
    Regards
    Chilla..

  • Partner determination in control record for EDI

    Hi all,
        I have a custom EDI output which goes into the delivery.  However this EDI output is not picking the correct partner.
    The sales order with 2 plants would create 2 deliveries.   First delivery is created for plant A121 while second delivery is created for plant A710.   However, the vendor partner is not picked up correctly for plant A121 in the first delivery.  LIkewise the second delivery.  When the sales order has same plants, it create 1 delivery.  This comes out with correct partner.
      My question is:  How is the partner determined in EDI control record before the delivery is created ?
    In Partner Profile, WE20, there are 3 defined partners (100 LI, 200 LI, 300 LI).  For plant A121, the partner would be vendor 200.
    Thanks
    Joyce

    Hi Vinod,
       Thanks for your suggestion.  I have condiiton record for this EDI which is plant and it would list the partner.  Somehow, it seems the plant is not picked up correctly when there are a few plants in the sales order.   Becasue the partner is not picked up correctly, it seems to affect other output types that are plant-based.
        Initially the all output for EDI works fine.  There have been recent changes made to split delivery by plant which is fine  Output is one that are having issues.
       Have you any other suggestions ?  I will continue to look at the program  you suggested.
    thank you.\
    Joyce
    Edited by: Joyce Chan on Mar 17, 2010 8:31 PM

  • Serialisation field in control record in idocs

    Hi Experts,
    I have one requirement like this.While generating idocs in control record we get serialization number by combining system date and time.
    But now my requirement is i have to change that serialisation field with required timestamp.Can we do this? If so can anyone explain me how to do that?
    Wiating for your valuable replies.
    Points will be rewarded.
    Regards,
    Swetha.

    hi,
    Firstly check the open periods for the compnay code in OMSY...
    If its not open then try in the MMPV to open it...
    You can also open it in OB52..which is FI trasaction...it open/close the two periods consicutively...
    You can reopen the periods but its not recomended...you can use MMRV..for back posting allowed...
    or else check this
    goto SU3
    select user profile
    in parameter ID give MMPI_READ_NOTE , and in parameterr value enter todays yyyymmdd and save.
    and goto MMPI intialise the periods to present one at a strech.

Maybe you are looking for

  • Updated to 3.1.3, now iPhone won't show up in iTunes

    Updated to 3.1.1, now my iPhone won't show up in iTunes. iTunes starts up when I plug in my iPhone, but then SyncServer.exe just sits there running taking up 50% of the processor. Everything worked fine before the 3.1.3 upgrade, now it doesn't.

  • Mail freezes when I try to send a group an attachment from contacts

    I tried to send an e-mail group located in my Contacts app a .pdf attachment but the Mail app freezes and does not send the e-mail.  When I manually input the e-mail addresses and try to send the same attachment the e-mail goes through just fine.  Ha

  • Problem in Converting Ms Word document while usining Star office 9

    i open very Complicated Word document using many styles format ,fonts,Pictures i lose my margins and the document need to be aligned and arranged again.But when i save it by .rtf i get 95% of the document structure please advise.

  • ORA-3106 : fatal two-task communication protocol error

    We get the following error intermittantly in our server. We are using WebLogic 6.1. Any reason. Here is the log we are getting... Parsing: BEGIN gid_msg_fund.fund_get_details (:1, :2, :3, :4, :5, :6, :7, :8) ; END; Executing: BEGIN gid_msg_fund.fund_

  • Best Practices about context

    Hi SAP developers, I need somebody with a lot of WebDynpro experience. My question is the following: Under what conditions is it advisable to map context nodes/conetx attributes and when should I use the construct wdThis.wdGetTestComp().wdGetContext(