In IW32 no Planned Cost and Actual is showing Zero
hi,
In IW32 no Planned Cost and Actual is showing Zero,since activity type is mentioned.
how it could be displayed.
Thanks
Dear Sharma,
1. This is regarding Maintenance order, frist you confirm by clicking on the operations tab-> double clicking on the work center->click on costing tab, check here activity type, activity unit is maintained.
2. then in in KP26 check the activity price in the current period.if it is zero u will get zero
3 then in the order click on components, if components are consumed also check the component price in material master.
this will resolve your issue
sree
Similar Messages
-
IW32 needed Plan Cost and Actual Cost table name
Hello ,
In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
Req: needed plan cost & actual cost table names for particular order number.( For New Report )
Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
Thanks in advance !
Regards
Rahulhi ,
i too had same issue , i wrote following FS for that :
Actual and planned cost from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for PMCO-OBJNR taken from CAUFV -OBJNR for order number AFIH-AUFNR and also currency from CAUFV-WAERS .
Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type PMCO-WRTTP = 1 , which will be placed in different column
hope this helps
regards
satish -
In which table production order planned cost and actual cost i can see?
Dear PP Guru,s,
from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
Regards,
sreeDear,
Planned and actual costs of prod order from COEP, COSS, COSP S027 tables
production order shows the planned cost based on the quantity structure.
Please refer my reply in this thread for details,
Re: Actual Halb Material Cost
Regards,
R.Brahmankar -
Function Module to find Planned Costs and Actual Costs against WBS element
Dear All,
We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
Are there any function modules to retrieve this value?
Thanks for the help.
Warm Regards,
JudithHi,
The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
Please let me know if this helps.
jibat -
Dashboard content is not populated with Planned Cost and Actual Cost
Hi
We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
Has anybody got this data in the Dashboard?
Kindly suggest the solution
with regards,
K Rama Krishna
9394712743Hi Rama,
It is difficult to say, where the problem is.
but typically, the causes of the problem are
customizing is set incorrectly or the evaluation is not carried out.
You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
Hope, it helps.
Kind regards,
Zhenbo -
Actual Costs , Planned Costs and Variance
Hi,
I know that there is a standard function module that gives the actual costs , tha target costs and variance, K_KKB_KKBCS_ORDER_REPORT. But is there any Funcion Module for calculating the Actual and planned costs and variance? or could the same FM be used for the purpose?OK
-
Data for Actual/ Plan Cost and Budget
Hi All,
Can you please adviseme which content i need to activate to get the Actaul, Plan cost and the Budget Data in SAP BW.
Do i need to exploer CCA cubes or Fund managment Cubes.. Please let me know... I need to know the Tables in R/3 Side for budget data to make sure that in R/3 we have budget data..
Please let me know.
Thank you
SAPHi there,
For those check in here:
[http://help.sap.com/saphelp_bw33/helpdata/en/d3/561be24e8c11d596f30000e835339d/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/60/0f07d3532c864aab7ec5f113146da2/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/26/d0cccc8d98c344925915ec81d5a421/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/43/de43fcf6e2154bbbbcecbc63cdf287/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/23/d5cf85683c3348b2189199e49a35cf/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/ad/be383fd98d1201e10000000a114084/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/1a/8c42588afe11d496d80000e835339d/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/d3/29ae399c1a6651e10000000a114084/frameset.htm]
Hope this helps.
Diogo. -
Target cost and actual cost not picking in production order
Hello,
The target cost and actual cost is not updating in production order when I display it in CO03 in cost analysis.
Even though we have maintained planned price in KP26.
Please suggest how it can be populated.
Best Regards,
TapanHi Tapan
For Target cost
1. Your std cost must be released before Goods Receipt
2. There must be goods receipt posted on the prod order
3. You must calculate variances in KKS1/2
For Actual Cost
1. Post Goods receipt and Goods issues
2. See if any mat movements are pending in COGI
3. Ensure that operation is confirmed in PP and no entry is lying in COFC
Regards
Ajay M -
Estimated Cost and Actual Cost
Hi Friends,
Can someone tell me, which MM tables(logically database) has these fields stored?? Estimated cost and Actual cost??
Note : Where and How can I find the logical data base??
Thanks alot in advance,Yes thank so much for your quick help.
I see here we can get 1- Plan cots , 4 Actual cost, But in PMCO, how can we get the estimated cost, I see that WRTTP = 1 also contain the value for estimated cost but not plan cost . Please help me.
Thanks -
I need just to know the difference between plan SKF and Actual SKF in business example and when I use one of them.
thanksHi Salaam,
Statistical Key Figure (SKF) is a base to allocate the cost between cost centers. Usually, common cost centers cost should allocate to respective department cost centers on monthly basis.
Some of SKFs are: Calculating floor rent on SFT, Telephone charges on No. of units, and employees head count is with "Each" in SAP.
Apart from Ajay's reply, you can consider the Canteen exp in an organization. Assume Admin, Fin and Mfg departments are getting food services from Canteen. Here, total monthly cost of Canteen exp should be allocated to respective departments. Here, we use SKF as total head count of each department and distribute the cost.
Planned SKF is what you planned on the beginning of a period. (Assume head count was planned as 30 in the month beginning)
Actual SKF is what exactly you consumed over the period. (Actual employees provided canteen services during the month is 25)
BR, Srinivas Salpala -
Hi All,
When is the target cost and actual cost gets populated and from where does the data comes from liek labour,machine,overhead cost comes?
Thanks in advanceDear Friend,
speaking from controlling point of view, target and actual costs will be flown from "costing variant planned" and "costing variant actual" respectively.In above mentioned varinats, whats the process has to be followed to calculate material costs,activty costs,overhead costs etc will be defined. These variants will be assigned in order type dependent parameters OPL8.
Target Costs - In standard cost estimate(ck11n),target cost will be calculated in the following way
-material cost from material master and BOM
- activity costs from routing( for this u need to plan the activity costs in KP26)
- other costs from the definitions of planned costing variant.
- after running the standard cost estimate,u need to mark n release(ck24).
Actual Costs - material costs frm goods issues (via goods mvmts thru MBIA,MB1B etc) against
production/process order.
- activity costs(as per the price u plannned in KP26)through operation confirmation in
COR6N/CO11N.
- any other costs like overheads,cost center issues etc as per the process defined
in 'actual costing variant'.
Hope this will clear your doubt.
Rams. -
PS: BAPI For Planned Progress and Actual Progress
Dear All,
Is there any BAPI available for Planned Progress and Actual Progress for PS Project.
Regards,
SohailHi,
Try using this report s_alr_87013532.
Also for planned and actual progress the table is rpsqt. Could not find any bapi for the progress
Regards
Hiren K.Chitalia -
Tcode for planned production and actual production
Hello,
I am working with a report I want to check the values with R/3 for Planned Production and Actual production. Does anybody have any idea how to check?
Thanks in advanceHey Suman,
i have the same problem, did you find a solution?
thanks -
Service Order Planned Costs and Cost Center Planned Line Items
Experts,
I am curious of Service Order Planned costs, and whether or not these planned costs are being posted to the Cost Center linked to the Service Order Operation's work center.
I am a but puzzled as I don't see any planned costs from any Service Order Operation in a cost center linked to the Operations work center, when reviewing "Cost Centers: Plan Line Items" report.
BR,
CenkThe planned costs were input in one of the Service Order operations as planned hours. There is a column for it in the operations list. The amount of hours have incurred a planned cost on the Service Order header.
I simply assumed that this cost would be credited to the Cost Center linked to the operation's Work Center. But that is obviously not the case. I am not familiar with the PLICC field and the functionality it provides.
Thanks! -
Raw material planned cost and qty in table MCKALKW
Hi,
Raw material planned cost and quantity in table MCKALKW is not equal to cost analysis in CO01 / CO02.
Could you please let me know how to get the planned cost and quantity for production order components for report development. i checked other tables like AFPO and AFKO and it is showing only for main material and not for its compoenHi,
You can check the cost of the individual components in Bill of materials of each material seperately. Hope this works for you.
Thanks and regards,
Murali krishna Maganti
Maybe you are looking for
-
How to make all rules active in Mail
Every time I sync my MacBook with my IMac through Mobile Me, the rule sync OK but it deactivate my rules. I have to click on every single one again to make them active. Is there a faster way to make all the rules active at once. TIA.
-
I believe that all the examples I've seen of nib/xib files have been connections to the corresponding controller or view files, or to the app delegate and the main window, Please correct me if I'm wrong, I might just be tired and missing an important
-
How do I restrict the number of emails that my iphone downloads on ios7
On ios6 I had my mail set up to only download 25 messages per box to my iphone. I have updated to ios7 today and this option has disappeared from the settings menu and now my phone has downloaded more then the 25 that I want it to. How can I specify
-
Database vendor error 556?
Hi, I use CR XI (sp4) at runtime to print report using an ODBC connection to text files, my project is working fine except on one computer where i have an error message (database vendor error 556) . I used the same method to install this PC (runtime
-
What can I safely remove?
Yogo 13" - 4gb 128 ss drive version. I don't feel comfortable in my knowledge to do a complete wipe and renistall... So what can I do to get some of this crap off here... The apps, the extra bloatware...?? Also the mcafee - can't I just use windows d