In-process inspection- operation wise result recording sequence

Hello Everyone,
I have just come across a requirement and would be grateful if someone can help me out in this regard.
1.     This is make to stock discrete manufacturing scenario.
2.     Inspection type 03 has been activated in material master.
3.     The setting in OPK4 are, error if no inspection results exist and error when operation sequence is not adhered to.
4.     As a result of which I cannot confirm the operation in CO11N unless result recording is done for corresponding operation.
The requirement,
1.     User should not be able to carry out result recording for operation 30 unless at least 1 quantity of operation 20 (preceding operation) is confirmed. Likewise it should behave for rest of the operations.
2.     Practically material is processed for operation 30 only if 20 is confirmed. Therefore operation 30 should be inspected after 20. System allows to input result recording for all the operations irrespective its confirmations.
Is there any standard solution for this or should I go for any exit?
Thank you,
Anand Rao

Hi Sujit,
Thanks for so prompt response.
I am using inspection point 100. Still it is not restricting. The operation confirmation is done through CO11N and not feasible for users to perform it through QM module.
The logic is, if I try to carry out result recording for operation 30 , system should firstly check whether any confirmation number exists or (at least 1 quantity is confirmed)for previous operation i.e. 20. If not it must stop doing RR for 30 operation.
Whether exits QEEM0011 and QEEM0015 can restrict this, as by their description I think these work after entering RR. Here it is required before RR. Any guesses?
Thank you again for your kind reply.
Regards,
Anand
An addition,
Even though QEEM0011 works before valuation user is able to enter RR. The requirement is user should not enter the any RR irrespecive of valuation. If user enters RR and do not valuate it this exit may not work and eventually can allow to confirm OP30.
Edited by: Anand Rao on Aug 24, 2011 1:21 PM

Similar Messages

  • How to find the inspection Operation wise status ?

    Hi
    There are two operation in result recording
    two different persons are entering the result in different operation....
    there is no sequence in entering the results...
    any one can enter at any time....
    but user requirement ...is
    they want to know whether they entered the results or not without going into result recording screen...
    Suppose if results entered they want to know which operation is completed  (Because system status showing INSP , if any one operation is completed)
    Is there any work around...(Like User status........?)
    R Karthikeyan

    Hi,
    Do result recording  in transaction QE51N, here if you expand the  operation you can see Red,green or gray  indicators. Red indicates recorsing completed but some rejection, green indicates completed and accepted and gray indicates not valuated.
    Please check.
    Best Regards,
    Shekhar

  • Error in operation level result recording

    Hi,
    I need held; result recording of inspection type =03 (operation level Quality inspection)
    A product manufacture via three operations (10, 20, 30)
    All operation quality inspection active let operation no-10, all products reject and confirm as rework.
    Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)
    How to add the quantity after reworks for next operation quality inspection?
    Pl helps me finding the solution.

    Hi,
    As per your more clearence , As per Example  production order Quanity =1, passes 3 operation10,20,30
    Operation=10 require rework as per quality ,
    Operation =20 system raise the error message = Operation =10 rework .
    If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity
    ( 1 Rework + 1 Ok ) .
    Supose rework order create and confirm then next 20 & 30 operation how complete .
    Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level
    I hope under stand my problem
    Need help- please

  • Serial Number wise Result Recording

    Hi QM Gurus,
    My Client requirement is he wants inspect the goods serial number wise.
    Example: Product P0001 production entry 100nos with serial number like s001, s002, s003, s004, u2026u2026u2026u2026 s100.
    But same thing Quality people has to record the result serial number wise.
    How to map in SAP, Kindly help me.
    Thanks in Advance.
    Babusingh.S

    Hi,
    Results recording for units to be inspected (with serial number profile)
    When you record inspection results for a unit to be inspected, for which the maintenance of serial numbers is specified in the material master, you must use the predefined serial numbers.
    To record results for units to be inspected with a serial number requirement, the following conditions must be met:
    The material was assigned a serial number profile and the serializing procedure was defined for maintaining inspection lots.
    You have set the indicator for single unit inspection in the QM inspection setup of the material master.
    Sanjay

  • Requirement of displaying inspection method in result recording

    Dear All,
    My clients requirement is to have the inspection method code in the result recording screen. I have the option of inspection method short text in the result recording screen. But i want a code should appear so that user can see the same for his convinient reference.
    Regards,
    Anil

    Dear Anil,
    You can create attachment in word of whatever data you want to maintain for inspection method. you can also save drawings in this attachment. assign this attachment to inspection method .You can assign attachment by
    Service for Object=> Create=>Create Attachment
    Now this attachment u can view while doing result recording & parallaly u can record results. Hope this will help you.
    Regards
    Amit

  • Reset inspection plan after results recording

    Dear all,
    i had one problem to be cleared, if u can please solve it.
    My problem is i have assigned wrong inspection plan for one insp. lot, and i have recorded results and saved. My question is there any provision that i can reset the other inspection plan for that particular lot and record resullts again.

    Hi Vijay,
    Goto QA11/QA12 Change Udage Decision enter the inspection lot number and select Usage Decision -->Functions -->Cancel Lot.
    Then cancel the Material Document by which the Inspection lot was created.
    Then make the GR and new lot will be generated. Then assign the Inspection Plan, Results Recording.
    Thanks and regards
    Murugesan

  • In-process inspection in repetitive manufacturing

    Hi,
    My client handles assembling of electronic products.  product passes through different set of operations where in it proceeds to the next operation only when the prior operation is approved in terms of quality.
    We are trying to go with repetitve mfg but we are unable to understand in-process inspection operation wise.  Pls advise is this feasible or we only need to go with discrete mfg with production orders.
    Regards,
    Sravan Kumar V
    Edited by: SRAVAN KUMAR on Oct 6, 2008 6:45 AM

    Dear,
    1. Setting up inprocess inspection
    for inprocess REM you have to maintained inspection type 13 in material master. and select task list. for that you have to maintained inspection point in your rate routing for ex for partial lot quantity based.
    2. GR Inspection from production
    then you go for result recording for inspection point and do the reporting point backflushed through result recording of every inspection point.
    3. At what stage the QM lot is generated .
    for that you have to create inspection lot in t code MFPR for your production version and for that inspection lot you have do above work.
    Please refer this link also,
    http://help.sap.com/saphelp_46c/helpdata/en/8a/a5aadd4adc11d189740000e8322d00/frameset.htm
    Regards,
    R.Brahmankar

  • Inprocess Inspection & result recording

    Hi all,
    We are implementing QM.
    The requirement of client is to carry out inprocess inspection(preferable without inspection plan) including result recording & defect recording & that to with quiet ease.
    Help me with the basic settings.
    Also to have the relevant report to analyse the inspection activities.
    We are using developed T code for operation confirmation, in the back end it is co11n only. So also elaborate the consequences of the same if any.
    Mangesh

    Ramanuj/ Murali,
    Thanks for your reply.
    Let me explain the process in details.
    We are having around 10 operations.
    We need to carry out inprocess inspection for 8 operation starting from 3rd operation.
    The inspection to be carried out is like length- 5 cms, shape- ok or not ok, if not ok then what is the defect, assay- 90%, if below 90% then defective like this.
    I have assigned inspection type 03 in QM view in the material master.
    Inspection lot is also getting created.
    I am stuck up at result recording & defect recording.
    So kindly guide me how to map this in details.
    Efforts would be appreciated.
    SmanS

  • Result Recording for inprocess lot

    Hello SAP gurus.
    For in process inspection lot i have 3 operation for testing my requirment is if i goning for result recording for second operation without result recording for first operation system should restrict me. we are using 100 inspection point for inprocess inspection please suggest how can we do this?
    Regards.

    Dear,
    Goto OPK4 -Select order type /Plant - Select 'Generally valid setting' for 'Operation sequence-Select 'Error when operation sequnce is not adhered  and also QM Error message if no inspection result exists.
    Or you can use the exit CONFPP05 PP order conf.: Customer specific enhancements when saving .
    Regards,
    R.Brahmankar

  • 03 In-process inspection

    Hi, i have  assigned 03 inspection type in material master. created and released prod order with that material in which we have 3 operations with control key qm04. confirmation will be done for operation 10. results recording will be done for peration 10. next confirmation will be done for opration 20, results recoring will be done for operation 20 and so on. at last operation, after results recording and ud will be done. is it the correct procedure with 03 inspection. or do we need to do ud after completion of each opertion after rrecording? please advise.

    Dear Raju
    You are correct. Please find my inputs
    1) IN 03 inspection you can do result recording and confirmation together.
    2) UD has to be given once all the confirmation is over. UD is for the lot so operation wise UD anway is not possible
    Regards
    Gajesh

  • Reverse the result recording in QM

    What is the process of cancel the result recording in stage of INSP RREC SPQR lot statuse in SAP QM.

    Hi,
    Just go to QE12..Result Recording changes for the inspection point. Enter the inspection lot, operation number and the sample number.
    The next screen will show the results. Click on the option  "Put to Process" The status will change from 5 "Processing completed" to 2 "Inprocess". Then remove the result for that characteristic and save it. Automatically your result recording will be reversed.
    Please ask me if you need any other details.
    Regards,
    Srinivas.D

  • Problem in Result Recording

    Dear Guru,
    During the production process I am having parallel operations. & All the operation having result recording process. So, I want to make the result recording for different operation simultaneously. So is it possible to make inspection for one production order?  Is there any provision for creating lot for different operation?
    Guide me how to do the result recording for the same lot.
    Srinivasan

    Hello Guru,
    I too agree with the previous answer.You need to do the result recording for each operations in samples .Since every production order create one inspection lot at a time result recording need to be done for every lot ,by selecting operations and samples.You could check the batch record afterwards for recorded results.
    Regards
    George

  • Usage decision vs result recording.

    Hi All Guru,
    I am new in QM , was MM & PP support. I am confused here about the usage decision vs result recording.
    I do understand in QM there's inspection lot , in order to release the inspection lot , i should released the UD.
    So what's the different between this both ?
    Can i have inspection lot without result recording ?
    Or can i have inspection lot without UD ?
    Please help to clarify my confuse.
    Thank you

    Hi Crag ,
    Thanks for understand because i am totally new in QM.
    I won't use QM for Notification here. I will use QM for stock transfer & QM in Delivery before PGI.
    As i know the basic requirement of QM 
    Setup the Master Data (QM View & all QM relavant data) ---> Type of inspection (which will determine which type of inspection to carry out ) -----> Inspection Lot Configuration --->Configuration for UD ----> Configuration for COA.
    Master data that which required
    Material master QM view,
    Master inspection characteristics,
    Task lists or inspection plans
    Code, Code groups and Selected sets.
    Quality info-record
    My Question :
    By having the above setup and configuration , without result recording can i have the COA to print out for either Post Process Inspection (Final FG) or Inspection at Delivery ?
    With the Master Data which i mention as above , is it sufficient for me to activate
    Post Process Inspection (Final FG - QM PP)
    QM Inspection at Delivery (QM /SD)
    QM stock transfer with inspection type 08.
    Hope to hear from you.
    Thank you

  • Preventing UD without results recording

    HI,
    We are able to do force closing of the inspection lots without results recording by registering the UD directly. How to prevent this? i.e. we dont want to register UD for lots without result recording for all the characterisitics. With User status we cannot achieve this because if we register results for some characteristics also the system status will be updated.
    Regards,
    Ravi Kumar C.

    hi
    yes as Mr.Shyamal mentioned, you can get through User status and in MIC slect the Required Characteristic radio button on control indicators,
    If you set this indicator, the inspection characteristic must be inspected.
    This means that you can only make a usage decision for the inspection lot after you have confirmed inspection results for this inspection characteristic.
    -pl check
    -ashok

  • Result Recording for In Process Inspection

    At the time of taking Usage Decision for In Process Inspection, system gives warning message if Results have not been recorded. Can this Warning message be changed to Error message so that user could not able to take UD without recording the results.
    Thanks in advance
    Srini

    Dear Srini
    1)Use status profile for restricting the user to do UD without doing RR. use this link for doing it
    Link: [https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20fbc091-ea3a-2b10-f0a3-877ffbf36436]
    2) you can use this auth object for doing the same restriction - Q_INSP_FIN
    Link: [Re: Preventing UD without results recording]
    Regards
    Gajesh