In which table production order planned cost and actual cost i can see?

Dear PP Guru,s,
from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
Regards,
sree

Dear,
Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
production order shows the planned cost based on the quantity structure.
Please refer my reply in this thread for details,
Re: Actual Halb Material Cost
Regards,
R.Brahmankar

Similar Messages

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • Target cost and actual cost not picking in production order

    Hello,
    The target cost and actual cost is not updating in production order when I display it in CO03 in cost analysis.
    Even though we have maintained planned price in KP26.
    Please suggest how it can be populated.
    Best Regards,
    Tapan

    Hi Tapan
    For Target cost
    1. Your std cost must be released before Goods Receipt
    2. There must be goods receipt posted on the prod order
    3. You must calculate variances in KKS1/2
    For Actual Cost
    1. Post Goods receipt and Goods issues
    2. See if any mat movements are pending in COGI
    3. Ensure that operation is confirmed in PP and no entry is lying in COFC
    Regards
    Ajay M

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • Dashboard content is not populated with Planned Cost and Actual Cost

    Hi
    We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
    Has anybody got this data in the Dashboard?
    Kindly suggest the solution
    with regards,
    K Rama Krishna
    9394712743

    Hi Rama,
    It is difficult to say, where the problem is.
    but typically, the causes of the problem are
    customizing is  set incorrectly or the evaluation is not carried out.
    You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
    Hope, it helps.
    Kind regards,
    Zhenbo

  • Estimated Cost and Actual Cost

    Hi Friends,
               Can someone tell me, which MM tables(logically database) has these fields stored?? Estimated cost and Actual cost??
    Note : Where and How can I find the logical data base??
    Thanks alot in advance,

    Yes thank so much for your quick help.
    I see here we can get 1- Plan cots , 4 Actual cost, But in PMCO, how can we get the estimated cost, I see that WRTTP = 1 also contain the value for estimated cost but not plan cost . Please help me.
    Thanks

  • Target Cost and Actual Cost

    Hi All,
    When is the target cost and actual cost gets populated and from where does the data comes from liek labour,machine,overhead cost comes?
    Thanks in advance

    Dear Friend,
    speaking from controlling point of view, target and actual costs will be flown from "costing variant planned" and "costing variant actual" respectively.In above mentioned varinats, whats the process has to be followed to calculate  material costs,activty costs,overhead costs etc will be defined. These variants will be assigned in order type dependent parameters OPL8.
    Target Costs - In standard cost estimate(ck11n),target cost will be calculated  in the following way
                              -material cost from material master and BOM
                              - activity costs from routing( for this u need to plan the activity costs in KP26)
                              - other costs from the definitions of planned costing variant.
                       - after running the standard cost estimate,u need to mark n release(ck24).
    Actual Costs - material costs frm goods issues (via goods mvmts thru MBIA,MB1B etc) against
                          production/process order.
                              - activity costs(as per the price u plannned in KP26)through  operation confirmation in
                                COR6N/CO11N.
                              - any other costs like overheads,cost center issues etc as per the process defined
                                in 'actual costing variant'.
    Hope this will clear your doubt.
    Rams.

  • Huge Variance between Target cost and Actual Cost

    Hi,
    In Product Costing,I am getting Huge variance between Target cost and Actual Cost.It is showing the Target Cost as ZERO.Why i am getting this target cost as Zero? what could be the reason? Kindly help me in fix this issue.
    Thanks
    Supriya

    Dear,
    First do the GR final DEV for Production order
    You need to do the variance calculation in KKS2, then when you save the variance, the target cost is calculated.
    Target cost appear after GR.  And you will get the Variance also right.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Std Costing and Actual costing at process Order

    Hello Friends,
    Followings are the client requirements, Please give me your ideas :-
    1 . Costing variant is same for all three - costing run, process order (plan and actual), means there is no prices variance on process order level. ( material at std price, Activity plan price, overhead fix%)
    2. Alongwith this above client also need to capture actual result (material at MAP, activity at monthly actual price, overhead fix %)
      In this case there is price and  usage variance can see.
    Now as I think that both scenarios are not possible on process order level.  According to me we can do by a customize actual costing cockpit.
    Need your openion that do we have any option thru standard funcations of sap to get this requirement.  If you need any other explanation , please do let me know.
    Thanks
    Ravi

    Thanks friends. I have done.

  • Variance key for calculating variance between planned price and actual cost

    Hello CO Experts,
    I am not following standard cost estimate. I am using price control V for FG. Now I did all the process:
    1. Process Order creation
    2. Process Order confirmation
    3. Template Execution
    4. Process Order revaluation
    5. Process Order - TECO.
    Now when I am running KKS2 (Variance), system is giving following error:
    Only remaining var. in version 0 - no target costs for 000001000047
    It means system is searching target cost in process order. However, since I didn't executed standard cost, system will populate target cost. Hence my requirement is that the system should calculate variance with respect to planned cost.
    Also I have assigned variance key to target version  1. In that assignment, I have selected "planned / preliminary cost"  in target cost section.
    When I am running KKS2 (variance analysis), system is calculating for both versions. Because of this, it is giving error. There is no input parameter, where I can give specific version.
    Please help

    Hi Deepak,
    For Finished Goods materials  if you assigned Price control  V (Moving Average) it is irrelevant  to run the Standard Cost Estimation.
    My earlier client we don't have variance because of the Moving Average Price for Finished Goods.
    Please check, It is really required Variance??  If it is required check whether variance key is automatically assigned to Process order or not. (Control Tab)
    Ravi Polampalli

  • PLANNED AND ACTUAL COST IN A PROCESS ORDER

    From where the planned cost of material and activity types in cost itemizationafter creation flow ?From where the actual cost of a material and activity types in  cost analysis of process order after confirmation flow?

    You may be knowing you give Costing Variants ( Both actual as well as Planned ) in Order type. These Costing variants contains Valuation variants which says which costs are to be taken while creation ( for Planned Cost ) and Actual cost ( while confirming and Moving Goods) to be calculate. These Variants decides mode of Cost Flows.
    Now, Data in Planned costs are Standard Cost figures or Current prices for material or Planned Prices of Activities.
    As far as Actual costs are considered it may be the price for the consumed quantity @ the moving average price of the day or activity price for the qty. consumed which include up planned consumption too.....
    Reward if you find useful

  • Production Order wise List for  Target cost v/s Actual cost

    Dear Sir,
    We have make to order scenario . We want to have a list giving Production Order wise "Target Cost" and "Actual Cost" . The purpose of list is to analyze the Variances Production Order wise .
    I request to kindly guide us , how can the above list be generated please .
    Regards
    B Mittal

    KKBC_HOE - With Defined Summarization Hierarchy
    S_ALR_87013104 - Sales Order Selection
    KKAC - For Sales Order with Assigned Orders
    KVBI - Actual Costs
    KOB3 - Variances

  • Standard and actual costing run

    I am doing actual coting run ckmlcp every month end on last of the month. stadard costing run I am doing on start of the month on 1st day of the month before actual transactions taking place.
    Here the problem is I already did the stadard costing and actual costing runfor april, now i want to do stadard costing today midnight 1AM for june and I want to do actual costing tomarrow evening 6PM for may.
    April stadard price is Rs150 and current stadard price is Rs 160 beacause of 1st june costing run.  If I will do the costing for May month now means  (1st)tomarrow evening which stadard price it will pick in ckmlcp and varience calculated.

    as cost estimate is run for the material in plant u can not  get cogs at  depot  level.
    Edited by: kumaraguru v on Jan 17, 2008 12:24 PM
    Edited by: kumaraguru v on Jan 17, 2008 12:25 PM

  • Table for Production order planned and Actual cost

    Hi Experts,
    Can anybody please tell me the name of table where Production order planned and Actual cost gets saved ?
    Thanks in advance.
    Regards,
    Bijay

    Table COEP
    don't forget the points

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost., CN41N | ABAP, SAP, benX AG, benXBrain,&…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

Maybe you are looking for

  • How can I see web classes done in adobe flash?

    I am trying to take an online course on my iPad 2 but Adobe Flash is required. Can anyone tell me how I can see my class on my iPad? The message says it's not available on my device so is there an app or some conversion I can do. Thanks for your time

  • Webdynpro ABAP application is not displaying in Portal

    Hi,   I have installed NW2004s and NW ABAP7.0 trail versions and configured Portal(SLD,Jco,.SSO).   I tried to created one WD ABAP iView with proper application name, etc.. when i go to preview of that iView its opening in separate winow and gettting

  • Backup iTunes Library to DVD

    On Windows Vista trying to backup a 7.5 gb library to DVD, iTunes writes the first disk, asks for the 2nd, says it is writing song such-and-such and just freezes. Can anyone help?

  • Deleting main EAN (MEAN-HPEAN = 'X') in retail material master data

    Hello experts, I have a customer (IS Retail) that realized, after data migration from legacy system, that many EAN including the main ones were obsolete or wrong. They asked me to clean all the EANs for a set of items, before deciding the new ones to

  • Need larger font in Mail message list....

    Hi-I am using a MacBook Pro running ML. I have 3 columns: my mailboxes on the left, in the middle is the list of messages and on the right is the preview of the messages. I would to increase the font of the middle one. Also like to increase the icons