Inconsistent Dev System: Infosource assigned to incorrect Source System

Hello all
Our Development box contains inconsistent assignments of infosources to source system.
When I compare the dev, quality and production boxes I find:
> Quality and Prod are consistent and all infosource systems are assigned to correct source systems - all loads execute as expected.
> However I find ips defined in the process chains in Quality and Production under incorrect source systems in the Development box.
> Also, the inconsistencies are varied for ex: SALESORG_ATTR is assigned to source system Y, while SALESORG_TEXT is assigned to source system X, while 0CUSTOMER_ATTR is assigned to source system Z ( where Z is the correct source system).
I have not been able to figure what lead to this inconsistency except that I am aware that there were plugins installed and some refreshes done followed up by BDLS.
I did try having BASIS execute BDLS to convert all logical systems X to Z ( but there were errors in the log stating that destination Z already exists - which is correct since for ex 0CUSTOMER_ATTR is assigned correctly to source system Z)
I was considering the following to rectify this situation:
1> Make the rectifications manually
1a> Identify all the infosources in all the process chains in quality/production
1b>Manually reassign all infsources/datasources to the right source system
1c>Check all the mapping rules (transfer rules) and ensure they are same as quality/production
1d> Activate the transfer rules
1e>Create infopackages
1f> Transport the ips to quality and reassign them to the process chains.
> This is a very labourious task and invovles high risk due to manual effort
2> Refresh from quality into dev
2a> Recreate the transport routes
2b> Resynchronize all the loads with the R3 dev box
> This would cause loss of version history and therefore not recommended by SAP
3> Rollback to a restore point
3a> We would need to find whether we maintain a restore point in the past before which the system were consistent.
3b> Reimport all the transports from the restore point till date
4> Rerun BDLS
4a> This might involve deleting all occurences of source system Z from the dev box
Please advise what would be the best approach / if theres a better way to address this issue.
Thankyou
Edited

Hi,
   Goto RSA1 in yy BWQ system.
In the Menu ---> Tools --->  Mapping of Source System Names ( Shift + F6)
Change the Target Source System as BWP server.
Now move the transport to BWQ. Your BWP will be assigned as source system.
Regards,
Balaji V

Similar Messages

  • Remocute ??? how to assign to a source system

    hi all,
    Created an SAP RemoteCube for InfoSource 0CO_OM_CCA_9 in the customer system by using the proposed characteristics and key figures from InfoSource 0CO_OM_CCA_9.
    then i tried to assign a relevant source system to this RemoteCube but i am not to able to assign my source system,bcos it is in disabled mode... ..
    Any way to assign my source sytem??
    Ganesh

    am following the below mentioned document to work on Reconciliation scenario.
    but am not able to assign my source system to my remotecube... you may find the actual screen shot in the 15th page of this document.
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/7a5ee147-0501-0010-0a9d-f7abcba36b14
    Ganesh

  • Source System of Dev System is not active QAS System.

    Hi
    I am trying to transport my SAP-BI flow from Dev System to the Quality System.
    but I am getting an error  "Source System of Dev system is not active in QualIty System.
    I have checked RFC Connection ,everything is fine.Please help.
    Thanks and Regards,
    Asim

    Have you checked the mapping of the source systems in the conversion table (RSLOGSYSMAP)?
    Usually, DEV source systems are not available in QA, so when you transport to DEV, the source system assignment has to be changed to a QA source system.
    For example, source system CRDCLNT100 (CRM DEV system) is connected to BWDCLNT100 (BW Dev)
    and CRTCLNT100 is connect to BWTCLNT100.
    Objects in BWD which are assigned to CRD, have to be re-assigned to the CRT source system when transporting them from BWD to BWT.
    The mapping table is maintained in RSA1, menu option tools > 'mapping of the source system names'.
    Jan.

  • Connecting IDES source system to BI Dev system

    Hi,
    Can we connect IDES R/3 system to BIW dev system???
    If yes, then is it the same procedure for RFC or something different???
    Thanks & Regards.

    Hi Ganesh,
    Yes, you can. Is like any other R/3 system.
    You just create the source system in BW and that's all.
    Hope this helps.
    Regards,
    Diego

  • Trans struc is not available for InfoSource ZF_GLER in the source system

    Hello Experts,
    I am facing an issue:
    While trying to load data in the data target(ODS) from the data source ZF_GLER i am getting an error message :
    Error message from the source system
    Diagnosis
    An error occurred in the source system.
    System Response
    Caller 09 contains an error message.
    Further analysis:
    The error occurred in Service API .
    Refer to the error message.
    Procedure
    How you remove the error depends on the error message.
    Note
    If the source system is a Client Workstation, then it is possible that the file that you wanted to load was being edited at the time of the data request. Make sure that the file is in the specified directory, that it is not being processed at the moment, and restart the request.
    The error message states that:       No transfer structure is available for InfoSource ZF_GLER in the source system
    For this I activated the data source in se38> RS_TRANSTRU_ACTIVATE_ALL.
    After this I tried to load data again I am getting the same error.
    Pls provide me the solution
    Thanks in Advance,
    Amit

    Hi,
    This is a Time stamp error
    You need to Replicate the respective Data source from the corresponding source system first then Activate the Transfer Rules and load again
    If you are in Production system you cannot activate transfer rules directly
    Go to SE38 --> run the Program RS_TRANSTRU_ACTIVATE_ALL --> mention the infosource and click execute. this will activate the transfer rules and try to reload.
    Regards,
    Gunjan.

  • DB Connect: Infosource assignment problem

    Dear Colleagues,
    You have been always helpful when needed and I have always given credit to your help. So coming to problem I am facing now...
    I am using BW 3.5 and MS SQL as a datasource.
    DB connect is successful and now for doing extraction test, I have created one table in MS SQL and trying to load that table in BW. Created the DB source system, tested successfully, created Infosource and assign datasource to Infosource. Data target is also created. Till then everything is find.
    Now while loading the data, in monitor it gives the error "<b>No mapping available for DataSource 6DB_XXXX. Assign an InfoSource. Error in Source System</b>". Whereas Datasource assignment to Infosource is created and activated successfully.
    I search the entire forum, but did not get any proper solution for this.
    Please do help.........
    Regards
    Pankaj

    Pankaj,
    If you deleted and then made again an assignment it wouldn't help.
    There is something wrong with your DS. You need to regenerate it again. For this you need to delete an IS-DS assignment first. After that you'll generate a DS again. Then make a replication.
    Don't know why you couldn't see a replication option. Do you see something like "Select tables"?
    And how did you create a DS?
    Best regards,
    Eugene
    Message was edited by: Eugene Khusainov

  • Assign Project to Source Client

    Hi All -
    I need to copy SAP standard roles from source client 000 of my development system to my QA system. My problem is, that a SolMan Project must be selected at the time I create the transport request in development. Currently I do not have any projects assigned to source client 000 of my dev system.
    Does anyone know how I can assign a project to the source?

    Which transaction are you using to create your messages?
    I cannot recreate your issue in NOTIF_CREATE.  I see all of the projects when I don't select a Solution. If I select a Solution first, I see that Solution's subset of projects.

  • Regarding Infosource Assignment

    Hi All,
    I need clarification regarding Infosource Assignment. I am doing Business Content Extraction. After we replicate the Datasource, I am selecting I am assigning infosource, by selecting the option "Assign Infosource" in the context menu of the Datasource. Here we will get three options:
    1. Content
    2. Application Proposal
    3. Others
    Can any one give me information regarding these three options.
    Regards
    Ravi Y

    hi,
    1. content means business content assignment, system will automatically determine the business content infosoruce, in business content installation/activation, you may use 'in dataflow before' with source system selected then system will install the datasource.
    2. application proposal, i think this means application component, system may propose based on the same application component name of datasource and infosource.
    3. others, we 'free choice' the infosource.
    in your case, the option should be 'content' since you use all business content.
    hope this helps.

  • BI Portal is not displaying Dashboard while Executing from BI Dev System

    HI Friends,
    I have created Dashboard based on Bex Query using SAP Netweaver Connection and published it to BI Dev System.
    it was running good but past 3-4 days it is not working.
    When I am executing it from BI Dev its not showing the output in BI portal.
    its only show initializing part of dashboard.
    please suggest ........
    Regards
    Sanjeev

    has your bex query changed that the dashboard is sourcing its data from? if so, and you have set the connection to "refresh before components load" it will sit at this state until it times out (error handeling is not great).  perhaps worth dropping a refresh button in an trying it without refresh on open - this will rule out (or in) a problem with the data connection.
    Cheers,
    Jeremy

  • Regarding Client Role change in DEV system.

    Hi All,
    I had some requirement from SapHR they want to do some Holiday calender changes in Sap Level.
    and we have only Test Role client in our Dev System. They want me to change the Client Role from Test to Customizing Client.
    Kindly let me know if Client Role is changes from TEST to CUSTOMIZING. is there any inconsistany in TMS.
    Thanks,
    Abdul

    Hi,
    Run BDLS to change the source system assn. Then check to see if all your transfer structures are active and also your source system is now the correct one. Easiest way is to goto RSA7 on the src system and see where the system is pointing to.
    Cheers,
    Kedar

  • DEV SYSTEM Functinal verifictaion

    Hi All,
    Sql server and sap patches are completed in dev system just now
    Asking me to do functional verification of the system  dev system
    what can we do functinal verification of the system mean's
    Thanks

    Hi,
    This info may be helpful.
    You need to test if the extractions are working fine, data is getting loaded into targets, post load activities like activation, rollup, compression etc are successfull etc.
    We test the PC chains also.
    We schedule / trigger the chains and monitor them. We ensure that all the process types are happening successfully.
    Also in cases where we use events/third party shceduling tools to trigger BW chains we check that out.
    Executing reports to check the definitions are correct.
    The volume of data will be lesser in Quality compared to Prod.
    Also activities like Change runs,Deletion , Selective deletion etc are done.
    Also make sure the V3 jobs in source, all other shceduled jobs are reshceduled if they were removed from scheduling.
    Refer
    Re: Quality System
    Re: bw developer_unit_integration_testing
    Integration Testing
    http://www.sap-img.com/general/role-of-sap-consultant-in-testing.htm
    integration testing
    SAP testing
    SAP Testing
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/e5d8d390-0201-0010-e284-e418e3f0e150
    Can any one explain about the SAP Testing process in Implementation Project
    Thanks,
    JituK

  • Master role-derive role concept and FICO role in dev system!!!

    Hi all,
    I have created a master role with t-codes
    AWUW
    BAPI
    BD10
    BD100
    BD101
    BD102
    BD103
    BD104
    BD105
    BD11
    BD12
    BD13
    BD14
    BD15
    also included object PLOG where maintained org data
    and created a derived role from that master role and generated from the master role.
    After that I wanted to change the org level but the system is not allowing me to change, although I selected the values from the F4 screen.
    Now I want to maintain seperate org value of each of the derived role...and when adjusted from the master role..these maitained value should not vanished.
    How should I proceed???
    I have another issue....I am now in Dev system....I need to create a role with FICO module with SPRO....
    Should I go ahead and cread a role and assign FICO block and assign SPRO...will that be sufficient??
    Thanks in Advance
    Regards,
    Souren

    Yes, It seems that you have broken the org level by directly making changes in the org level field inside pfcg.
    One way to correct this is to regenerate the role in expert mode by selecting the option 'Delete and recreate profile and authorizations' (in case you want to correct it for all the org level fields.).
    If you want only for PLOG, then delete this object and add again. Then go to organization level tab at the top and give the required value. Do this in the master role and generate and push the changes to derived role. Now, goto derived role and make the org level change the same way you did for parent role..
    For your second question, you will have to see what all auth objects are being checked by SPRO for a FICO module assosciate. You can create a test role with SPRO in it and then do authorization trace through ST01 to see what all objects are checked when they work.

  • How to map BW DEV system to new R3 system

    I need to map our BW DEV system to a new R3 system.  Currently, BW DEV is connected to the R3 Client 200 and we need to map to R3 Client 300.
    I created the Source system for Client 300 in BW and replicated the DataSources. 
    Is there a way to get all the transfer rules and infopackages that are setup for Client 200 moved to Client 300?
    Thanks.
    Ryan

    Hi Ryan,
    I've another suggestion. Try this:
    Why don't you simply change the client in the RFC-connection (SM59) of your source system in BW? You don't need the connection to client 200 anymore, don't you?
    Bye
    Frank

  • Problem when transporting form from DEV system to PRODUCTION system

    Hi Experts,
    We are developing forms in ABAP, for example there is a form developed in dev system and this form has JS coding in some UI elements events like initialize, on change and on exit; also has one script object defined as variable. this script object has some functions defined in order to do some common validations and field specific ones too.
    The form in DEV work fine, all the functions calling, all the validations and the events are working properly as expected. But there is a problem when we moved the changes done in development system into production system. Specifically the script object has the problem: even though the coding is the same in both systems, in production system we had an script error: "Body.CATALOGPARAMS has no properties", as if the Body.CATALOGPARAMS was never instanciated, or it is not defined...
    The code that produces this error is the following:
    var itemCount = 0;
    itemCount = Body.CATALOGPARAMS.DATA.instanceManager.count;
    CATALOGPARAMS is table defined as context table coming from an ABAP FM where is filled and passed into the form.
    In order to fix this problem I changed that part for the following
    var itemCount = 0;
    var catalogTable = null;
    catalogTable = xfa.resolveNode("Body.CATALOGPARAMS.DATA");
    itemCount = catalogTable.instanceManager.count;
    This still works as fine as the other in DEV system. But my question is: will I have the same problem when we transport the changes to production system, you have to know that a transport is not something that you can do every day, so I am taking precautions before the transport. Which of both coding is the best for doing this?
    Any observations, comments, questions in order to clarify some points are welcome, so please do it.
    In advance, thanks a lot.
    Mauricio.-
    Edited by: Mauricio Poblete on May 11, 2010 4:20 PM

    As always, you are the first one to reply... thanks for that!
    before everything, I activated the form, then I added this form to a new transport using se80 transaction: I navigated through the form objects and I added the form to a new transport by second click on the form -> other functions -> write transport entry. is this the correct way to assign a transport package with the entire form (including script objects, layouts, and all you told in the last reply)??
    Can you give me a guide on how-to add the specific parts to the same transport for forms?
    as always, thanks in advance.
    Mauricio.-

  • Activation BC first time in DEV system

    Hi,
    I was told to activate following BC in DEV system and it is CRM-BI implementation. I need to activate: 0CIC_MP01, 0CIC_MP02, 0CRM_CT_I, 0CRM_CT_O, 0CRM_C06, 0CRM_C07, 0CRM_TGRP, 0CRM_TGCT, 0CSAL_C01.
    My questions are:
    01.Exactly same above objects do I need to activate in QA and PROD also?
    02.In "Grouping" tab, if I select 'Only Necessary Objects', is it enough or do I need to select 'In Dataflow Before and Afterwards'.?
    03. What are general steps should I follow beginning of project, regarding Business Content Activation?
    Thank you.
    Regards,
    Md

    01.Exactly same above objects do I need to activate in QA and PROD also?
    You collect the objects in a transport and send it across systems - you do not activate in the PRD systems...
    02.In "Grouping" tab, if I select 'Only Necessary Objects', is it enough or do I need to select 'In Dataflow Before and Afterwards'.?
    If nothing is there currently - you would have to do Dataflow before and after...
    03. What are general steps should I follow beginning of project, regarding Business Content Activation?
    Make sure you can raise requests in the system before doing so. Also the source systems should be available and also the datasources required for the same should be replicated into the BI system.

Maybe you are looking for

  • How to find classtype and class for a material.

    Hi, How to find classtype and class for a material. which table contains this data. Thanks Kiran

  • How do i use youtube/safari without wifi

    I know people LOVE the wifi option, and i do too.... HOWEVER im running on a VERY slow internet connection at home, using "Basic" internet, which allows me to download at a max of 24kbps for torrents, and for when i download with firefox. So, it take

  • Error KB19454 when syncing

    When syncing the Curve 8300 to the ICal on a MacBook Pro running OS 10.5.8 i now get the following message. "The Calendar cannot be accessed for synchronization. For help resolving this issue, refer to KB19454 in the Blackberry Desktop Manager Knowle

  • Source works fine, EXE gives no memory error

    I have finished my program and am now trying to build the exe taht will run on the cliends workstation. The source has been well tested and does not throw any errors when running. Building the exe works fine but when running the exe I get an out of m

  • Re-use of XSL from existing middlware to PI 7.1

    Hi Friends, I am working on SAP BC to PI7.1 migration project, existing SAP BC envirement we using XSL Mappings ,we aretrying to reuse same XSL  in PI?? but my question is its posible to re-sue same XSL in PI?? thease XSL using XALAN Parsing, any cha