Individual / collective indicator in MRP 4

What is the use of this indicator and when to use individual and colloective option ?

Hi,
If you maintain Individual requirement seeting in MRP 4 view , always a PR or Planned order is generated aginst the WBS element based on Procurement type setting ( E or F). If a PR is genearated, and is converted to PO and when we do GR of the item , for a valuated stock , Stock and price will be in project stock not in actual cost. ( can see report in T-code GR55. Report Z6P2.)
If you maintain collective requirement seeting. Always a reservation is created against the network activity. Once the item is issued against the reservation , cost is debited from the activity and item is consumed. No stock.  Cost will booked to actual cost.
Can check the same by testing with same material ....
first have seeting as a Individual requirement. Genrate PR , convert to PO , do GR and check MMBE (stock report) and GR55 cost reprot.
next time same material , change setting to collective requirements, Reservation is created , DO GI against that resevation. Check MMBE ( No stock should be there ) , Check GR55 cost should be booked in actual cost.
No change in costs. Only change in the flow of qnty and cost.
Thanks
Saikishore Ganga
P.S : Kindly confirm as soon as you try this.

Similar Messages

  • Individual and Collective Indicator in MRP 4 View and BOM Expl.No

    Hi
    Please get back to me on the below queries
    a) I am using Planning Strategy u2013 40, do we need to maintain Individual or collective Indicator in MRP 4 view?? If I maintain what will be the impact and if I do not what will happen to the dependent requirements.
    b) What is BOM Explosion No?? please let me know this functionality and the configuration steps if any..
    Thanks

    Hi,
    u2022Individual requirements
    Requirement quantities of the dependent material are stated individually.
    u2022Collective requirements
    Requirement quantities of the dependent material are grouped together.
    BOM Explosion Number:
    1) Starting from the MRP menu, choose Master data -> BOM explosion number -> Edit.
    The system displays the initial screen for maintaining the BOM explosion number.
    2) Choose Execute.
    The screen for maintaining the BOM explosion numbers now appears.
    3) Choose New entries.
    A screen now appears where you can enter new BOM explosion numbers.
    Enter data as required.
    BOM explosion number - The BOM explosion number is the object for which the following data is maintained. It can be entered alphanumerically.
    Fixed key date - The fixed key date determines which bill of material is exploded.
    Plant - You can also specify a BOM explosion number for a specific plant. Enter the appropriate plant in this case.
    Material - You can specify a BOM explosion number for a specific material. Enter the appropriate material in this case.
    Status - You can set the BOM explosion number to active or inactive using the status field. Only active BOM explosion numbers are used in the planning run.
    4) Save your entries.
    Regards,
    Sulabh

  • Individual Collective indicator

    Hi
    Is there any report abt Individual collective indicator
    I need a report regarding  the requirements created on each date for the collective requirement of the material
    I have maintained collective indicator for the material
    Regards
    Anand Srinivasan

    Dear Anand,
    There's no standard report regarding  the individual/Collective Requirements.
    But still if you want the list of materials with 1 - Individual Requirements only or 2 - Collective Requirements
    only,you can get it from the table MARC in T code SE16.
    Regarding your second part of question i'm sure whether you are l;ooking for this,
    If you want the total Requirements for those materials,then go to T code MD73 - give the Requirements
    Plan as * and enter the plant and the date range and proceed.
    Regards
    Mangalraj.S

  • MRP4 View: Significance of Individual/Collective indicator

    Hi,
    Ref : MRP 4 view , Field : "Individual/Coll."
    Request to give the significance of the above field.
    I am not able to understand the help data available for the filed in SAP.
    If possible request to give example to elaborate the significance
    Regards
    Nitin

    Hi,
    This indicator is useful in case of sales order planning.
    If u enter 2, in collective/individual for component, then in component stock requirement list u can see there is no reference to sales order.
    That is commom stock will be consider by system.
    If u enter indicator 1 or no entry, in MTO after creation of sales order, for component sales order stock will be created. U can see the sales order in component stock requirement list. The common stock of component will not consider the common stock. Pr will be generated for the component/ For this situation u have to transfer common stock material to sales order stock.It depends of the requirement of company. Where to check common stock or sales order stock.
    Check the above & reward if found suitable.
    Regards,
    Suhas

  • What is the functionality of Bom explosion individual/collective  in MRP 4 View

    Hi Experts.Please give idea about what is the use of functionality of BOM explosion Individual/collective in MRP view 4.How this function will work in strategy 10 and 20.
    thanks in advance.

    Hi,
    This is a very generic question...If you explore in forum or net you will get lot of information...
    This is normally used in make to order strategies like 20, 50 etc...
    The individual/collective indicator in the material master record determines
    whether a component is procured for a special customer requirement in the
    individual segment.
    The indicator "1" for individual requirements means that the material is being
    specially manufactured or procured for a sales order. A special individual segment
    is created for each requirement. An individual requirement is only created if the
    higher-level material does not create a collective requirement.
    The indicator "2" for collective requirements means that the material is produced
    or procured for various requirements. You can find these requirements in the net
    requirements segment.
    The indicator "blank" means that the component is to be planned in the same way
    as the higher-level assembly.
    In the above example, two individual segments are created for the shaft for sales
    orders A and B.
    Thanks
    Kumar

  • Material Master MRP4 Individual / Collective Requirement

    Hi All,
    I would like to ask in case I want to use the Individual / Collective Requirement functionality in Material Master MRP4 view, is it a MUST to set the Strategy Group in MRP3 view to 20 : Make-To-Order Production? Because I find if I dun set this field, nothing happens after I execute MD01 for the MRP Run.
    Another query is in case the Stock Requirement is on two different dates, can I still group them together into one Plan Order or one Purchase Requisition using the selection - 2. Collective Requirement selection?
    Many Thanks.

    Hi,
    I would like to ask in case I want to use the Individual / Collective Requirement functionality in Material Master MRP4 view, is it a MUST to set the Strategy Group in MRP3 view to 20 : Make-To-Order Production? Because I find if I dun set this field, nothing happens after I execute MD01 for the MRP Run.
    Yes Individual / Collective indicator only works for MTO strategies.
    Another query is in case the Stock Requirement is on two different dates, can I still group them together into one Plan Order or one Purchase Requisition using the selection - 2. Collective Requirement selection?
    You can but if the dates are different you have to use Periodic Lot Size.like PK.and all requirements within one period will be grouped together and they will be planned together.
    Check and Revert,
    Santosh Sarda

  • What is exactly difference btw individual collective call blank and 1?

    Hello all
    Could you please to help me get ride of that what is exactly difference btw blank and 1 in MTO scenario?
    it is better if you guy can show me a example.
    Thanks

    Hi,
    In case of any requirement through sales order, it will be the special stock categoery E and material should have Individual and Collective Indicator as 1 in MRP4 view .It depends on what item category you are going to use in the sales order .
    In MTS strategy, You can't achieve based on each requirement But you can get the plan order( system will combine all the requirement ) generated.
    Example
    If you have Asembly Material A, and components X,Y & Z for A.
    For MTO
    MRP generates the Planned Order for the Assembly and components with respect to the sale order requriement.
    Fot MTS
    MRP generates the Planned Order for the assembly and components based on the stock requirement.
    Regards,
    Sundhu

  • Individual/collective req ind

    Dear experts,
    I'm using MTO. I have multilevel bom structure. I have faced a problem.
    For example I have a material in level2 followed individually according to customer order. I want the level3 materials to be managed collectively. I'm setting all the materials collective indicator in 3rd level. But sometimes I forget to create the MRP view of the 3rd level material. Then the system plans the requirements of 3rd level according to 2nd level and as the 2nd level followed individully this 3rd level  material is also planned individually.
    My question comes: Is there any way to define the system plan the materials always collectively if mrp view does not exist or if I don not set any indicator.

    Hi,
    Yes you can set the collective/Indual indicator with out MRP view also..
    In the BOM you can set..
    In component details there got a Explosion type for this explosion type in the background setting set as collective requirement and assign the same in the BOM items.
    hope clear..
    Revert me if any issue
    Regards,
    Ravi

  • Individual/Collective in BOM With Phantoms

    Hello All
    Iu2019m working with variant configuration using strategy group 65.
    My BOM has several levels and the first level is always a phantom.
    When exploding the BOM MRP create individual requirements for each component.
    Because the components are used in other finish goods with different strategy I don´t want to set in the mater data the individual collective flag to 2. Instead I create e new explosion type in the BOM to create collective requirements.
    My problem is that MRP bypasses this explosion type from the BOM when the component is phantom which forces me to enter it at the level of the no phantom component.
    Is possible by any means force MRP to only create Collective Requirements for the Components of a MTO ?
    Thereu2019s any chance to force SAP to Look to the explosion type in the phantoms and create only collective requirements?
    Thanks for your comments
    Pedro Coelho

    Dear
    I do not think so it is possible  in Standrad MTO process .
    In MTO process , you can not club all the Depedent  Requirement ( Phantom BOM -componenets ) in to one PR  utlising MRP4 individual and Collective Indicator .
    Basically indiviaul /collective indicator MRP4 as 2 then  PRs or planned orders will be generated during the MRP run for dependent requirements with account assigned to respective WBSE or Sale order
    Where as at header level it will work  like this  : Individual and collective indicator in mrp4 view
    Just check this
    Regards
    JH

  • Individual/Collective Requirements MRP4 View

    I have a situation where my top level material (FERT) is a MTS item (reorder point planning).  In the BOM is an intermediate (HALB).  Due to the nature of my process I must have a 1:1 relation ship of the HALB to the FERT.  However: as many have pointed out, where I have multiple production orders for the FERT, the MRP behavior is to combine multiple order reservations for the HALB into one planned order, regardless of the individual/collective requirement setting.  There must be a way to get a planned order for each order reservation in this MTS situation.  I know that I am not the only one who has this requirement.  Any advice/expertise would be greatly appreciated.  Thanks.

    Mgf,
    I believe expert Sundaresan has answered your question - for Baseline SAP.
    In addition to Baseline, though, SAP offers several addons that are industry specific, and some of them appear to me to be tailored to industries in which Milliken is a participant.
    Check out the standard industry addons in
    http://help.sap.com/content/documentation/industry/index.htm
    You also might want to consider hiring a consulting company to explore possible SAP solutions for you.
    Best Regards,
    DB49

  • List display based on PR collective indicator.

    Hi all
    I am able to use the function "PR collective indicator" in project definition for grouping the items in respective PR.
    I have defined the grouping like MECH and ELEC.
    Is there any display of PR's to have selection by this value MECH or ELEC for the respective project?
    Can we have list display like ME5J to have selection based on this grouping?
    warm regards
    ramSiva

    hello Zaafran Ahmed ,
    I populate the list items as in your example..I populate the list items as follows,
    My Code is :
    /* WHEN-NEW-FORM-INSTANCE Trigger*/
    DECLARE
    rg_countries RECORDGROUP;
    vTemp NUMBER;
    BEGIN
    rg_countries:=CREATE_GROUP_FROM_QUERY('rg_countries',
    'SELECT country_name NAME, COUNTRY_ID VALUE FROM COUNTRY ORDER BY 2');
    vTemp:=POPULATE_GROUP(rg_countries);
    POPULATE_LIST('BLOCK3.COUNTRIES', rg_countries);
    END;
    In the WHEN-LIST-CHANGED Trigger of the COUNTRIES list item i write as follows :
    /* WHEN-LIST-CHANGED Trigger */
    DECLARE
    rg_states RECORDGROUP;
    vTemp NUMBER;
    BEGIN
    rg_states:=CREATE_GROUP_FROM_QUERY('rg_states',
    'SELECT STATE_NAME NAME, COUNTRY_ID VALUE FROM STATE WHERE COUNTRY_ID = '||:BLOCK3.COUNTRIES||'ORDER BY 2');
    vTemp:=POPULATE_GROUP(rg_states);
    POPULATE_LIST('BLOCK3.STATES', rg_states);
    DELETE_GROUP(rg_states);
    END;
    My problem is now, When i select a country in "COUNTRIES" list item [ For example I select India], The "STATES" list item shows all the states belongs to india..But i cant select states from that..Only the first value in "STATES" list item
    can be selected..Other values can't be select by me..What can i do..
    My table structures:
    SQL> desc country
    Name Null? Type
    COUNTRY_ID NOT NULL VARCHAR2(30) [This is primary key]
    COUNTRY_NAME VARCHAR2(30)
    SQL> desc state
    Name Null? Type
    COUNTRY_ID VARCHAR2(30) [This is foreign key ]
    STATE_NAME VARCHAR2(30)
    My example datas:
    SQL> select*from country
    2 /
    COUNTRY_ID COUNTRY_NAME
    002 usa
    001 india
    select*from state
    COUNTRY_ID STATE_NAME
    001 tn
    001 kerala
    001 bangalore
    002 ca
    002 NY
    002 la

  • View Reports for individual Collections

    Hello,
    Is there a way to view Reports for individual Collections?  When I review my Usage Reports or look at Reports within the PSM I only get a break down of total user actions per day for the whole site.  I don't see a way to view data for just a single Collection.  It would be extremely helpful to me and my faculty if we could see reports or stats for specific Collections.  For example, if I could see total subscriptions and downloads for HIST1010.  It'd be even better if we could view totals for whole months rather than each day of the month but at this point any data about a whole individual Collection would be great.  Any help in viewing the data in this way is really appreciated.
    Thanks!
    Nikki
    Multimedia Tech
    Roane State Community College

    Hi Syd,
    Thanks so much for your prompt reply.  I was able to use your directions to pull stats for the last few weeks for the faculty member who requested this info. 
    My dream (if Apple is reading) would be to view monthly stats and have that information attached to each course so faculty members could view and sort that information on their own.  This would be especially helpful because as our site continues to grow and I continue to encourage faculty to manage their own content, the ability to access the data on their Collections would provide great feedback on how their ocntent is being used.  Being able to see how frequently the content they're taken the time to make is being used could be empowering.
    Anyway, thanks again for assisting with how to access the data that is currently available.
    Best,
    Nikki

  • Significance and use of CVD indicator and MRP indicator in J1IEX

    Dear Frndz...
    Plz expln significance and use of CVD indicator and MRP indicator in J1IEX.
    Regards,
    Amit P Hiran
    njoy SAP..
    njoy Life...........

    hi
    >CVD TICk
    CVD indicator will be auto ticked when when u go for IMPORT PROCESS
    check folowing for import process
    import process customization
    >MRP TICk
    MRP tick is used for the first stage dealer scenario ,where at time of purchase u cant have excise values
    the bill will be including base price exciseothertax + delears commisiion
    E.g.:
    Material Price = 80/-
    Excise Duty = 14/- (BEDECessSECess)
    Margin = 6/-
    Total =100/-
    VAT @3% = 3/-
    Grand Total =103/-
    Step 1:
    Create PO with Base Price as 100/- by selecting tax code which is having VAT as 3% (Total PO value will be 103/-)
    Step 2:
    Post MIGO and Capture Excise Part - 1
    Click on More details icon in Excise tab (header), check MRP Indicator in miscellaneous tab, Enter Assessable value as 80 in Excise tab Item level and enter the excise values BED, ECess , SECess manually, check & save the document.
    Step 3;
    Post Excise Part 2 in J1IEX
    Step 4:
    Post MIRO by checking calculate tax, edit base value as 80/- enter the amount in header as proposed by the system (103/-), simulate & post the document.
    Note 1104456 - Use of MRP indicator for capturing excise duties from dealer

  • Individual/Collective Requirement indicator in MTS

    Hi Gurus,
    Can you please let me know what is the relevence of individual/Colelctive Requirement indicator from MRP4 view of material..
    for Finished product as well as its sub assembliees in case of make to Stock planing strategies.
    i know how it works in MTO and how depednent requirements can be grouped together or sepated based on this indicator.
    When i tested the same in case of MTS, i found for dfinished product as well as sub assemblies behaviour is always like collective irrespective of MRP4 indicator.
    any thougts lets me know.

    Dear Santhosh,
    MRP-4 as 1 : In individual planning, this indicator is used to display the dependent requirements of a component separately.
    MRP-4 as 2 : In collective requirements, this indicator is used to display the dependent requirements of a component grouped together.
    This Indicator is useful to control the planning of dependent requirements if the main product is being planned with strategy 20 ie; MTO Process.
    Ramagiri

  • Printing Indicator (Individual/Collective Slip) at Display MIGO GR document

    Hi, Good Morning...
    FYI , I 've been check Collective slip indicator when prepare GR document. Once after press CHECK  and POST button, system will generate document GR number. Then I just want to display the document again. When system prompt out, we discovered there is not in collective slip indicator status but it become individual slip. Any Other suggestions?

    The system is default to pick the individual slip. Are you getting the print from MB90. If yes, then you dont need to worry on this one. On some systems I have seen all 3 options, mapped as collective slip for convenience of users, so that whatever they choose, it doesnot effect the print. Only main thing here is to get the Print active check enabled. If not the print will not go to MB90.
    Usually I make the Print check button mandatory, so that material document is not saved without this check.
    Edited by: Afshad Irani on Apr 28, 2010 7:33 AM

Maybe you are looking for

  • Shared variable engine OPC delay

    Hello All, I've got a bit of a problem with the delay time of updates between a non NI OPC server and a shared variable engine OPC client. I am using the redion OPC software OPCWorx with a database of around 120 tags to monitor and log data from a sm

  • How to set application parameter in web dynpro abap?

    Hi experts,                 Is there any way we can set up our own application parameter (for ex. mode ) of our application. And based on that parameter we can visible/invisible certain elements of view .  so by having only one webdypro application c

  • Exception condition "NO_FIELDCATALOG_AVAILABLE" raised in an alv grid.

    Hi. I saw other threadhs  with this problem, and in each ones somebody explained how to use the fieldcatalog. In this case I wish to know why I can't use the structure name. The code is at the bottom. I'm working with a rel. 4.6c. I'm sure that when

  • What's up with the ipod touch photo quality

    what's up with the ipod touch photo quality

  • VS2013 Pro w/Up3 and Update for Windows (KB2506143)

    I'm try to test the http://www.visualstudio.com/explore/cordova-vs and when I select the Multi Device Hybrid App it says I must first install Update for Windows (KB2506143) for my Win7 64 box.  I've tried to install this update and it does nothing bu