Hi Experts,
I have a process chain that includes several infopackages. One of those infopackages is from a DS that currently is not bringing any data (no data in R3 for time), and when is exectuted in BW gets status yellow (not yet complete/warning) because it doens't bring any data.
When I run the process chain, the process gets "stuck" on this infosource, and it doesn't continue. The only way to make it continue is to mannualy force the passage from status yellow to status green.
Does anybody know what is the solution to keep this IP in the PC (they might statring to have data in R3 side in the future) and make it continue (maybe a way to automatically get the loading green)?
Many thanks
Joana

Hi,
I think due to no data availability in source system it is in yellow status,hence you can change the status to green when ZERO records
Defining the Request Status if there is no Data in the Source System
Under   Scheduler   Color of Traffic Light for Empty Request   you define how the system reacts if there is no data in the source system for the data request.
You can find more info.....
http://help.sap.com/saphelp_nw73/helpdata/en/4a/28bc5572e91cb8e10000000a42189b/content.htm
Regards,
Satya

Similar Messages

  • Infopackage returns 0 when triggered from process chain

    I have an Infopackage triggered by process chain (say PC A) which is further triggered by other meta-chains.
    So PC A, is triggered by PC B, and PC B is triggered by PC C.
    Daily it returns 0 records.
    However, if I run the process chain manually, that is PC A, the infopackage returns correct number of records.
    What may be the cause?
    Rusyinni

    Hi ,
    When you are executing through PC then it is running with the user id ALEREMOTE because of not having proper authorization it picking 0 records but when you run the same with your ID manually then you are getting the data for the same .
    You need to get in touch with the Basis team to check for the authorization for these 2 ID's .
    From my point you can use SU01 to get the information for all the profiles associated with the ID   and  then with RSECADMIN you can check for the Tcodes and related authorization activity associated with the ID.
    Please check and updated accordingly later .
    Thanks
    Kamal

  • UNCAUGHT_EXCEPTION with msg CX_RSR_X_MESSAG while scheduling Process chain

    Hi Gurus,
    We are facing a short dump while scheduling process chains, as follows:
    <BR><BR>
    Runtime Errors         UNCAUGHT_EXCEPTION
    Exception              CX_RSR_X_MESSAGE
    <BR><BR>
    Error analysis
        An exception occurred which is explained in detail below.
        The exception, which is assigned to class 'CX_RSR_X_MESSAGE', was not caught
         and
        therefore caused a runtime error.
        The reason for the exception is:
        No text available for this exception
    <BR>
    Information on where terminated
        Termination occurred in the ABAP program "SAPLRRMS" - in "RRMS_X_MESSAGE".
        The main program was "RSPC_MAINTAIN_SINGLE ".
        In the source code you have the termination point in line 82
        of the (Include) program "LRRMSU13".
    <BR>
    We tried to schedule it as a remote process chain from some other system it cancelled the job there with an ERROR_MESSAGE. We checked the RFC Connections at the source system side but it is working properly. We then tried to schedule the chain manually, we had this exception. Then we tried to have a look at previous logs of the process chain. It had this exception. We tried to reactivate the chain it was successful but when tried to schedule the chain same issue again. We tried to run the Meta chains under the same chain separately. They too gave us the same exception.
    Please help.
    Regards,
    Sourabh Deo

    S Simran wrote:
    Hi,
    >
    > Ours is a fresh installation..
    >
    > When i am loading for the first time till PSA it is successful..
    >
    > As HR data sources are 3.5 datasources, i am loading cube via infopackage..
    >
    > When i start the load to cube it is giving me dump with exception CX_RSR_X_MESSAG.
    >
    > i checked note  615389 which talks about "buffering of number range object BIM9999998".  the 0REQID is not buffered, but it does not throw any error msg in RSRV to correct the error..
    >
    > and one more note 1157796 which talks about patches with version BI 7.0.
    >
    > Now we are in BI 730 with heighest level 0005.
    >
    > Not sure how to solve this error
    >
    > Any ideas?
    What's your SP? Are you having any master data updates left unattended? Check the Master data objects, check the flows. Related SAP Notes : 914304 / Check 967202(SP10) and 998673(SP11), 1157796, 763203 and 615389
    Edited by: Arun Bala G on Feb 12, 2012 9:50 PM

  • Aggregate never completes in process chain

    Hi,
    I have AA cube which got 61183291 records, whenever I try to run the process chain - everything goes fine and it stops at aggregates... first I waited for 1 day still it didn't completed... then cancelled it and restart the process chain.... this time I waited for 4 days and it is still running...... not sure what is the probelm.... can anyone come acrossed the same problem?
    your help i highly appreciated....
    thanks
    Vijay

    Bhanu,
    in process overview I see
    time------ report -
    Cl.--user-----Action 
    334122    GP1HXOK8TX    100    ALEREMOTE  DB procedure
    table
    DB-PROC "/
    Dinesh,
    Might be your are correct. I will check with my basis on this.
    Thanks,
    Vijay
    Message was edited by: Vijay Kumar
    Message was edited by: Vijay Kumar
    Message was edited by: Vijay Kumar

  • Issue with ABAP program execution from process chains

    Hi All:
    We have a process chain with 3 steps, each of them executing the same program with three different variants. The program is ftp's the file from APO's dataexchange (mount) to another ftp server. The first variant transfers file A to a directory in the external ftp server (say /X) . The second and the third variants are supposed to transfer different files, B and C to the same directory.
    That is where the problem is. After the process chain is successful, I see two files B and C but the contents are same and that of C. So, if I switch the steps in the PC to bring in A then C and then B, I see files B and C with content of C. I tried C then A then B. I see the file names correct but now the contents are A, A then B.
    Have any of you come across this issue? Do you know that these is an existing problem? IF you have a solution, pl. let me know.
    Thanks
    Narayanan

    Narayanan,
    Instead of doing it in three steps - would it be possible for you to have one UNIX script or equivalent doing the above and calling the same from your process chain ...?
    We do a lot of FTPs but then our file names are standard and we have a UNIX script for the same executed using a system command through a process chain and it has been working without issues for the past 1 year ...
    Maybe I have not got your situation properly ... some more detail on the program details and what you are doing in more detail would help....  also SP levels please..

  • Process InfoPackage based on a condition in Process Chain

    Hi,
    I would like to include a Function Module in my Process Chain.Based on the output of the Function Module (example Flag - 'A','B','C') I would like to load data from Infopackage.
    Could you please suggest the best possible solution.
    Thanks,
    Nimai

    then you need a decision step...
    as you want to use a FM to get the outcome, you can't use the standard decision step as you can only use a formula...
    so you need to implement a new decision step...look on sdn for the how to paper 'Enhanced Decision Process Type for BW Process Chains'...
    this how to paper will lead you to create a process step of the type decision but you can use abap forms (take a look at it and it will become clear)...once you have done this, drag/drop the step in your chain. within the variant, you can define the result of the if, elseif, else...you can add as much elseif as you want (a lot in any case)...you need to create for every 'if' the form using the FM... back in the process chain you can link this step to all the infopackages, and indicate the result of the decision step leading to the infopackage execution...
    that's the nice way...
    the easy way :
    create for every infopackage a single process chain (you can easily copy them)...they should start after event EV_A, EV_B, and so on...every chain after another event...now create an abap program and call the function module...now depending on the outcome of your FM you can trigger one of the events and the corresponding chain will start, leading to the correct infopackage being loaded.
    look on abap forum on more info about event triggering, how to create event,...

  • Problems with BPC Export Transaction Data process chain

    Hi everybody,
    we are trying to implement the procedure "How to Export BPC Transaction Data using a custom process chain " for SAP BPC NW 7.0 and everything seems fine. However, when we execute it from Excel, the package apparently runs well (the message 'IMMEDIATE RUN: The package is running...' appears) but when we go to the watch the package status, the package does not appear in the list and there is not any file exported.
    When we go to watch the log of the process chain from NW, the Modify Dynamically step runs wrongly but there is no clue of what could be done to solve it. We have done it again from scratch but we always have the same error.
    Any idea out there?
    Thanks in advance. Kind regards,
    Albert

    Hi Rich,
    in the end we managed to export data. Our NW administrator created the custom process type wrongly - putting a blank space before ZBPCTXEXP - and now it has been corrected and everything works fine.
    Well we have managed to transport applications to one server to another one and to export/import the transactional data.
    Is there any doc that explains how to transport process chains from one server to another?
    In BPC Opps manual there is not too much information and we should transport quiet a lot of process chains related with Runlogic issues .
    Thanks a lot for your help.
    Kind regards,
    Albert Mas.

  • With out sm37 completion Whole process

    Dear
    in my Business process Once created sales order automatically Delivery , pgi , And Billing will be completed Then In sm37 We will release manually Process
    so here My requirement is once completes sales order My user no need to Go to sm37 
    But he wants billing creation Automatically
    Plz tell me how to achieve this 

    Dear ,,Thanks for replaying
    But We can use this program SDBILLDL program in SM36 Only For automatic billing Process
    When No Automatci deliveries and No PGIS
    is it possible to do when auotomatic delivery and automatic PGI ARE Available
    thanks a lot

  • How to handle hierarchies in process chain

    Hi All,
    I am designing the process chain for a master GL account number . It has attribute hierarchy and text.
    I am successfully able to create the process chain for the attribute and text . But when i add the infopackage for the hierachy I am confused as I have two hierachy infopackages as the client is using two hierachies for the GL accounts.
    How should i incorporate these two infopackages which are refereing to two different hierarchies of R3.
    I will appreciate your replies.
    Regards
    Rahul Bindroo

    Hi all,
    But when I try to put the infopackage with first hierarchy in the process chain I dont get the save hiearchy and attribute change run automatically while as for attributes i get the attribute change run automatically.
    If I have to add the load process 'Save hierachy ' i do the following steps:--
    Drag and drop save hiearchy--->if i use F4 no list appears/if i create the variant i get a screen with the object type field -
    What should I select there.......?>**
    Am I following right steps or I am missing something.
    Regards
    Rahul Bindroo

  • Infopackage red in process chain but green in monitor

    With our system (BW30B, patch14, W2K, Oracle 9.2.0.5) we are having some issues with some infopackages which are included in a process chain.
    In the process chain, the status is red with the following error messages: "Processing in Warehouse timed out; processing steps mising", "<DS:DE.RSCALLER>Caller  is still missing." but the data was loaded properly --> if I open the monitor status for that infopackage, the status is green (and I confirm that data was properly loaded).
    But, this is a problem as it screws up the process chain. I did not find a fix after seaching OSS notes, but the note #766712 seems close to our issue - I tried to apply it but it did not work. In the note, it's recommended to turn on a higher enqueue time --> could you please help me on how to do it? I checked everywhere and did not find the menu option to do it.
    Any help appreciated
    Thanks
    Ioan

    Thanks Roberto
    I do not think it is related to this setting (it's now set to 30000, which is 3H) - the data properly ended loading before.
    When I change the status manually in the monitor, it is reflected in the process chain - but this happens every night, so I have to turn them green manualy every morning ...
    The note is 766721 (and not 766712)
    Thanks in advance for any help
    Ioan

  • Issue with Delete Index in process chain

    Hi All,
    I have a situation with Delete Index in my process chain.
    Delete Index step, before loading data to cube, is taking around 2Hr to complete but some times it completes within 5 mins.
    Anyone faces such issue? If yes, how can I fix it?
    Thanks and Regards,
    Alok

    Hi,
    If Statistics are not maintained for the cube then also it might casue the high run time in index deletion.
    if its urgent then, can u try doing it manually form performance tab....
    or once process chain step is complete, create statistics for the cube. Next run should take less time
    Please try.
    Regards,
    Gaurav

  • Process chain with abap report

    Hi all,
    I have an abap report which is used to fill a table . This report is scheduled on daily basis .
    Now i want to do is , whenever this report completes my process chain should start in BI so that data in table can be filled in GDS .
    How to do that ???
    Please help.
    Regards
    Shweta

    Hi,
    You can do it in two ways.
    1) Include the ABAP program as the first process in your process chain. Once the program is completd the following processes will continue.
    2) Use "After Job" Scheduling options to schedule your process chain.
    Mention the job name of the program in the After job.  The process chain will get triggered once the job is completed.
    Regards,
    Balaji V

  • Skip steps in process chain if 0 records received from InfoPackage

    Hi Experts,
    In one business scenario, we need to change existing process chain such that if InfoPackage/DTP has brought 0 records process chain should skip rest steps or it should get failed.
    Do you have any ideas about this.
    Regards,

    Dear Ganesh,
    you can change the traffic light color for empty request in the infoPackage maintenance window. Top menu --> Scheduler --> Traffic light color for empty request.
    Using this option and connecting process chain nodes correctly, process chain execution will stop whenever the infoPackage gets 0 records.
    For a DTP, you can use ABAP code in the start routine of the corresponding transformation. You should check the contents of SOURCE_PACKAGE internal table and raise exception accordingly.
    I hope this information helps you.
    Best regards,
    Nacho

  • Converting Infopackage groups to process chains

    Hi guys,
    I was wondering if you could assis me on how to convert an Infopackage group to a process chain? I am in RSA1OLD [in BI7], and i am trying to convert all Infopackage groups to process chains. If you could explain how to do it step-by-step it will be helpful. Thanks in advance

    Hi,
    1. Goto prcess chain maintenance screen (RSPC)
    2. Create new Process Chain
    3. Create variant for Start process (Give description and Tech. name).
    4. From process types select "Infopackage" and drag it to the process chain window.
    5. Select Infopackages used in Infopackage Group (one bu one)
    6. Link thes processes as per the execution sequence in Infopackage group.(Click on process and drag to the other process)
    7. Activate the process chain.
    Regards
    SS

  • Process Chain Red 'X', Exec Infopckg Yellow, Infopckg monitor/data correct

    Dear and respectable colleagues of the forum,
    I am experiencing a problem in a process chain when executing infopackages. The process chain has 6 "Execute infopackage" processes. Sometimes (1 of 4 attempts average) my process chain ended with red color with 'X' status in the Process Chain Display Log View.
    Reviewing within the chain Log, there is one of the "Execute infopackage" processes that appears in yellow color (it loads from direct update ODS to an infocube). However, revising the Logs for its corresponding Infopackage execution I found that it says that "Data successfully updated". Moreover, If I review the data loaded it seems to have been loaded correctly.
    Then, Why does the "Execute infopackage" process in PC finishes with yellow color if the Infopackage execution itself finishes correclty?
    To complete the whole scenario: I execute this process chain every night from an Abap program; the program has a Loop that traverses a table, and executes the process chain as many times as the quantity of rows in that table (table has 10 rows meaning offices). As you can understand, the chain is executed 10 times, and the error occurs in any of the 6 "Execute infopackage" processes indistinctly.
    I review ST22 and SM37 for all users for the datetime when the error occured butnothing bizarre was reported. It is left to review SM21.
    The following is the detail of messages.
    Logs for Execute Infopackage
       Data successfully updated
    Monitor of Infopackage
      Details Tab
         Requests (messages): Everything OK      
         Extraction (messages): Everything OK
         Transfer (IDocs and TRFC): Everything OK
         Processing (data packet): Everything OK
           Data Package 1 ( 45 Records ) : Everything OK
             Transfer Rules ( 45  -> 45  Records ) : No errors
             Update rules ( 45  -> 45  Records ) : No errors
             Update ( 45  new / 0 changed ) : No errors
             Processing end : No errors
         Process Chains : Errors occurred
           Llena cubos de carteras vtas sec por distrib - autom

    Dear s v desh,
    I am on SAP BW 3.5, I already checked the cube and it is green - all right.
    The message in the infopackage excution node in the process chain says (non-error):
      "Data successfully updated"
    The error message in process chain monitor (log) says:
    ......"Overall status: Error occurred: or: Missing messages
    ............Process Chains : Errors occurred"
    I just realized that there is no messages at all in the infopackage monitor (log).
    I have received a clue, someone asked me to review note 1396417, and I will.
    Regards
    Juan Alonso Teevin

Maybe you are looking for

  • CUCM 8.6 - 8961 "Phone Not Registered"

    Hi, I can't get my 8961 to register to my CUCM 8.6. My 7941 registered without a problem. I verified that I correctly entered the MAC Address. My 8961 can reach the TFTP server and get its TFTP file. Status Messages: 00:41:37 VPN Error :VPN is not co

  • Grid photo gallery

    What is the best way to set up a photo grid gallery in DW6? I had previously used a table.

  • Can I run windows on iMac 24-inch?

    Hello, I am new to apple, thinking about buying a second hand Imac 24-inch Early 2009. Processor: 3.06 GHz Intel Core 2 Duo, Memory: 8Gb 1067 MHz DDR3, Graphics: NVIDIA GeForce GT 130 512 Mb, OS X 10.9.2. I understand bootcamp is included in this ver

  • PDK 6.0 for EP 6.0 SP9

    Hi I completed an Installation of EP 6.0 SP 9. I need to install PDK 6.0 SP9. But I am unable to locate it in the sdn.sap.com The link https://www.sdn.sap.com/irj/sdn?rid=/webcontent/uuid/84e5f758-0501-0010-07a7-a89474be25e3 just provide PDK 6.0 SP2

  • Transitions in imovie 06

    i have a bunch of pics in a timeline when i add transitions, instead of allowing the picture to play (slideshow) it pretty well goes right into the next transition on the timeline, it shows the transitions being actually connected how do i make sure