Information on APO or 3'rd Party Planning Software

Dear Experts,
We are into discrete manufacturing with MTO scenario & want to map the planning process in SAP PP. As we experienced in standard SAP PP has the ability to run MRP and perform unconstrained planning. Capacity Leveling is also very difficult task as the no. of orders are huge in our case.
Can some one please suggest the 3'rd party Planning Software that can be integrated with SAP PP. Also suggest some links on APO from where we can see the features / tutorials of APO.
Thanks & Regards,
Srinathan.

Srinathan,
APO is part of SCM.  Here is the SAP SCM site with lots of high level info
http://service.sap.com/scm
APO Supply chain planning overview
http://service.sap.com/~sapidb/011000358700001870512008E
APO online help at
http://help.sap.com/saphelp_scm70/helpdata/en/92/dd013872af2946e10000009b38f8cf/frameset.htm
I don't make recommendations for third party software.  However, SAP now has established a partnership with ICON, who created Supply Chain Response Management, an advanced planning tool which SAP now markets, and considers to be an 'add-in'.  Some info by SAP at
http://service.sap.com/~form/sapnet?_SHORTKEY=01100035870000739105&
Best Regards,
DB49

Similar Messages

  • APO DP - product characteristic in planning object structure

    I am using APO DP V5.
    In my planning object structure I am using a bespoke characteristic ZPRD for product. I have navigation attributes for this characteristic, which is why I am not using the standard 9AMATNR characteristic. So, in my planning object structure, I assign ZPRD as the product chaarcteristic (via Edit > Assign prod/loc).
    I have defined ZPRD as character 40, with conversion routine PRODU - so that it is consistent with 9AMATNR.
    In my solution we are integrating APO DP with a SAP ECC system, where of course the product is defined as character 18.
    So, my question is: does ZPRD <u>have to be character 40</u> (to be consistent with 9AMATNR), or could I defined it as character 18?
    Thanks,
    Bob Austin, Atos Origin

    HI,
    You can define the product out put lengh in customizing setting of APO.
    And also this setting is independent of R/3 system.Kindly refer
    the following help information on this customizing setting:
    'Specify Output Format of Product Number
    Dependencies
    Effects on SAP R/3 systems via SAP APO Core Interface (CIF):
    The settings made here are independent of the SAP R/3 system and only
    influence the conversion of the internal SAP APO display to external SAP
    APO display.
    As with conversion of SAP APO data, there is also a similar conversion
    of the internal SAP R/3 display to external SAP R/3 display. So that the
    numbers also appear immediately on the interface, it is recommended that
    you use a corresponding conversion in SAP APO and in SAP R/3.
    If the SAP APO is planning for several SAP R/3 systems, it may be
    necessary to make the identical numbers from different SAP R/3 systems
    unique in SAP APO. It is usual to use a prefix or suffix to do this. In
    this case, the internal SAP R/3 display and the internal SAP APO display
    are different. The conversion between the internal and external SAP APO
    display thus also differs from the conversion in SAP R/3.'
    Hope this will helps you.
    Regards,
    Sunitha.

  • General Discussion - Why to choose APO over R/3 for planning?

    Hi All,
    Why do we choose APO over R/3 for planning? What are the inputs or other factors that make APO a better planning tool?
    Are the factors which make APO a better tool not available foe R/3 planning?
    Thanks in advance
    Changed subject suitably.
    Message was edited by:
            Somnath Manna

    I do aggree what other have mentioned .Here are specific inputs on newly desined process in APO in comparisosn with R/3
    1. Existing Processes in SAP R/3
    <b>Forecasting</b>
    Forecasting enables companies to run statistical forecasting model, aggregate and disaggregate forecasts, as well as the capability to modify forecasting numbers manually
    Newly-Designed Processes
    Demand Planning DP (SAP APO)
    Demand Planning adds to forecasting capabilities to manage promotions, product introductions and phase outs, as well as the impact o causal factors, like weather or macro economic data.
    Additional forecasting techniques are available like Linear Regression (Causal Factors), Croston Method (Slow Moving Items) and Weighted Average
    Consensus based Planning enables Marketing, Sales, Logistics to share and collaborate on their forecast and create a final consensus forecast
    Forecasting based on characteristics instead of SKU for configured products
    2. Existing Processes in SAP R/3
    <b>Sales & Operations Planning</b>
    SOP allows to consolidate forecast based on supply capabilities, through reporting and interactive planning capabilities.
    Newly-Designed Processes
    Supply Network Planning SNP (SAP APO)
    Demand and Supply Plans can be intelligently balanced leveraging cost or/and revenue based optimization techniques
    Trade-off Analysis to determine product-mix, inventory build ups for seasonal demand, capacity allocations for alternative manufacturing locations etc.
    Web based information sharing and collaborative interactive planning environment
    KPI Reporting
    3. Existing Processes in SAP R/3
    <b>Distribution Requirements Planning</b>
    Traditional DRP logic allows to calculate requirements for a single stage distribution network
    Newly-Designed Processes
    Supply Network Planning SNP (SAP APO)
    Supply Network Heuristic enables to run DRP across the complete supply network generating requirements (production and purchasing) at each node.
    The planner can easily navigate through the network to view and modify demands and supply‘s in their different categories
    Demand Planning Units and Stock Keeping Units mapping can be done on quotations.
    4. Existing Processes in SAP R/3
    Not available
    Newly-Designed Processes
    <b>Deployment SNP (SAP APO)</b>
    The ability to deploy products through the supply network based on pull or push concepts. Different heuristics like fair share logics are supported.
    Transport Load Building allows to combine different products to a single load, interactive, as well as via heuristic to create full truck loads.
    5. Existing Processes in SAP R/3
    <b>Master Planning</b>
    Master Planning allows to plan production at an aggregated level including rough cut capacity planning.
    Newly-Designed Processes
    Supply Network Planning SNP (SAP APO)
    Supply Network Planning allows to consider distribution, production and transportation constraints concurrently.
    In addition to a generic SNP Optimizer based on Linear Programming and capacity leveling algorithms, industry specific optimization is available for
    Campaign Optimization
    Capable to Match
    6. Existing Processes in SAP R/3
    <b>Material Requirements Planning</b>
    MRP calculates material requirements based on BOM structures, lead times, lot sizes etc.
    Capacity Planning
    CRP in a second step looks at the capacity requirements
    Newly-Designed Processes
    Production Planning PP/DS  (SAP APO)
    Production Planning allows to consider material and capacity constraints simultaneously to derive material, capacity requirements and dynamic lead times. BOMs and lot sizing will be also considered
    Pegging relationships between customer order, production orders, purchase orders will be stored and enable bi-directional propagation if changes occur on the demand or supply side
    7. Existing Processes in SAP R/3
    <b>Transportation Planning</b>
    Manual Planning of shipments, including predefined master routes.
    Newly-Designed Processes
    Transportation Planning TP/VS (SAP APO)
    Transportation Planning enables companies to determine the right shipment mode and route based on demand and supply situation, considering transportation constraints and costs.
    8. Existing Processes in SAP R/3
    <b>Shop Floor Scheduling and Assembly Processing</b>
    Planning Table to view in a Gant Chart the schedule.
    Heuristics like forward/backward scheduling (infinite)
    Manual scheduling
    Newly-Designed Processes
    Detailed Scheduling PP/DS  (SAP APO)
    Finite and infinite scheduling, considering material, capacity, time and market constraints.
    Manual scheduling
    Scheduling optimization via optimization algorithms, like
    Genetic Algorithm
    Constraint based Propagation
    Kiran Kute

  • I need information abt APO

    hi friends,
    i am in bw, actually i need some information in APO, i heared APO is PP advanced module, is it related with SCM also. can i get general theory for APO, bec i need to make some reports in bw.
    please give me some basic material in APO.
    Thanking u
    suneel.

    Suneel,
    Have a look at this thread
    Data Flow
    Will try posting some more info
    Regards
    Kumar Ayyagari

  • Ship Load in APO causing incorrect Distribution Requirements Planning

    Hi,
    I would like to ask help to you guys am a bit new in APO, i am more on a R/3 person. Please kindly guide and help me to resolve this issue.
    Ship Load in APO causing incorrect Distribution Requirements Planning. Load 10000123 shipped but still showing in sales order line and Distribution Requirements Planning is calculating as if product is needed to fill order.
    What possible root cause of this where should i start to investigate. And how to fix it. please guide. Thanks a lot!

    Had figure out already on what to do on it.

  • FI Changes for HR Payroll Integration with Thrid party Payroll Software

    Hi
    I am looking for information the SAP FI activities/ Changes to be done for enabling SAP HR Payroll integration with third party payroll softwares. Can you give some issues you might have encounter and any recommended thrid party payroll softwares. Highly appreciate any documentation on the same.
    Regards,
    Vic

    Download all the files into Execel, hope after tht u can change it to CSV.... To download HR MASTER DATA use Ad-Hoc qqry. Else use SE11, SE12 or SE16 to download IT wise. PA starts with PA0000 ets OM starts with HRP1000. Hope through this u can download and send to 3rd party system....
    In std we are having an option for 3rd part PY transfer. Check this if help
    SPRO>CROSS APPLICATION COMPONENTS>PREDEFINED ALE BUSINESS PROCESS> HUMAN RESOURCES>HR EXTERNAL SYSTEM

  • Integration between SAP and third party tax software

    can some body explain me or provide me docs regarding integration between sap and third party tax software like vertex.
    Thanks

    Hi
    First configure the same via the following menu path:
    1.) IMG>Financial accounting>Financial accounting global settings>Taxes on sales/purchases>Basic settings>External tax calculation>Define physical destination
    2.) Then test connection (option is available there).
    3.) If the connection is successful, also verify that the external tax package installed supports the R/3 4.6 version of the API. You do that by going to:
    System Information>Function List
    Check if the following functions are listed:
    • RFC_CALCULATE_TAXES_DOC
    • RFC_UPDATE_TAXES_DOC
    • RFC_FORCE_TAXES_DOC
    • RFC_DETERMINE_JURISDICTION
    4.) Then test the tax data retrieval:
    From SE37, select the relevant function modules like RFC_DETERMINE_JURISDICTION.
    The above 4 steps are necessary to satisfy that the RFC connection is established
    Hope useful
    S Jayaram

  • I just tried to install Photoshop 4.0 to my iMac (version 10.9.3) and I was informed that there was an error with the software.  I could not install it.  Where do I go from here?

    I just tried to install Photoshop 4.0 to my iMac (version 10.9.3) and I was informed that there was an error with the software.  I could not install it.  Where do I go from here?

    Photoshop 4.0 is not compatible with MAC 10.9.3 . You will face issues as when Photoshop 4.0 was launched there was no MAC Mavericks and Adobe has not tested the version on new MAC OS.
    If you want you can download the latest version of Photoshop CC 2014 and you can use it as a trial for 30 days and you can plan to switch to the latest version.
    http://www.adobe.com/products/photoshop.html

  • Third Party Chatting Software

    Does anyone know if third party chatting software like jivetalk count towards the number of texts u have or solely as data b/c my plan only has 200 texts. If it counts only as data that would be great!

    If you are using Safari, then its data only. If you are using SMS, then it counts as text messages.

  • II am looking for information on iPad and iPhone apps and Mac software that are "top of the line" for academic research. The most current and comprehensive information I have found is dated July 2010.

    I am looking for information on iPad and iPhone apps and Mac software that are "top of the line" for academic research. The most current and comprehensive information I have found is dated July 2010.

    PogoPossum,
    My area of interest is in business and economic history. There is a considerable amount of reading and charting. Until the iPad hit the streets, I only considered stacks of books, journals, and downloaded documents, all marked up with highlighters, underlines, and marginal notes.
    Most of my PC based work involved MS Office, Endnote, and MS OneNote.
    What I would like to do with the iPad and MacBook are the same things (Office, Endnote, OneNote) and add the ability to read and markup all forms of printed materials from books to pdf to webpages.
    I cut my teeth on an iPod Touch and have tried a lot of the note taking and reading apps. Without a camera the standard iPod Notes works for short quick notes and long think pieces. I just emailed the content and downloaded the stuff to my PC. Obviously, I do not want to continue at this "non-integrated" level of work.
    Does this help?
    Dick

  • The best third party recovery software for  OS X?

    Can someone please recommend the best third party recovery software for  OS X. Accidentally emtied my trash when I shouldn't have.
    Thank you for your help.

    General File Recovery
    If you stop using the drive it's possible to recover deleted files that have not been overwritten by using recovery software such as Data Rescue II, File Salvage or TechTool Pro.  Each of the preceding come on bootable CDs to enable usage without risk of writing more data to the hard drive.  Two free alternatives are Disk Drill and TestDisk.  Look for them and demos at MacUpdate or CNET Downloads.
    The longer the hard drive remains in use and data are written to it, the greater the risk your deleted files will be overwritten.
    Also visit The XLab FAQs and read the FAQ on Data Recovery.

  • Third Party Reporting Software

             Can anyone give me a line on thrid party reporting software that dips into the CUCM and has the ability to create custom reports and then send them via email, FTP, text, etc.  Need something that can be scheduled and automated as well.  The CUCM is very limited.  Don't want to do a bunch of sql stuff either.  Need something that a simple administrator(s) can operate from a gui.    

    Hi John,
    Sorry for the delay...I'm not on the support forum on a regular basis.  This maybe an answer to your request - it's web-based, you can customize your reports with the data fields you want, schedule delivery of the report via email or FTP.  Here are some screenshots:
    It's called Variphy Insight.  You can find them online via Google, and ask for a free trial. Mention you found them via the Cisco Support Forum and they'll extend the 15-day trial license to a 90 day trial.
    Regards,
    Chris

  • Third party backup software, how is the log sequence working?

    Me and a colleague had a discussion about how third party software and full backups locally on the SQL works together.
    If we use TSM that do full backups and then logbackups every hour in between for example.
    If I between the two full backups from TSM accidently do a "non copy-only" full backup do I then also break the whole log sequence backup from then and untill the next TSM backup is?
    Or can I use the full backup from my mistake and then take the log backups from TSM that occured after that fail and restore the database?
    I guess this depends on the third party backup software, but in my mind it should work but according to him it doesn't.
    Try to "paint" how I mean:
    I = full TSM backup
    - = log TSM
    F = my fail backup full but not copy only.
    I---F-------I
              ^ is where I would want to restore with both my full one and the logs from TSM. Hope you understand what I mean.

    yes, you should be able to use the full backup taken in middle and use the rest of the log backups taken afterwards to restore the database.while I do not use TSM, we use QUEST(DELL) LITESPEED, that takes full backup once a day and log backups
    every 15mins.
    if someone accidentally takes full backup in the middle of day with out 'copy only',
    log sequence will break and successive log backups depend on this full back up.
    while this should be prevented from happening in first place, you can still restore from native full backup and then apply log backups taken from third party taken after the  native Full backup.
    if this happens, I would restore the FULLBACKP with NORECOVERY using NATIVE SQL and then use  lite speed syntax to restore the log backups.Remember, native sql cannot read third party formatted backups(atleast litespeed), thats why I restore the full backup
    using native sql, since it was taken with native sql backup and log backups using litespeed syntax.
    Hope it Helps!!
    Thanks, well it was just a theory discussion we had about the issue. But none of us could find info on the internet easy to prove our point :) Thanks.

  • UOM issue of SR that push from third party integrated software into SAP

    Dear SAP Expert/Guru,
    Would like to seek for your advise what is to be done to check the issue of different UOM created in SR when push from thrid party intrgration software into SAP.
    The material only being maintained 1 UOM which is PKT however, when the data being push from the integration software it created the material with the UOM CTN and this cause the whole SR cannot be used.
    Is there any way to check between the data integration? The client is using BAPI to push the data.
    Currently the client just implement PI module and the third party software is integrated with PI module.
    Kindly advise is there any other way to check.
    Thank you
    Regards
    Leonard Tan

    Dear Shailesh & Jurgen,
    Due to the T-code CUNI is maintained as Fire Fighter in the production server, so I only can use the QA server to analyst the UOM maintained in the server.
    Below is the result of the analysis:-
    <u>ISO Code</u>   <u>ISO code text</u>
    CT             CTN
    PK             Pack (assuming this is used as packet)
    As in the Change Units of Measurement of Dimension: Overview. THe result as shown:-
    <u>Unit</u>   <u>Commercial</u>   <u>Technical</u>   <u>Meas.unit text</u>
    CTN             KAR             CTN             Carton(SC)
    PKT             PKT             Pkt             Packet(s)
    When double click the "Units of Measurement, select any unit and click on the lens, here you will see a small box called ALE/EDI, you will get to see the ISO Code in the box and a small checkbox called primary code"
    There is no checking being clicked at the primary code and nothing is being keyed in the ISO code
    Kindly advise what is to be done? is it the ISO issue or is there any setting being done wrongly.
    Thank you
    Regards
    Leonard Tan

  • Wedding Planning Software - does it exist?

    I've been looking for wedding planning software for a MAC with no luck. Any suggestions? Wedding Planner is terrible with awful support - and the rest don't even offer a MAC version.

    I purchased and used such an application for OS 9 but that was many moons ago - well before OS X was available. I believe Wedding Planner is about it for OS X unless you install Windows on your MBP.
    http://www.amazon.com/Summitsoft-Wedding-Planner-Win-Mac/dp/B000CSRAN0

Maybe you are looking for

  • CUSTOS: COMO SE DÁ SEU CÁLCULO NO R/3?

    Amigos, Gostaria de saber como se dá o cálculo de custos de materiais no SAP R/3. Inclui-se os gastos operacionais ou não? E o custo direto e indireto o que usar pra esse tipo de cálculo de custo? Procurei na Biblioteca do Site mas, nada descobri, a

  • Additional duty taken 50% credit

    Hello, I have one scenario in which local  dealer vendor is procuring Import material & vendor is passing all creditable durtes to us. JMOP - Basic custom duty JEC1 - Edu CVD JSEP - Heigher CVD JAOP - Additional custom duty we are  procuring material

  • Spool request 0 missing

    Hi Experts, when i am in printpreview of the layout screen  of a smartform, when i am clicking on the Back button i am getting the error, Spool Request 0 missing . why the error plese help me on this . Regards Swaraj

  • Need Sun WorkShop 6 update 2  for Solaris 8

    Would it be possible to download an installation package for Sun WorkShop 6 update 2 for Solaris 8? I have an old development project that I need to resurrect, and it requires this version of the Sun compiler. Thanks, -Ken Cooley

  • Cannot connect to 10g instance from 11g client (ORA-12638)

    Hi, I don't know why I have problems when I connect from a 11g client to a 10g server. I get the error ORA-12638. However, it works fine doing the same with a 10g client. Can anybody tell me how to avoid this problem without having to install the 10g