Hi Kumar,
For connecting the ECC>>APO need to do following setting.
Settings in R/3
u2022     Check ALE settings or activate ALE settings
u2022     Define the logical system --  BD54
u2022     Assign logical system to a client -- SCC4
u2022     Set the RFC destination ---SM59
u2022     Assign target system and queue type--- CFC1
u2022     Maintain the SAP APO release--- NDV2
u2022     Activate BTEs for SAP APO integration ---BF11
u2022     User parameters for CIF ---CFC2
Settings in APO
u2022     Check ALE settings or activate ALE settings
u2022     Define the logical system --BD54
u2022     Assign logical system to a client ---SCC4
u2022     Set the RFC destination --SM59
u2022     Set up business system group
u2022     Create BSG--- /SAPAPO/C1
u2022     Assign logical systems to BSG ---/SAPAPO/C2
u2022     Maintain distribution definitions ---/SAPAPO/CP1
u2022     User parameters for CIF--- /SAPAPO/C4
Regards,
MJ

Similar Messages

  • Can anyone explain me the procedure and initial settings to do sto for schedule lines?

    can anyone explain me the procedure and initial settings to do sto for schedule lines?
    Create a STO with new doc type for material M1 to ship from plant 1 to plant 2 with qty as 100. On pressing enter you should be able to see schedule lines in delivery schedule tab. In schedule line you should see the Material availability date, GI date, loading date etc.
    can anyone give the answer for this question..

    Hi Megha,
    Please find below links for Config STO with schedule lines.
    http://dhavalatsap.blogspot.sg/p/configuration-of-plant-to-plant-sto.html
    https://scn.sap.com/thread/1260375
    Thanks,
    Bala.

  • Guideline Performance Initial Download from SAP for Utility into SAP CRM

    Hello,
    Please find below a link (valid for 10 weeks) to the document Guideline Performance Initial Download from SAP for Utilities into SAP CRM. The document is also published in the SAP Service Market Place at http://service.sap.com/utilities. Then choose Technical Information Center - Migration.
    The purpose of the document is to give guidelines as well as to share experience for an efficient and high performance execution of an initial download from an SAP for Utilities system to an SAP CRM system, such as:
    - Configuration of the initial download
    - Ensure optimum performance for the initial download of the relevant business objects
    - Avoid unnecessary business data being downloaded
    - Monitoring of the initial download and taking corrective actions in case of problems
    - Handle errors occurring during the initial download of business objects
    - Minimize performance bottlenecks
    The document explains the setup and configuration of the SAP for Utilities and SAP CRM systems only if necessary for the understanding of the solution of a described performance problem. This document does not cover the performance optimization of the delta down- and upload and the synchronization download.
    The document has the following structure:
    Chapter 1 describes the basics of an initial download
    Chapter 2 describes how to plan and execute tests to achieve an acceptable performance
    Chapter 3 describes the most important technical activities to prepare the involved systems
    Chapter 4 describes the most important functional activities to prepare the involved system
    Chapter 5 describes how to perform an initial download
    Chapter 6 describes measures to improve the performance of an initial download
    Chapter 7 provides a list of important repository tables
    Chapter 8 contains a list of important SAP Notes related to initial download
    I'd highly appreciate your valuable feedback on this document.
    Kind regards,
    Fritz
    Edited by: William Eastman on Feb 17, 2011 2:34 PM

    Hi Fritz,
    sorry for the late late reply but I didn't notice your answer.
    Here are my answers:
    (1) I monitored the behaviour on the CRM system, CRM 7.0, SP5
    (2) The change should be implemented in the CRM system
    (3) Deactivate buffering for scenarios marketing, sale and service via SM30 and table T770MATTR.
    By doing this the initial load of 3.2 million business agreements took around 2 hours, with activated scenario buffering I was at least ten times slower.
    After the initial load you have to activate the buffering again.
    Interesting to know would be why the scenario buffering only affects the initial load of business agreements and no other object. As far as I know the scenario buffering is relevant for the organizational management.
    Regards
    Alexander

  • Transaction CFC9 in ECC - regarding CIF change transfers to APO

    I am using APO 5.1 connected to an ECC 5 system.
    I am using ECC transaction CFC9 for CIF settings.
    How do the 'change transfer' settings (online/periodic) in transaction CFC9 actually relate to the use of the online change transfer via CFC5 and the use of the periodic change transfer via CFP1. Is there a dependency here?
    Thanks for any advice on this...

    Hi,
    CFC9 is where you specify what way you want to have the data transfer for master data from R/3 to APO - online, periodic or no transfer.
    Based on what you maintained in CFC9, you need to either maintain configuration relevant for ALE (periodic transfer) or BTE (online transfer).
    So, if you selected periodic transfer, you should use periodic change transfer using CFP1. Alternatively, you could schedule a periodic job corresponding to CFP1 to send change pointers from R/3 to APO. You should also select "acticvate ALE change pointer generally".
    Not sure what you meant by CFC5. If you want to send master data changes online (using BTE), you should have activated "online transfer using BTE".
    Thanks - Pawan
    Edited by: Pawan Pathak on Feb 15, 2012 6:16 AM

  • Impact of PR created in ECC from  APO

    Hi,
    there are 2 systems, ECC1 and ECC2. now , Purchase requisition is created in ECC1 and transferred to ECC2 through idoc messages.
    but the process is changed and  instead of PR created in ECC1 , APO creates the PR and transferred to ECC2.
    Now , my job is to analyse the impact of  PR  created from APO.
    what would be the impact and are there any side eefects of this ?
    Raghu

    Raghu,
    Based on the business requirements stated up until now, it is unclear what business processes will be performed in which systems, and what data must be maintained in each of the 3 systems.
    So, a direct answer to the latest post.
    If you create PRs in APO, and transfer to ECC2, the implication is that all data required for the creation of PRs must first exist in APO.  This means all master data, and enough transactional data to support PR creation, and configuraton to support planning (you haven't stated if you intend to perform planning in APO, but I will assume this is the case).
    If you thereafter treat ECC2 and APO as the primary OLTP-Planning combination, then there are no special implications.  You can establish 2-way CIF between this pair, and, as far as APO is concerned, you can 'pretend' that ECC1 does not exist.  The sole source of Master and Transactional data in APO would then be ECC2.
    If it is necessary to continue to exchage some data between ECC1 and ECC2, I would suggest that you continue to use IDOCs, and do not attempt to connect ECC1 to APO. In addition, my opinion is that you should evaluate, 'is it still necessary to retain 2 ECC systems?' 
    You ask about the impact of creating a PO in ECC1 without the benefit of a PR.  That totally depends on what you intend to do with the PO in ECC1.  Technically, SAP supports the creation of POs directly, without reference to PR.  However, without knowing your entire business cycles (eg, order-to-cash, plan-to-execute, and procure-to-pay) I can't tell you if you will run into problems.
    Regards,
    DB49

  • CIFing the data from APO to ECC

    Hi - I know how to CIFing the data from ECC to APO. But i would like to know how  to transfer the data from APO to ECC.I also would like to know how to debug the code...I see some of the questions in this forum on CIF debugging, but they are all CIFing the data from ECC to APO, but i need the other way around ( APO to ECC )
    Could anyone provide me the detail steps to CIF debugging ?
    I really appreciate your help.

    Hi
    What kind of data do you want to transfer from APO to ECC ? Lets say you want to transfer live cache reqs generated by APO to R/3 and create firmed reqs , then the following are the prerequisites
    1. Make the publication setting /n/sapapo/cp1 as mentioned by DB
    2. Make sure the material -plant for which you want to transfer reqs is active in the PO/ Preq integration model in R/3
    3. In APO /n/sapapo/sdp110  make sure the transfer setting is set to immediate.
    Once all this is done , you dont have to do anything manually. The reqs will get transferred to R/3 automatically.
    Also we have to transfer master data from R/3 to APO since R/3 is the master and i dont think it is possible to do the opposite - transfer of master data from APO- R/3 (no standard tool available) . Also we generally transfer only live cache reqs and PIR's (demand plan) back to R/3 . For PIR's you need to use the transfer profile.
    Thanks
    Aparna
    Edited by: Aparna.Ranganathan on Feb 11, 2011 5:21 PM

  • Transferring Product Master Data Changes From APO to ECC/R/3

    Is it possible to transfer product master data changes in APO to ECC via the CIF?  If so, does it require custom coding?

    Hi James,
    In all the different clients where APO is being used with ECC systems. ECC system is always the main system (system of record) which contains all the master data and data present in ECC supposed to be the reference for APO system for planning purpose.
    Generally it is not recommended to transfer master data from APO to ECC but as mentioned earlier by some experts you may have ways to do that.
    I would be interested in the business scenario where one needs to transfer master data from APO to ECC.
    Thanks,
    Anupam
    Edited by: Anupam Sengar on Aug 11, 2011 12:31 AM

  • Set up for Extraction the data from SAP ECC system

    Hi!
    I would like to analyze the transaction and master data from SAP ECC system into SAP BI system.
    I have created the connection (entry for SAP ECC system) within SAP NetWeaver System.
    Unfortunately when I try to load the transaction data for Info source the process does not end successfully.
    There are no information within SM58 on source system.
    The ST22 does not contain some suitable information.
    Question:
    Which settings do I miss and how can solve my problem?
    (user authorization, etc.)
    Thank you very much!
    regards
    Holger

    Hi!
    many thanks for your reply.
    The error I get:
    Errors while sending packages from OLTP to BI
    Diagnosis
    No IDocs could be sent to BI using RFC.
    System Response
    There are IDocs in the source system ALE outbox that did not arrive in the ALE inbox of BI.
    Further analysis:
    Check the TRFC log.
    You can access this log using the wizard or the menu path "Environment -> Transact. RFC -> In source system".
    Error handling:
    If the TRFC is incorrect, check whether the source system is fully connected to BI. In particular, check the authorizations of the background user in the source
    Can you please help me to identify the error?
    Thank you!

  • Same material number Ciffing from different ECC system

    Hello Gurus,
           I have APO system connected with two ECC system.
    If there is a material with the same name in both the system how does the APO system finds the respective system.
    Even if I assign BSG for the logical systems, to which system will the transaction data will be transferred after planning?
    Thanks,
    Siva.

    Although I do not have real-time experience working in this kind of scenario from what I understand there will be two product-codes based on the BSG.
    Eg. HAMMER@BSG1 will be the Product code for material HAMMER coming from your first ECC system which is mapped to BSG1 and HAMMER@BSG2 will be the product code for material HAMMER comping from the other second ECC system that is mapped to BSG2.
    Transaction data will then flow back from APO to respective ECC system based on the BSG mapping. Note in the Distribution Definition you maintain the connected ECC logical system name as well.
    Hope this helps.
    Thanks,
    Somnath

  • Purchase order creation triggered from APO diferent from one created in ECC

    Hi All:
    When you check the 'Conv. Ind' against a purchase requisition in /SAPAPO/RRP3 it triggers conversion of PR to a PO in ECC.  The problem is, the PO created this way does not have a tax code in the PO item> Invoice tab in ECC.  But if I try to convert the same PR to PO using transaction ME21 or ME21N in ECC this field becomes mandatory.  Question is , is APO trying to use a different transaction.  If so, how do I find out what it is? 
    Pl help.
    Thanks
    Ryan

    Thanks for your reply Sreeni:
    I understand the process of PO creation triggered from APO is automatic.  But what is the setup needed to automate it?  Is the setup in ECC or APO or both?  Where do you setup which PO creation transaction to trigger in ECC to create a PO triggered by APO? Pl. let me know.
    Thanks
    Ryan

  • Steps for IDOC trasnfer from APO to R/3

    Hi,
           I know we can transfer the of data say PR from APO to R/3 is done via CIF.
    Suppose if I need to transfer the same PR via IDOC instead of CIF how can I do it? Let me know the steps to follow and way to find out how the data got transferred (CIF or IDOC)?
    Thanks for your reply.
    Best Regards,
    SIva.

    Did you check log in SLG1 , /SAPAPO/C3 . whats is the message in the log.
    Can you check your queues SMQ1/SMQ2 in both the system , is there any block ?

  • Not able to cif transiton data from APO to R/3 and from R/3 to APO

    Hi:
    I have made all relevant setting as per required for configuration of cif architecture in R/3 and in APO.I am able to cif master data from R/3 to APO but when I am transferring Planned Order from APO to R/3 or Sales Order from R/3 to APO I am not able to tranfer it .Even I am not getting any blocked q.
    Even I am able to access remote login to both system by RFC Connection.
    Please let me know how to debug it and solve it.
    With Regards
    Ashish Gupta

    Hi Ashish,
    Please try ciffing only one transactional data and then check on the application logs using t-code CFM1 or SLG1 in R/3 and /n/sapapo/c3 & slg1 in APO.  This will give you idea where is going on wrong.
    Kindly confirm
    Regards
    R. Senthil Mareeswaran.

  • User-exit on APO side for the deliveries that are coming from R/3

    Hi,
    When a delivery is created in ECC for a VMI customer, it creates an EI order in APO. We need to record some details of these orders on the APO side.   Can you please let me know the user exit/BADI that gets triggered when a delivery comes to APO through CIF which we can use for our requirement?
    Thanks in advance.

    Hi,
        You can use APOCF006(EXIT_/SAPAPO/SAPLCIF_PU_001) CIF User exit on APO side for CF_OBJECTTYPE = B(Delivery).
    I hope this will help you.
    Regards,
    Saurabh

  • Wrong production version picked for planned order in ecc after CIF

    Dear experts,
    I am new to apo and was working on Cif of transactional data to ecc after planning run in Apo.
    we have active integration model and all the master data cifed in apo.
    we are cifing ppds ppm which is converted into snp ppm.
    The scenario is:
    We have a product FG100 at Loc1. For this product we have five alternate PPM's in APO.
    When we do SNP planning run, for some planned order it picked alternate 4 or 5 as source of supply. Which is alright.
    The problem is when we see the same planned order in ECC it shows source of supply as alternate 1. i.e. planned order in apo with alternate 4 and planned order in ecc with alternate 1.
    Is this the expected behaviour, or there is some configuration setting for this. We want that it shows the same source of supply in ecc as in SNP planned order.
    Best regards,
    AKS

    Hi Vikas/Nandkumar,
    thanks for the response, in my case the issue is that I have got two production versions in ECC. One production version is used for planning in CTM while the other version should not be considered in APO CTM for planning.
    The productionj version which I am not using for planning, I can manually attach the version in ECC to the planned order and the planned order should get CIFed to APO with the source of supply and resource details.
    Vikas after executing the report also the source of supply is not getting displayed in the planned order.
    Is their a solution by which i can achieve the above results.
    Thanks,
    Sanjog

  • How to set up the CIF from APO to R3?

    Hello
    we are trying to send planned independent requirements from APO ( SNP) to a specific PP scenario in R3 using the /sapapo/dmp2 transaction
    unfortunately no Plann Indep req are generated ( we suppose this is due to a luck in the CIF set up_ from APO to R3)
    could somebody kindly provide the steps of CIF ( from APO to R3) set up?
    thank you very
    elena

    Hi,
    You can check the CIF settings on
    http://help.sap.com/saphelp_scm50/helpdata/en/9b/954d3baf755b67e10000000a114084/frameset.htm
    Regards,
    Prafulla

Maybe you are looking for

  • No delivery costs exist for PO

    hi, during miro, i click on planned delivery cost indicator and got the error message as above. may i know how to know the PO has no delivery cost? 1) is it from purchase in record? 2) or is it from condition type? if from condition tab how to know t

  • Dynamic SQL Joining between tables and Primary keys being configured within master tables

    Team , Thanks for your help in advance ! I'm looking out to code a dynamic SQL which should refer Master tables for table names and Primary keys and then Join for insertion into target tables . EG: INSERT INTO HUB.dbo.lp_order SELECT * FROM del.dbo.l

  • Deleting photos from HD

    I see a lot of threads concerning deleting photos from the HD via iPhoto, but they all seem to be for previous versions of iPhoto, and none of those solutions seem to work for iPhoto 08. So... Does anyone know how to delete a photo permanently from t

  • Conditional suppress only if all column values are zero

    I would like to suppress whole column if dbfield value is 0.00. I was able to suppress it in common tab of format field by using formula if dbfield =0.00 then true else false. But i would like to suppress column value only when all the values in colu

  • Value mapping values to be reflected dynamically

    Hi All,    I have a scenario where R3 entries should be reflected in value mapping dynamically for a particluar field . Can anyone explain wht does the component SAP BASIS 7.00(NS- http://sap.com/xi/XI/System,MI -ValueMappingReplication) has the role