I have one inspection lot of origin 03 i.e. production. This production order has 3 operations in which 2nd operation has control key related to inspection. Operation 10 is not for QM
Whole Order is released on 10.12.2009 and accordingly i can see lot start date as 10.12.2009 WHICH IS WRONG.
Lot start date should be when operation 20 is starting i.e. 12.12.2009 but it shows 10.12.2009 when order is released. It should be operation specific dates
Why is system taking order release date as inspection lot start date? Is this standard SAP???
Please reply
Regards

Dear Vicky
03 inspection start date is based on operation date only. It is not based on the release day of the production .
When an inspection lot is created for a production order, the scheduled start of the order is used as the planned starting date.
you can get the same in the sap help also. Go to QA03 for the 03 inspection lot >  DATA for lot origin> press f1 on inspection start date
Check the order for the inspection lot and confirm whether the date maintained for the QM operation is 12.10.2009
Regards
Gajesh

Similar Messages

  • REPORT TO CHECK DIFFERENCE G.R DATE AND U.D DATE FOR A INSP LOT

    Hi
    I want to track how many dates it has been taken to clear a insp lot for a G.R. So I am looking for a report which shows these days or a report which have G.R date and U.D for inspection lot.
    Please guide if there are any reports for this.
    Thanks
    Dhananjay

    Dear Dhananjay
    This is available in MCXA, MCXC report as lead time. Lead time is nothing but time taken for clearing the lot after GR
    Regards
    Gajesh

  • I recently got the iPhone 4s, but my iPod has a lot of apps with a lot of data on them and don't want to start over. I already synced my iPhone from the computer that had all my apps from my iPod, how do i transfer the data over, the other apps did.

    I recently got the iPhone 4s, but my iPod has a lot of apps with a lot of data on them and don't want to start over. I already synced my iPhone from the computer that had all my apps from my iPod, how do i transfer the data over, the other apps did. But some reason the app Clash Of Clans did not. Thank you.

    If I wiped my phone I wouldn't have the contacts on my phone to send to my self.    I would need to take just the contacts from my back up. I would have to do this through iTunes and I don't see how I can just extract the contacts only from my back up. From what I can figure out it is all or nothing

  • Always used 1 main account.  Started using individual user accounts. So how do I use software or applications with a lot of data like Quicken under my own user account?

    I recently upgraded our family's mac to OS X.  I thought this was the perfect time to create and use "user accounts".  We had always used 1 main account.  So how do I use software or applications with a lot of data like Quicken under my own user account?  I wanted to be able to manage my own itunes library, iphone apps, messages.  But I still really need to use the Stuff I have in Quicken essentials.  I don't want to have to restart all my work done in Quicken already.

    I haven't used Quicken in a while, but most applications store your files in your Documents folder. Is that where your Quicken data file is? What you do next depends on how many family members need to get at that data.
    If multiple family members need to use the Quicken data file, try moving it to the Documents folder in the Shared account. That is an account that all accounts can see. It's at the same level as the other accounts. In other words, Shared is one level up from your Home account, or Hard Drive/Users/Shared.
    If you're the only one allowed to see that Quicken data, move the Quicken data file from the old main account to your account, and don't leave a copy behind. You can use the Shared folder as a way station for the transfer since you won't be able to see both accounts' Documents folders at the same time (because you're not allowed to peek into other people's accounts). Or you can use another disk or server for the transfer, as long as you can get to it when logged into either account.

  • Creation of Insp Lot through FM QPL1_INSPECTION_LOT_CREATE

    Hi Guru
    Can any body help me to create Insp Lot through FM QPL1_INSPECTION_LOT_CREATE
    based on fields of Z-table for following data:-
    Z-table relevant fields
    INSCALLNO- INSPECTION CALL NO
    PSPID-PROJ DEFINITION OR PLANT
    PACKCODE-PACKAGE NUMBER (PO NO.)
    INSP OFFICE AS ART FOR QALS
    MFR (MANUFACTURER CODE) AS LIFNR IN QALS
    Record to be created throuhg FM for QALS table
    following relevant fields are to be appended
    Z Field as ZZEBELN (PO no.)
    Z Field ZZINSCALLNO from INSCALLNO of Z-table
    PRUEFLOS
    LIFNR
    HERSTELLER
    MATNR
    KTEXTLOS
    ART
    STSMA
    ENSTEHDAT
    OBJNR
    ENTSTEZEIT
    KTEXTLOS
    ERSTELLER
    ERSTELDAT
    ERSTELZEIT
    and other relevant fields.
    Thnaks.
    YPB

    Hi
    for Inspection lot origin : 01 ,03 ,04 You can create Inspection lot manuaaly.through QA01 tcode.
    Regards
    Sujit

  • Cash flow start date and first posting date in REFX-RECN contract

    Hi,
    While reviewing old contracts, I have noticed that in contracts where first posting date is mentioned,  the cash flow start date is not editable in contract change screen.  In contracts where first posting date is not mentioned, the cash flow start date is editable in the change screen.
    Is this standard system behaviour?  Because i have read in the forum that cash flow start date is not editable after first posting of the conditions.
    I tried to change the field status of cash flow start date through RECACUST,  but despite keeping the field status as display,  the cash flow start date remains editable.
    Please help on how to make the field status not editable.
    sadhana

    Hi Sidhharth,
    Thanks a lot for your immediate reply.
    I still have one query.  You have written that
    Where First posting date is not updated it indicates that posting of the contract is yet to be done,not a single posting has been performed hence Cashflow date is editable.
    This means first posting date is always filled up after condition is posted.  but in our system i find that the date is blank and greyed out even after the 1st posting.
    Could it be due to having several conditions in the contract - some with one time posting, some with monthly posting?  eg.most of our contracts have atleast two contions - one for deposit which is one time payment, one for rent.  the first posting date is updated in individual condition for rent in conditions tab  but first posting date in terms tab is blank.     But even in single condition contracts, the first posting date is not getting updated in term tab (the field gets greyout out once contract is activated)
    Thanks once again.
    Sadhana.

  • Retrieve "Start date of Next financial Period" and "Current Period"

    Hi,
    T-code: cne5
    I would like to display 2 new fields in cne5 report result:-
    1) Start date of Next financial Period
    2) Current Period
    I can used
    CALL FUNCTION 'DATE_TO_PERIOD_CONVERT'
         EXPORTING
              I_DATE         = SY-DATUM
              I_PERIV        = 'K4'
    But what is I_PERIV ?
    How can I retrieve the above fields value? Any Function Module that I can used?
    Appreciate helps!
    THanks a lot.

    Hi,
    Yes, i_periv is Fiscal Year Variant.
    From running OB37, I can see that V3 and K4 fiscal year variant. Which one should I used when calling the function module DATE_TO_PERIOD_CONVERT?
    Thanks!

  • Org Management - How can I change the start date of all the org units

    How can I change the start date of all the org unit objects and its relationships at one shot ?  I have created some 100 Org units with the wrong start date. Please suggest.
    Thanks in advance..
    Cheers
    Vijay

    Hello Archana,
    Thanks a lot... This has solved my issue...
    Cheers
    Vijay

  • How to Update employee Effective Start Date

    Guys
    i am getting error while making terminate of an employee the error is being occurred as "the Person Must Exist as an Employee at the Time Specified by date start". after lot of finding, Ii came to know that the problem is being occur due to mismatch effective start date & original date of hire. so i need to update effective start date instead of Date Start(Hire date).Can you tell any one, Which api need to use update for this issue,
    Kindly help me.

    There is no API to update effective Start Date column.
    Your case falls into the type of data corruption in application tables. You either need to correct the data by yourself or take the help of Oracle support to correct the person data.
    If you decide to correct the data without taking help from Oracle support, you can always take help of these forums in doing the same. we will be more than happy to help you. :)

  • PROCESS CHAIN error "Incorrect start date"

    hi sap gurus,
    I have parent chain in that a newly created meta chain is creating problem.I am getting error in the process chains since two days i am not able to solve this.Can anybody try to help me.
    error: Incorrect start date: 00.00.0000; Start time 00:00:00 RSM     847
    After that the process chain is turning red,but when i manually execute the process chain its running properly.
    Please help me its urgent.

    hi gurus,
    Its working fine now.
    Solution:
    first exchange the variant with the smae and then activate and run.After that it will work in the process chain.
    Thanks a lot to every body,especially MOHAN KRISHNA,

  • Production order start date gets incremented by 1 day

    Hi,
    I have a scenario where in when the Planned Order gets converted to Production Order the Start date gets incremented by 1 day.
    If the planned order date is 11.02.2009 after converting to Prod Order it shows the start date as 12.02.2009.
    Can any please help me in resolving this issue,
    with rgds
    Ranjith Singh

    Dear,,
    Please run the MRP MD02 with Scheduling- 2 Lead time scheduling.
    Planeed order date may be from in house production time which is lot size independent.
    But production order date is from routing time which are lot size depnendent.
    Hope clear to you or come back if any problem.
    Regards,
    R.Brahmankar

  • BIAPPS how can we manually set both ETL start date and end date?

    Dears experts,
    how can we manually set both ETL start date and end date while conducting incremental load IN DAC?
    Please advise me.
    thanks,
    Joe.

    You can set those dates in the DAC system parameters tab. You should see lots of $$xxxxxx parameters.
    If I may, I'd suggest you use the OBI Applications forum for questions on DAC.
    Antonio
    BExpert, Brazil

  • Planned order start date & finish date

    Dear All ,
    I am running MRP for finished material ,
    But i am getting Planned order start date & finish date are coming same (todays date ). But when i am converting the order then proper scheduled dates are coming .
    Why for the Planned order the scheduled dates are not coming ?
    Regards

    Hi Venky,
    Pls try to understand how MRP works
    After MRP planned orders are created for the requirement(in house)
    In the planned order stage -basic dates are deteremined
    For the determintaion of basic dates system check the in house production time/replenishment lead time maintained in the material master
    For your requirement you maintain lot size dependent in house production data in the work scheduling view & check
    You have to key in data in set up time,processing time ,base qty etc
    Hope it is clear
    Rgds,
    SVP

  • Employee Start date

    Hi Experts,
    Can anybody tell me the TCODE to see employee master data like employee start date and end date.

    Hi Guys,
    Thanks a Lot.
    But i don't have authorisations to access those TCODES as iam BI consultant.
    Can you please give me the table names so that i can look for employee master,please.

  • Planned order start date is in the past

    Hi Experts,
    I am running MRP with lead time scheduling (2) at my production plant. The planned orders are generated against the requirements but the start date of the planned order is in the past. I have not mentioned anywhere in the configuration allowing the scheduling in past. I cross checked plant parameters, MRP group, settings for determining basic dates & scheduling parameters and every where start in the past check is blank.
    Since the planned order basic dates are calculated based on in house production time in material master, I maintained the lot dependant times in work scheduling view (Set up & processing time with base qty). But system is not considering this in MRP run. But its considering the lot independant inhouse prod time maintained in work scheduling view in MRP.
    Is there any other check to be maintained or system limitations? Your expert view on this please.
    Appreciate an early reply.
    Thanks & Regards
    Prathib

    Check OPU5
    S Anil

Maybe you are looking for

  • Report Background Engine Memory Increasing on Reports 6i

    Hi... we recently upgraded our ERP system from Developer 2000 to 6i. Some of our functions require many reports to print at once (labels, invoices, pick tickets, etc).. What we've noticed is that when we do this, the report background engine increase

  • File Size Shown in Folio Producer

    Hi, Is there currently a way to see the entire download file size of an app in Folio Producer? If not, this would be a helpful feature in another version of DPS, especially with the increased folio sizes with the new iPad.

  • How to set the Correlation ID in Oracle Q from JMS Adapter

    Hi, I'm using a JMS Adapter on my BPEL process to push messages to an Oracle instance in another machine. While testing, I could see that a message is posted on the Q table, but the Correlation ID is null. How is the correlation ID on the Q set from

  • Derivation Rule: COPA

    Hello Everyone, Could you please tell me how to write derivation rule in COPA.  I would appreciation if you send me any document related to it. Thanks in advance. Sneha

  • Explanation For the query

    Hi All, Could anybody please explain me the following query. How to display number value in words? SQL> select sal, (to_char(to_date(sal,'j'), 'jsp')) from emp; i know that j indicates Julion day. i am unable to understand how to_date converts sal in