Inspection Lot Type 03 Confirmation Pop-Up

Gurus,
Can anyone tell me why I am getting a Pop-Up that has the fields for 'Yield', 'Scrap' and 'Rework Qty' and Radio buttons for Partial Confirmation, Final Confirmation and No Confirmation on an 03 Lot when I complete all results and hit save in transaction QE51n?
I have my Master Inspection Characteristics on a Recipe and the lot generates just fine upon Process Order Release. I am just confused on why I am getting a confirmation and Qty pop-up on a Results Recording Save.
Please Help.
Thanks a ton.
Bruce

As Craig said, it's based on your settings of inspection point completion and the control key settings for an operation in the recipe/routing.  Check the operation in the recipe where the insp.char are maintained. Go to your recipe, double cliclk the operation and check the QM settings. There are 4 variants for inspe.point completion - I think you have the first variant selcted - quantity, valuation and production - due to this setting you are getting the pop up for quantity confirmation. If you do not want quantity confirmation, change it to valuation or automatic valuation.
This is not a SAP standard setting- simple Master data setting.
Hope it helps.
Thanks,
Ram

Similar Messages

  • Can this inspection lot type 06 be changed

    Hi! all
    could you please suggest me on this
    this is related to QM
    When using the standard SAP customer returns process an inspection lot is automatically created. Can this inspection lot type 06 be changed to allow stock to transferred to u201CUnrestrictedu201D or u201CBlockedu201D stock in a similar way as inspection lot type 01.
    regards
    Vikas

    Hi,
    Go to MM02, QM view, here deactivate inspection Type "06" and activate Inspection Type "05" i.e. Inspection for other goods receipt
    And then go to Schedule line category of Return sales (For e.g. DN ) in VOV6 and assign the movement type as 655 instead of 653 and then run the complete new cycle and check.

  • Manul Creation of Inspection lot type 01

    Hi All,
    While we create manual inspection lot with std inspection type '01', is it possible to allow to enter PO number  also ?
    Regds
    Jomy

    Dear Jomy
    It is not possible in standard to put the PO number. You can make use of the short text. please look into the below link for the same subject
    Link: [Re: Manual Inspection]
    Regards
    Gajesh

  • QM Scenario for Automatic Data Transfer to Inspection Lot

    Hi Experts,
    I have explained one QM scenario below. And also mentioned queries that I have in this. Could you please help me out on the same?
    There are 2 SAP systems, A and B.
    Process works as follows:
    -Delivery is created at A with B as recipient.
    -Automatically an IDOC is being created and send out with the quality data of the batch/inspection lot (electronic COA)  
    -In the background a workflow is triggered which transfers the data to the goods receipt from production inspection lot.
    In the system B, a subcontracting plant (DE08) will be created. During the subcontracting the materials provided to the subcontractor in real-life, however in SAP it will be brought to the subcontracting plant on a storage location specific to the subcontractor.
    Now the subcontracting service itself will be simulated by a process order (own order type is ZSUB). During the creation of the process order, a service purchase requisition will be automatically created which is connected to the process order. This purchase order will be transferred to A.
    After processing the purchase order, A will send service to B. B will do the process order confirmation. After process order confirmation an Inspection lot of type 04 will get generated automatically.
    Once the service delivery from A to B is done, the IDoc incl. the QM-data will arrive. Workflow will be triggered by inspection lot status CNF (Confirmed) – I0009. Now the workflow needs to identify the 04-'Goods receipt from production' of the process order and transfer the data into this inspection lot. The connection for this would be the purchase requisition number which is included in the process order. So the connection would be from purchase order number- purchase requisition-process order-inspection lot.
    Workflow template: WS03100078
    Business Object: BUS2045
    I have following queries. 
    1. Do I need to create Z-business object or the standard one will do the job?
    2. If I need to create Z-business object, then what changes will be required in coding?
    3. If I am using standard one, what all settings need to be done?
    4. What configuration needs to be done in the workflow template?
    Thanks & Regards,
    Mrunal

    Dear Swarup,
    The standard BAPI 's BAPI_INSPECTIONPLAN_CREATE Or ‘QAPP_CUST_IP_CREATE are not fulfilling my requirement .I need to create inspectiontion lot in R/3 system , which will invoke a process for creation of sample in another subsystem.But it is not very clear to me what a sample really means in QM, as i am an XI consultant .should a sample contain the recently generated Inspection lot number and its corresponding datas  ?

  • Inspection lot creation while partial comformation-QM

    Dear SAP Guru
    Can anybody plz tell me- how to create inspection lot while partiallly confirming production order ?
    It is being created at full confirmation of production order.
    Regards
    Pooja

    Hi All,
    Does someone have some specific instructions for the set up for QM inpsections?
    I need the steps, transactions and configuration for the inspection process.
    Is it possible that an inspection lot is created at the time of GR and then I just clear it or reject it using the UD. i do not want to do any other process like the sampling,defects recording,results recording etc.
    Regards,
    V S

  • INSPECTION LOT POSTING

    Hi Gurus,
    For some material Type, When i record results & do UD, in QA32 i am unable to post the stock in unrestricted use or any category as i am not getting a<b> tab of</b> <b>Inspection lot Stock</b> thr. which i can post the stock.
    I am unable to view stock of these materials in MMBE but these materials are purchased n are spare part materials.
    In Material Master QM view is also maintained properly.
    Suggestion required.Points will be rewarded.
    Thnx in Advance.
    Message was edited by:
            PRADEEP

    Dear Pradeep,
    For Inspection Lot Type nos - 04,01,05,08 are stock relevant,where in QA32,while
    doing the usage decision ,you will be able to see the tab page for Inspection Lot
    Stock.
    For Inspection Lot types - 12,13,06,03 & all manually created inspection lots are
    for Result & Documentation purpose,i.e they are non-stock relevant.
    Regards
    Mangal

  • Inspection Lot Selection

    Gurus
    I have 2 inspection types in my inspection lot origin 00 i.e. First is A & second is B.
    When i did MIGO for order created by Kanban; system created inspection lot type A
    When i create purchase order manually; it creates inspection lot B. Why? Here also i was expecting lot type A viz first
    On what basis there is difference in automatic and manual lot creation??? There is no preference given in material master also
    Regards

    Hi
    Are you sure you have inspection lot origin 00?
    What is the Preffered inspection type in Inspection setup.?
    For kanban order type have you maintained inpection lot type
    check following path
    QCC3->Inspec lot creation->Maintain Parameters for Production Order Type>select kanban order>Under plaaning tab check last entry
    check Inspection type>this can be a reason
    Regards
    Sujit

  • Inspection lot measure unit

    Hello,
    I am straggling to find out where  from the maintenance inspection lot (source 14) takes the "measure unit" to the inspection lot quantities tab?.
    I find that "The system always selects the base unit of measure from the material master as the unit of measure for the inspection lot quantity"
    But I works with inspection lot type 14 based on function location
    Our BW  team says that those units make them a lot of trouble
    Best regards
    eyal

    Hi,
    As per SAP help, system creates lot for maintenance order and for each piece of equipment.
    My understanding is ,system  always  takes measurement unit in Inspection lot as PC for Inspection type 14
    How ever for materials  i.e ROH , HALB, FERT with inspection types 01,03,04,08 etc etc  it takes from the material master as you mentioned.
    Regards,
    Nitin

  • Manual Inspection lot

    Gurus,
    I need to create a inspection lot for a confirmed production,is it possible.I take UD for Production order.Then shift the material to warehouse.Then i find the product is not perfect.I need to create an inspection fo this material,manually.

    Yes.. activate the 04 inspection lot.  But in the settings in the material master for the 04 inspection, click OFF the "Post to QI" indicator. When you do this, any inventory goes right to unrestricted inventory.  Shipping can pick the material and ship it to their hearts content.
    The quality guy can take a week to clear the inspection lot if he/she wants to. 
    If you really want to get slick, use DMR to have all the 04 lots created as SKIP lots.  Set a wait time on skip lots in the plant QM settings of say about 10 hrs.  Set up the automatic UD program to process the skip lots and run it every hour.
    When you confirm production, an 04 inspection lot with skip lot status will get created and all stock will go to unrestricted inventory.  If everything is good, ten hours later the 04 lot is processed automatically.  No one touches it.  If something is bad, the quality person has ten hours to access the inspection lot and record results, defects, problems, create notification, etc.... whatever you want them to do.
    Craig

  • Scrapping management from inspection lot 0130

    Hi Gurus !
    Please explain how to manage this scenario :
    Subcontractor vendor delivers us 10 parts coresponding to the last operation of our production order.
    We create inspection lot type 0130  at GR to control the delivery and find 2 parts to scrap.
    As in my inspection lot 0130 we can't manage stock, how can we scrap these 2 parts and keep the 8 good parts for our stock ?
    Thx

    Hello,
    sorry if it was not clear enough.
    Let us take an example.
    1) According of what the supplier said he will send, I create my batch  (BATCH01) via MSC1n and for the characteristic "color" I precise, it will be "yellow".
    2) The material is coming, I put it into my stocks via MIGO, giving the batch number (BATCH01).
    3) I get automaticaly an inspection lot and send a sample to the lab.
    4)The lab send the resutls and finaly the "color" is "orange". So in results via QA32,  I precise orange, and I expected my batch to be updated after the usage decision.
    5) But I still see "yellow"... the system tells me he is not able to change the value.
    I hope you can understand it better.
    Best regards

  • Inspection lot creation while partial comformation in 03 inspection type

    Hi
    I want inspection to be created while partial confirmation of operation in CO11N in 03 inspection.
    It is happening with release of production order.
    PLz let me know -if anybody can help.
    Regards
    Pooja

    Hi Ram,
    Just check the SPRO setting SPRO---> Quality Management ->Quality Inspection->inspection lot creation--->inspection for goods movement --->deactivate quality inspection for a movt type.
    Here against movt type 262 uncheck the QM not active tick.
    It will solve your problem.
    Cheers,
    Tushar

  • Inspection lot creation for inspection type 05

    Hi Gurus,
    We have finished material FERT & semifinished material HALB.We have assigned insp. type 02 & 05 in material master of matl. HALB.When we create production order for FERT & confirm the order , inspection lot is generated for matl.HALB of inspection type 02.
    Now we are reversing the goods issue by movement type mb1a, movement 262.In customizing for movement 262 inspection lot origin 05 is assigned.
    My problem is that when i reverse the goods issue with mvmt.262, inspection lot is not created for insp. type 05. What should be the reason behind this? or are any changes to be done to above setting?
    Regards
    Ram

    Hi Ram,
    Just check the SPRO setting SPRO---> Quality Management ->Quality Inspection->inspection lot creation--->inspection for goods movement --->deactivate quality inspection for a movt type.
    Here against movt type 262 uncheck the QM not active tick.
    It will solve your problem.
    Cheers,
    Tushar

  • Inspection Lot creation for the 103 movement type

    <<Don't ask for or offer points>>
    Dear Experts,
    we have the requirement of Creating the Inspection lot for the 103 movement type. we have done all the necessary settings for 103 movement type (in OMJJ and under the node   Quality Management --> Quality Inspection -->Inspection Lot Creation -->Inspection for Goods Movements) but still I am unable to achieve the results. Same is happening for 105 movements.
    Kindly let us know what settings need to be done in order to achieve the same.
    Full points will be awarded for the reply
    Regards.
    Edited by: Matt on Sep 18, 2011 4:44 PM

    Hi,
    If you have activated two inspection types (eg 01, 0101) of same inspection lot origin (01), in material master you should  have a preferred indicator set for the inspection type for which you want to be selected when you perform goods receipt.
    This check box is available in the inspection type set up in the Material master.
    Also check whether the post to inspection stock indicator is set for the material (in the inspection type), then only material will be posted to inspection stock.
    Please confirm, what happens to the stock after making MIGO. check in MMBE and confirm
    Go through the link and maintain the necessary settings. I think default settings for 01 type should work.
    http://help.sap.com/saphelp_470/helpdata/en/2d/350e4d448c11d189420000e829fbbd/content.htm
    Regards
    Hari

  • No inspection lot created for new inspection type created

    Hi all,
    We create a new inspection type which is based on a copy-version of an existing inspection type. These inspection type has a inspection type origin of standard SAP 04 (i.e. Goods Receipt from Production).
    Question 1 - we bumped into problem when come to testing in which when perform goods receipt, there is no inspection lot created, may I know why?
    The following fields of this new inspection type are all checked; those not specified, are not flagged.
    1 - Insp with task list (flagged); Automatic Assginment (flagged); Check Chars (flagged); Skip Allow(flagged); Automatic UD(flagged); Serial Number Poss (flagged).
    Question 2 - for this kind of inspection type with origin 04, do i need to perform a goods receipt against a production order or purchasing order? How do I perform a GR against a production order?
    Thanks.

    Hi Tuffy,
    Possibly you might not have ticked on preferred inspection type in material master. This could be one of the reasons. Try to do GR after ticking this.
    The setting you have mentioned (flagged parameters)are seems to be correct. But lot generation is governed by preferred inspection type.
    If you have assigned this newly customized inspection type to lot origin 04, then it would be used against production order and not the purchase order.
    There are several ways to carry out GR against production order. It depends on the scenarios which you follow
    1.     MB31 101 movement
    2.     You may use backflush so while confirming order through CO11N auto GR is posted
    3.     In case of repetitive manufacturing scenario generally GR is done by MFBF transaction
    Regards,
    Anand Rao

  • Inspection type 01 - inspection lot creation based on vendor batch number

    Hi Guys,
    this topic has been discussed several times here, but I was not able to find a suitable answer for my question.
    I am facing the folowing requirement:
    I have activated inspection type 01 for a raw material.
    I am receiving a firs goods receipt from vendor A with vendor batch number 0001.
    The system creates its own goods receipt batch number 0546 based on internal numbering.
    A new inspection lot is created.
    I am posting a second goods receipt from vendor a with vendor batch 0001.
    The system creates a new batch number 0547 based on internal numbering.
    A new inspection lot is created.
    I do not want to get the second inspection lot, because I received vendor batch 0001 before and I am assuming it has been inspected or is in inspection.
    Option 1: Post the second goods receipt against the first internal batch number created.
    I am aware of this need at the moment, but a user is not always checking if there is an internal batch with the same vendor received before.
    Can I customize the system to create inspection lots based on the fact that the vendor batch number was received before?
    Or do I have to use an exit and some ABAP code to get the wanted result?
    Thanks for your advice in advance.

    You need to use one of the enhancements that Do-Wook has suggested.  There is no standard SAP way to suppress the inspection based on the vendor batch number.
    With the first enhancement you use the system to check for a previously received vendor batch and if one is found, then that batch number is proposed and not the next one from the numbering series.  In this case, the lot isn't created than due to the inspection lot control of the inspection type.
    With the second enhancement you check the vendor batch number and if it's been received you suppress the inspection lot creation and the stock goes right to unrestricted.
    You'll probably need to do one or the other.  Myself, I prefer the first enhancement.
    Craig