Inspection plan for Pipelines?

Dear SAPIENTS,
Business scenario: Various pipelines located in plan and need regular inspection depending upon requirement. It can be 3 MOnth, 6 MOnth or anything. Inspection lot and result recording required.
Doubt: How can i link pipelines in system and how can i create inspection plan for them?
Regards,

Dear,
If i create as a equipment than where should i enter about its functional location and installation details.
i.e the reason i am asking if create an object link for the pipeline between two equipment or functional location than how can i create lot, notification for this link?
Regards,

Similar Messages

  • How to use Same Inspection plan for Multiple Plants?

    Hello,
    When I create a Process Order for material (M1), release and save it for a Plant A then I get the Inspection lot automatically.
    Now I have another Plant B that we have created. We would like to use the same Inspection plan that has been created for Plant A and M1
    So in the changed mode(QP02) of the Inspection plan for Plant A in the material assignment tab I added the Material M1 and the Plant B. I am assuming this means when I create the Process order for M1 in Plant B then it should use the same Inspection plan.
    But when I create the Process Order for M1 for Plant B, release and save it then it does not created the Inspection lot automatically(though I can create Inspection lot manually)
    Can you tell me if there is setting that will allow me to create the Inspection lot automatically on saving the Process order which should use the Inspection plan that I just assigned.
    And also let me know if there is a better way to handle same Inspection Plan for same material but multiple Plants.
    Thanks
    SAP Fans...

    Dear,
    For your message my understanding is that you are not getting Inspection lot created in Plant"B". Inspection lot for a material would get created based on the Inspection Setup for the material master "QM View", so compare the QM for the material in both plants and correct it for Plant "B".
    Probably I feel Inspection Setup is not complete for the material in Plant "B" - Generally when extending material by copying referance, in the QM view you need to click the Inspection Setup Button, for the data to be copied...otherwise it does not copy the Inspection setup from the referance plant.
    Regards,
    Prasobh

  • Measuring Instrument Needs to be added in inspection plan for each part

    Hi
    How to assign the Measuring Instrument in the quality inspection plan for all the materials.
    Whether i need to assign as material assignment or as PRT.
    how to use prt to assign to the operation in the quality plan (task list)
    Thanks
    VRAJ

    Hi,
    when i try to assign the Equipment for first Inspection Characteristics.
    the system thru the ERROR as,
    Production resource/tool is not intended for this type of task list
    Message no. CF230
    Diagnosis
    You want to use the production resource/tool in a task list or work order with task list type Q. However, according to usage 004 of the PRT, this task list type does not exist.
    Procedure
    Change the usage of the PRT in the master record or select a PRT which can be used in this task list type.
    How to resolve this issue.

  • Muliple inspection plan for same material and same usage

    Hi,
    I need to create multiple inspection plans for same material with same usage.during the inspection lot creation i need to select any one inspection plan.
    In standard SAP its not possible.Any user exits available for this..
    Regards,
    S.P.Selvathangam

    Dear Selvathangam Palanisamy ,
                                                       My Dear Shayamal is absolutely correct and we are corrently using this SAP facility. You can create 'N' number of inspectio plans for a material and then whenever the inspection lot will created ( Thru a process order or Manual) then you will get the Inspection Lot Status 'CRTD' (Created mode) then you have to select your Inspection Task list manually by two way...
    Either go to QA02 and then select it from the list of multiple plans.
    Or you can directly go from QA32 ...select your inspection lot row and directly click on the Inspection Lot icon to go directly to the inspection lot window to slect the Task list.
    Further there is no need to remove the Automatic Assignment from the QM View of the Material Master as if there is only one task List then system will automatically assign the TASK LIST, if you deselect it then you have to select in every case.
    Thanks

  • SAP QM Default Inspection Plan for all Inspection Lots created in the Plant

    Scenario: We have a Proto type plant in which Daily 15 to 20 materials are created every day. We have only one inspection plan for all the materials.
    Problem: We don't want to do material assignment in the Inspection Plant header every time a new material is created
    Requirement: Is there any way to default the inspection plan for all the inspection lots created in the Plant by Standard Configuration or User Exit.
    Your answers will be much appreciated and rewarded.
    Thanks in advance,
    Thiyagu

    Hi,
    In our case Creation of Inspection lots are controlled by QM View of Material Master. Our problem is to find alternative for assignment of New Materials in the Plan header in Tcode QP02, as we have only ONE INSPECTION PLAN. So our expection is all QM Inspection Lot created in the Plant should always get assigned to the SINGLE INSPECTION PLAN, with out doing any assignment of material in the Plan.
    Thanks,
    Thiyagu.

  • Inspection plan for inprocess inspection

    Hi QM Gurus
    please let me know can I use an inspection plan for inprocess inspection
    Thanks
    TR

    Dear,
    Inspection Plan is similar to routing, which will indicate what are all characteristics need to be checked / inspected when you receive a material. Is a master data. Once the inspection lot is created we will check the inspection plan and perform the inspection and give the defects recording and usage decision for the inspection lots.
    So for inspection type 03 use routing with usage as 1 and status as 4 and control key as PP04 to specify the inspection characteristics.
    when u cofirm that perticular operation it will ask to record the results. Inspection lot get genarated during order release this we can see in the order header data assignment tab. PP04 assignement says this operation is relevent for inprocess inspection and we need to assign MIC's for this which are relevent created in QS21 for this also sampling procedure created in QDV1.
    Regards,
    R.Brahmankar

  • Is it possible to create  inspection plan for "Inprocess Inspection"

    Hi,
    Is it possible to create  inspection plans for "Inprocess Inspection".
    If yes , what would be the "task List Usage".Is it "1"?
    If no ,then how to map this requirment?
    Regards
    Vemula

    Hi
    Vemula
    Generally as Per SAP std Routing is used for inspection of 03 type of inspection.
    but you can also customize the Inspection task list Usage for Inprocess Inspection.
    This is possible through
    QCC0>Quality Inspection>Insp lot creation>Assign Insp type to origine>
    here informt of 03 inspection type you can assign
    Task list type:Q
    Usage:either 1(Production) or 3(Universal)
    save
    Regards
    Poonam

  • Assignments of materials and vendors to inspection plans for the plant 1500

    Hi to all,
    Please give me solution for make assignments of materials and vendors to inspection plans for the plant 1500.
    Thanks,
    NAgesh

    hi gang,
    try to make usage decision ,kindly check in material document which you have created while making the GR, check in which storgare location you have specified and try to transfer the stock from quality to unrestricted.and also make a note on batch number also if you have activated the batch management
    regards
    thyagarajan

  • Inspection plan for all materials GOODS Receipt

    Hi qm experts,
    I have a scenario. How could I make an inspection plan which covers all materials with variable base unit of measure. Its because my client is using winlims for their results recording. I want to create only one inspection plan to incorporate all materials for assignment, how could I make this one. I hope anybody could answer my question.
    Regards,
    Edsel matildo
    QM Consultant

    Hi,
      Say u have different materials with different base unit of measure ( kg / ltr / ea / pc /  --- -
    etc ) And u have assigned all these material in qulity plan having only one unit of measure (say mm )for characterisrics then there is absolutely no need to maintain conversion rule for all these
    Beacuse base unit of measure is different and unit of measure is different .
    Note Conversion rule is only required if ur using alterenate base unit of measure
    Amol

  • Single inspection plan for all Inspection Plan usages

    Hi
    I have to prepare a single inspection plan, than can be used against inspection type '04' and '15' and '01'.
    Please tell me which inspection plan usage I should use, I tried '3' = Universal, but at inspection lot creation the system is unable to find inspection plan.
    Thanks in advance.

    My customer manufactures semi-finished good, some times he can purchase semi-finished from the market. Sample are reserved for future testing as well.
    so following inspection types are required for the same material
    1) GR against PO                '01'
    2) GR against Production    '04'
    3) Sample Management   '15'
    Almost all the time, the same specifications are tested and my customer wants to maintain a single inspection plan.
    I have one option that is to create 3 inspection types using all the above  inspection types and to use the same "Usage" say '5' in customizing of Inspection Type. But I don't know the consequences
    Please give me other solution or highlight the consequences of my solution
    Kindly help.
    Edited by: Chris SAP on May 13, 2010 11:36 AM

  • How to set up the inspection plan for the material in super BOM

    Hello,
    how to get the accurate inspection plan of the IQC for the material which was class item in a super BOM?
    I've gotten the characteristic value from the sales order, and get the PO after MPR. The problem is how to specify the target value and the range of inspection characteristic in inspection plan, because the value is temporary?
    Thanks!
    Lin

    Hello,
    I think you need to create MIC which linked with the configuration characteristic, and specify "inspection by configuration" for the inspection type.
    then the configuration value in the sales order can be transfered to the inspection lot when production released or goods receipts if you use inspection type 03 or 04. that means the value range for the MIC will be determined dynamically for each sales order.
    Regards, Winnie

  • Two Inspection Plan for the  same work centre

    Hi Gurus,
    I need your help,one of my client needs the following   requriment.
    1. He is having the two workcentre A and B
    2. A has lesser tolarance and b has the higher tolarance
    3.While confirmation the plan associated to the lesser or higher tolarance has to be automatically assign to the inspection lot.
    I think in standard  SAP, it canot be done
    Kindly suggest me way out
    Thanks in advance 
        Jai

    Hi Jai,
    1. You can go with the solution given by Mr. Reddy, You can cretate two insepction plans with two different tolerances assign the same material to both, system will give a prompt before releasing the lot for RR.
    2. You create singal insepction plan, assign the Both materail to it then, in the charecteristics overview screen, select the Charecteristics that is having differnt tolerence, and then you can use the Dependant charecteristic.
    Reward points is helpfull
    Regards,.
    Shyamal

  • Same inspection plan for different materials

    Hi, our materials are such that only visualinspection is required. so wants to create one insp plan to assign multiple materials. please advise how to do the same.

    Dear Raju,
    1.     QP01
    2.     Do not specify the material at initial screen
    3.     Put plant code
    4.     If required put group externally, otherwise system will generate internal number for it.
    5.     Enter
    6.     At header level you find Material assignment tab. Click there.
    7.     Here paste all material codes which have the same parameters of inspection.
    8.     Put group counter and plant code
    9.     If you want to assign n number of material codes, I would suggest to go for LSMW by recording method.
    Best Regards,
    Anand Rao

  • LSMW for Inspection Plan

    Hi Sapiens,
    I am a requirement to upload the Quality Management data through LSMW.
    1) Quality Info Recrod
    2) Inspection Plan
    For the first one, I could able to create Project in LSMW and successfully do for over 200 customers.
    I am saying problem in creating and uploading the Inspection Plan data.
    I created one inspection plan with a material in QP01 (Tcode), and assigned one customer in "Material Assignment".
    We have only hand full of materials (6-10 max) with MICs (10 - 15 max). So I using the same Inspection plan for material and I want to assign all the customer in Inspection plan at "Material Assignment". But at "Run Batch Input Record" in LSMW, it is failing. due to the below errors.
    1) Field MAPL-PLNAL(2) is not an input field
    2) Field MAPL-MATNR(2) is not an input field
    3) Field MAPL-WERKS(2) is not an input field
    I understand that these fields are repeating, as these fields are required in "Material Assignment" tab, where I will mention Counter, Matl, Plant and Customer. but it is saying these fields are not for input. If I dont use these fields in Field mapping then it will throw an error during actual recording.
    So, I need some inputs on it and all of your suggestions will be valuable.
    Awaiting of your reply on this soon.
    thanks,
    Mukesh

    Hi Mukesh,
    I would suggest to go for BAPI instead of LSMW for the inspection plans, if possible.
    Regards,
    Rahul

  • Inspection Plan specs for Vendors / Customers

    Hello every one,
    In my current client I had to maintain customer wise Quality specifications for each material. i.e. my quality parameters change for each customer / vendor. So how do I map the same? I heard we can use dependent characteristics specs. But I am not able to assign the vendor or customer here. Is there any specific configuration required for the same? If not, do tell me the step by step process to assign the same.
    Sincerely,
    Aji

    Refer
    Dependent Characteristic specs in inspection plan for customers
    "dependent char specs" push botton
    Dependent char for different materials in CWBQM
    dependent characteristic spec in qp01

Maybe you are looking for

  • Mapping problem with Multiple destination values

    Hi, I recently started to work on SAP MDM as a beginner. I am posting this message to get some help to solve the problems that I encountered as I run the SAP. For example, we can sub-categorize a 'Product' as Food>ProcessedFood>Frozen Food>Pizzas'. H

  • How to decompress the compressed backup files in BRTOOLS

    Hi Friends, I am new to SAP Technologies,.When i take offline backup,I took backup in compression mode instead of taking backup in Initialization of BRBACKUP tape volumes.Below i have attached the mistakes i did from log files.Please also tell me whe

  • Soft proofing copies gone?!?

    I am new to LR. I soft proofed several photos for printing. I came back to print another copy and the virtual copy proofing copy was gone. There used to be 2 side by side. Now to print do I have to readjust?

  • Select data form webservice

    Hi all! now I have a problem. I want to recieve data from mysql, I used web service and I built successfully, but it dose not return right. Please fix it for me! This code: package WsSrc; import java.sql.Connection; import java.sql.PreparedStatement;

  • SAP CC on Ubuntu?

    Hi, I downloaded the SAP Cloud Connector Linux (Developer) Edition from https://tools.hana.ondemand.com/#cloud and installed it on my Linux Ubuntu system. Then I started it via go.sh and tried to connect to it with the URL https:<host>:8443/. Unfortu