Integration of ECC 6.0 PM to EWM

Hi Friends,
I  am going to Implement PM mpdule in ECC 6.0.  WE are parallely implementing EWM (Extended warehouse mgmt).
What precaution should i take,  I dont know what are the integration points between ECC and EWM.
Please Help
Regards,
Shashikant

Dear salunke
There is no major integration between PM & EWM .
EWM is majorly used for warehouse Inventory managements.It also integrates with EHS for harzardous material management.
More info refer http://help.sap.com/saphelp_scm50/helpdata/en/5f/c69040bca2ef4ae10000000a1550b0/frameset.htm
regards !
Ajay

Similar Messages

  • How is the integration with ECC in SRM 7.0??

    Hi,
    Working with SRM 5.0 or 5.5  the use of XI for integration with ECC is not mandatory because when we send any document from ECC to SRM like requisitions (to convert them in shopping cards) or when we send any document from SRM to ECC like shopping cards, PO´s, contracts,  we only use the RFC´s and the abap programs.
    Is the same behavior with SRM 7.0?????
    Could the integration from SRM 7 with ECC 6 work with RFC´S without XI or for this vertions is XI mandatory?????
    Thanks

    SRM70 is closely integrated with XI for transferring docs between ECC and SRM.  SAP introduces eSOA tech nology with SRM70 and hence all documents like PR from ECC to SRM, Central Contract from SRM to ECC, PO creation (Classic), etc uses this techn ology.
    Thanks,
    Jagadish

  • SAP XI 2 BI Integration with ECC 6.0

    Dear all,
    we are planning to do XI integration between ECC 6.0 to BI
    1) How to Get the BI Standard data from ECC 6.0?
    2)We are planning to integrate Standard BI reports with ECC 6 0 through XI.
    Please sugget the scenario for integration between ECC 6.0 to BI through SAP XI.
    Thanks In Advance.
    Mahesh

    Hi Mahesh,
    Please go thru these links
    To push data from BW to XI, please check
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/biw/g-i/how%20to%20push%20data%20into%20bw%20from%20xi.pdf
    To send data from XI to BW please check
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/biw/g-i/integrate%20bw%20via%20xi.pdf
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/40574601-ec97-2910-3cba-a0fdc10f4dce
    XI-BI Integration unsing RFC
    Pushing data from BI to XI using RFC Adapter
    https://forums.sdn.sap.com/click.jspa?searchID=17734474&messageID=5878682
    Thanks,
    Shweta

  • CRM2007 integration with ECC 5.0

    Hi All,
    Will appreciate if someone can send a document or link that can help me with ECC5.0 and CRM 2007
    Regards,
    Suren

    this is copied from the installation guide
    Prepare an OLTP Backend System:
    n SAP R/3 or R/3 Enterprise systems as well as ECC 5.0
    systems require the R/3 Plug-In 2004.1 with at least
    SP10.
    See SAP Note 704564 (R/3 plug-in:PI 2004.1
    installation/delta upgrade) and SAP Service Marketplace at
    http://service.sap.com/r3-plug-in
    n As of SAP ECC 6.0, the R/3 Plug-In is no longer
    required. New and extended interfaces for integrating
    SAP ECC 6.0 are directly contained in SAP ECC 6.0.
    [SAP ERP 6.0 <Technology> on <Operating System>: Database
    then it should be done as with any OLTP system.
    I've done a connection to a R/3 Enterprise 4.7 system and that worked fine.
    Follow the Best Practices documenation and you will be fine!
    http://help.sap.com/bp_crmv12007/CRM_DE/HTML/index.htm

  • CRM 3.0 integration with ECC 6.0

    Hi all, I wanted to confirm if CRM 3.0 can be integrated with ECC 6.0
    If yes, then which support pack,etc. will be applicable and what all issues could be encountered in integration?
    Thanks in advance.

    Hi Animesh,
    just to be clear.
    the CRM and the backend ECC60 are communicating via  Plug -ins
    you can read more information here
    http://service.sap.com/r3-plug-in
    http://service.sap.com/~form/sapnet?_SHORTKEY=01100035870000601131&
    The other  SP level of the systems (BASIS etc.) are independent.
    Once you could conect the systems at basis level. You can begin your work at
    Application level.
    Whether you can have problems here please ask the CRM Gurus in a separate therad in other forum.
    I Hope I have answered all of your questions.
    Kind regards
    Imre Takácsi-Nagy
    Senior Support Consultant II.
    SAP Global Support Center Austria
    Netweaver WEB Application Server ABAP / JAVA

  • Integration of ECC Scheduling Agreement (Doc Type LP) with SAP TM

    Hello Experts,
    I am trying to integrate ECC Scheduling Agreement (Doc Type LP) to create OTR in TM System. I have maintained below settings:
    1. Create and Activate Control Key
    2. Output determination procedure linked to LP has output type TRS0 with requirement 27 assigned.
    3. Output condition record has been created
    4. I have checked Business Functions are also active
    I was able to transfer other Document Types like OR; RE; FD (ECC Free of Charge); SDF (ECC Subsequent Delivery - Free of Charge); Consignment Fill up and Consignment Pick up by maintaining these settings, but not able to push Scheduling Agreement LP to TM.
    The output TRS0 is not appearing automatically and if I try to insert and execute this output in Scheduling agreement, Output is failing with error message: "Order is not TM-relevant"
    Is there any other config or mapping or SAP Note that needs to be applied to achieve this integration? Because I believe standard integration is available for ECC Scheduling agreement (I have read in help.sap.com).
    Thanks and Regards,
    Vikram Bhardwaj

    Hello Vikram,
    You mean this documentation:http://help.sap.com/saphelp_tm81/helpdata/en/9c/787f3c0a771e57e10000000a114084/content.htm?frameset=/en/44/b0488e9c35612be10000000a155369/frameset.htm ?
    I think there is talking about the integration for SCM Basis as SOS, not Order Integration.
    Regards, Marcelo Lauria

  • ITS Integration with ECC 6.0

    Hi
    we are doing upgrade from 4.6c to ECC 6.0. It is technical upgrade. In SAP HR, we are using ESS timesheet entry (CATW). Now during upgrade we are facing problem in using ESS timesheet as we are using ITS server and SAP ECC 6.0 does not support ITS anymore. As the result the system doesn't allow to enter time data and save it through ESS, the error message it gives is "No Posted Data for 5_CPR_EXTID 5( Include LCATS_ITSF10)" but if we enter time in SAP directly then it is working fine.

    Replying to this old post hoping for some answers.
    We had researched this and converted to Integrated ITS using our ZCATW over a year ago. The notes read that while integrated ITS is a suppoted platform, ESS scenarios for which newer technology exists are no longer supported. We tested ZCATW under ECC5 and decided to move forward because of a pending technical upgrade. We are now in the middle of the technical upgrade and wishing to keep it technical we are trying to keep ZCATW going and then look at the newer components as a seperate project. Has anyone found a way to overcome the above issue in CATW/ECC6?
    Thanks,
    Doug

  • Error Connecting to SLD, while CC integration with ECC 6.0

    Dear All,
    I am using the CC v and from ECC IDES. I cannot connect to the SLD. It is giving an Error.
    When I try to register the Server Programs in Vis Admin and click the SET button I am getting an error "Error Adding Bundles". In the ABAP part I am getting the same error of RFC connection.
    Now from ECC when I do a SM59, and then goto TCP/IP connections, on creating this connections I cannot make them UNICODE as the R3 system is Non-Unicode. So these dont work.
    What am I supposed to do.
    Please let me know. This is very urgent and useful replies will be awarded full points.
    Thanks and Best Regards
    Chakra and Somnath

    Replying to this old post hoping for some answers.
    We had researched this and converted to Integrated ITS using our ZCATW over a year ago. The notes read that while integrated ITS is a suppoted platform, ESS scenarios for which newer technology exists are no longer supported. We tested ZCATW under ECC5 and decided to move forward because of a pending technical upgrade. We are now in the middle of the technical upgrade and wishing to keep it technical we are trying to keep ZCATW going and then look at the newer components as a seperate project. Has anyone found a way to overcome the above issue in CATW/ECC6?
    Thanks,
    Doug

  • Steps: SNC (Supplier Network Collaboration) Integration with ECC through XI

    Hi,
    Has anyone worked on the SNC(Supplier Network Collaboration) integration with SAP ECC via SAP XI.
    Could you pls share any documentation related to this. And also could anybody tell me the setup required to go ahead with the integration.
    Thanks,
    S

    Hi Xavier,
    SNC integration with XI has predefined mappings. So ask your basis guys to download the XI content for SNC using with PI. Once they deployed you will have a builtin predefined content in XI. Within the predefined content mostly they all are xsl mappings.
    If your requirement is with the standard idocs then you can use them directly. Else if their is customization they you may need to change the mappings according to your requirements.
    Also check this help:
    http://help.sap.com/esoa_scm_snc2007/helpdata/en/index.htm
    Regards,
    ---Satish

  • Sourcing integration with ECC using PI (percentage rebate scenario)

    Hi Experts,
    Sourcing - OP 7
    ECC - configurations done for rebate conditions as mentioned in standard configuratin guide
    PI - SP02 patch 0
    We are publishing percentage rebates in Master agreement from sourcing to ECC to create Online Agreement using standard predelivered content for PI from SAP, however ECC returns error in RFC response mentioning
    No currency code found for ISO code P1 in field HEADER_CONDITION/CURRENCY_ISO
    I checked PI content & I see for % rebates, field HEADER_CONDITION/CURRENCY_ISO is always populated in PI with P1.
    What are the next steps to be done in ECC or in PI to overcome the mentioned error.
    Any pointers will be appreciated, Thanks.

    Hello Jeet,
    I would suggest to check first that in both your SAP ERP and SAP Sourcing an ISO Code P1 for percentage exists. Further I would check if a rebate with an absolute amount works fine (also create multiple amounts and check if a scale is created in ERP, just to ensure that it works in general). E.g. check if the price condition/condition type exists and is configured correctly in ERP.
    If that all looks good you might want to check the ERP transaction BBP_ES_ANALYZE. I recently created a SDN blog about some tips and tricks, it also explains this transaction, please see ERP integration with SAP Sourcing – tips and tricks Maybe the error message(s) in this transaction will help you to better understand what is going on.
    Hopes that will help you
    Markus

  • Pro/E integration with ECC 6.0

    I want to integrate Pro/E with ECC 6.0 in order to transfer/exchange engineering data such as materials, BOMs, engineering changes, documents, etc.
    Does anyone know of Pro/E functionality or a 3rd party product that does this sort of thing?
    Kind regards,
    Rex L. Farris

    A direct interface is developed by .riess GmbH and SAP.  It is SAP certified and supported by SAP.
    For more information,
    Go to <a href="http://service.sap.com/plm">http://service.sap.com/plm</a>
    Life-Cycle Process Support -> Product Development -> Integration -> MCAD Integration -> Pro/ENGINEER

  • Integration of ECC 6.0 with SRM 5.0 SR2

    Hi Guys,
          Can any one please provide me with the steps for integrating ECC 6.0 with SRM 5.0 SR2.
    Regards,
    Max

    Hi ,
       Can anyone please let me know if any one has any kind of documentation on this.
    Regards,
    Max

  • C4C integration with ECC 5.0

    Guru,
    My company is looking for implementing cloud for customer, but our backend system is running on ECC 5.0.
    SAP had strongly recommended us to upgrade our ECC before implementing C4C project.
    Through some reading, it seems that integration prerequisite is ECC has to be version 5.0
    Or there is any workaround to integrate (standard integration) C4C to ECC 5.0 through HCI? Like by applying or enhancing standard iflow that released for ECC 6.0?
    Thanks.
    Cheers,
    Jim

    Not sure where you have read that ECC 5.0 would be supported. The official SAP position is summarised in the table below. You can clearly see that some functionalities even depends on what EHP level you are at with ECC 6.0.
    SAP PI and HCI leverage the same iFlow content.

  • Mobile Integration in ECC 6.0

    Dear Experts
    Is it possible for  IS Retail ECC 6.0 to have mobile intergration without Netweaver.
    Regards,
    Richa Grover

    Hi,
    It depends on the kind of Mobile integration that would fit-in for a specific business usecase.
    There are various ways of mobile integration even with out Netweaver like apps using Webdynpro online, other custom applications that directly talk to ECC via JCO etc mostly suiting light weight always connected scenarios.
    There are pros and cons for any kind of Mobile integration .
    Netweaver Mobile could be used to build mobile apps for occassionaly connected/disconnected scenarios and for wide variety of devices from windows mobile to smart phones available in the market.
    Regards,
    Liji

  • Integration with ECC 6 and Xcelsius

    Hi,
    I would like to know if its possible to integrate Xcelsius directly with an ECC report.
    For example, take the ALV data and 'send' it to Xcelsius in order to have an Xcelsius report.
    I know that Xcelsius has (now), built in integration with BW queries, but wonder if that is proprietary with BW, or can the concept of integrating a report from BW work in ECC?
    Please advise.
    Thanks.
    JP

    Hi,
    in case you would like to build an Xcelsius dashboard on top of ERP data you can use Crystal REports to connect to the ERP system  (see here: /people/ingo.hilgefort/blog/2008/03/23/businessobjects-and-sap-part-4) and then you can use Live Office to connect Xcelsius to a Crystal REports objects. see here:
    XC, CR and LO Part 1 of 4
    /people/ingo.hilgefort/blog/2008/10/03/businessobjects-and-sap-part-1-of-4--creating-a-xcelsius-dashboard-on-top-of-sap-bi
    XC, CR and LO Part 2 of 4
    /people/ingo.hilgefort/blog/2008/10/07/businessobjects-and-sap-part-2-of-4--creating-a-xcelsius-dashboard-on-top-of-sap-bi
    XC, CR and LO Part 3 of 4
    /people/ingo.hilgefort/blog/2008/10/07/businessobjects-and-sap-part-3-of-4--creating-a-xcelsius-dashboard-on-top-of-sap-bi
    XC, CR and LO Part 4 of 4
    /people/ingo.hilgefort/blog/2008/10/10/businessobjects-and-sap-part-4-of-4--creating-a-xcelsius-dashboard-on-top-of-sap-bi
    In regards to an ALV - there will be an integration with Crystal Reports but not for Xcelsius and keep in mind that an ALV is a push model and is only available when the transaction is been executed.
    Ingo

Maybe you are looking for