Integration of Time Sheet with FI

Hi Gurus,
Please tell me how accounting entry gets generated after entering the time sheet?
And also, from where system will pick the hourly rate?
Please revert back asap.
Thank you

Hello
PS integration with FI would be with the status of wbs elements,  egyou cant invoice till the status is teco. Your AP person may get an error and you will  have to co ordinate with PS team. You should understand the status of  wbs elements.
Created, Released, Teco.
Good to know all jargon of PS. you would invoice and enter a wbs element as a cost element. You may have to settle employee costs to a network they worked on.
Thats all i can think of now.
Plz assign points if helpfull

Similar Messages

  • Error while updating time sheet with BAPI_CATIMESHEETMGR_INSERT

    Hi Gurus,
    We are uploading data from 3rd party software to SAP with Z program.
    In this Z program using BAPI_CATIMESHEETMGR_INSERT.
    While updating data manually with CAT2 or with BAPI, data is entered properly without any problem but while using the bapi in Z program  error message " Version 0 is not set up for controlling area" is coming .
    Hence Version 0 is already active for the controlling area for fiscal year 2010.
    Please help me to resolve the issue.
    Thanks,
    Neha Duseja

    - First - Try to accomplish this via transaction CAT2 (*) (and then CATA or CAT6 to upload data to HR) - You may require some Customizing here ([Entry of Attendances and Absences for HR Time Management|http://help.sap.com/saphelp_bw/helpdata/en/64/400456470211d189720000e8322d00/frameset.htm])
    - Then - Use the same values in  [BAPI_CATIMESHEETMGR_INSERT|http://www.sdn.sap.com/irj/scn/advancedsearch?query=bapi_catimesheetmgr_insert#sdn_content_category_value_wiki]
    Regards,
    Raymond
    (*) Or ask to your functional

  • Integration of Plant Maintainence with Time Management

    Hello All,
    I need to present integration of Time Management with Plant maintaince.
    The focus points would be how to integrate Workcenter at the Plant with Time Management data of the employee.
    Kindly do send me any links or docs
    Pls this is very crutial for me and would appreciate anyone helping on the same
    Cheers
    Vijay

    Hi,
    The following might help u :
    http://www.sdn.sap.com/irj/scn/advancedsearch;jsessionid=%28J2EE3414900%29ID1321608750DB11628593195917906764End?query=integrationofTimeManagementwithPlantmaintaince
    All the BEST
    KRC

  • Why is my Time Sheet not working on Android Readers?

    I have a Time Sheet with Javascript that adds the times up, and it works perfect with the PC version of Adobe Reader, but when I try to use it on a nexus 7 tablet the calculations don't work.
    I have tried the official Adobe Reader for Android as well as about a dozen other readers.  If there is a reader that will work with this sheet as is, I don't mind paying for it, or perhaps part of my JavaScript is not supported on mobile, and I can change it with a workaround.
    Please Take a look and see what you can see:
    PR_Form_Tablet6.pdf - Google Drive
    Thanks,
    Mike

    Here's a list of what (should) work in Adobe reader:
    http://www.adobe.com/devnet-docs/acrobatetk/tools/Mobile/androidapi/index.html
    On Wed, Oct 15, 2014 at 5:32 PM, liquid One <[email protected]>

  • Timesheet(time Administartion- Time Sheet) WSDl is throughing error  when consumed by SOAP UI

    Hi,
    Requirement : We are trying to integrate the timesheet(time Administartion->Time Sheet) with external sheet
    We had downloaded the WSDL (i.e. Manage Employee Time data) from communication arrangment.
    when we try to process the same we are facing  the error as mentioned in attachment.
    can anyone help me on the same
    Regards,
    Prasad

    Hi Prasad,
    if you are testing Cloud WSDL via SOAP UI and any error you can check into Application and User Management --> Business Communication Monitoring --> and from drop down select "Reject Web Service Call" option to know more about your error.
    as per you error i thing if Work Assignment 1 is not available or may be leading zero problem, i don't know but you can check the error log into the cloud may be its helpful to you.
    Regards,
    Mithun

  • Time sheet customizing

    Hi,
    We are currently using CATS for posting time through Portal(7.0).  The users are not too happy about the UI.
    Is it possible to
    1)modify the Ui to make it more user friendly
    2)Is there a feature to copy previous weeks  time sheet to current instead of having to enter every day
    Thanks, Krishna

    Hello,
    I have similar requirement.  We are using Time entry iView    WD Java application.
    My requirement is to save the time sheet with working hours as template. So that, same template can be used for the future time entries. I can see the option to save the the data entry screen as template w/o working times(saving only Att/abs type).
    Can this functionality attained  through Time sheet configuration?  I have verified CAC1 but did not find anything related to my requirement.
    What are the other options I have? Any help greatly appreciated.
    Thanks,
    Batlanki

  • Problem with CAT2 - Time Sheet

    Hi Friends,
    We have recently upgraded the support packs and while testing the CAT2 transaction, when we correct the Time Sheet of an employee, system is giving an error message that " Collision with Full-Day HR record, there is a PTO in place on the same days but system should over write the existing entry in  R/3.
    Can any one give some inputs on this scenerio.
    Thanks in advance.
    Venkata

    Hello,
    Check CAC1 -> Data Entry Checks -> Collision.
    Then check the behaviour you want on this.
    Regards,
    Bentow.

  • How to configure Time-sheet in Project server 2013 please share the doc with screen shot

    How to configure Time-sheet in Project server 2013 please share the doc with screen shot
    Thanks and Regards, Rangnath Mali

    Hi,
    Please refer to the following Youtube video and article.
    https://www.youtube.com/watch?v=lZWvg4q17JE
    https://support.office.com/en-sg/article/Set-up-timesheets-and-task-status-672fa06f-8c4b-4e43-bfbc-4c355d681605
    Please don't forget to mark it answered, if your problem resolved or helpful.

  • The time sheet record collides with an attendance.

    Dear Expert,
    I got the following error message when I try to apply OT through CAT2.
    Message no. HRTIM00CATS208
    Diagnosis
    The time sheet record from 18:00 - 19:00 o'clock collides with an attendance or absence of less than one day recorded in HR Time Management. The record entered in HR Time Management is entered in the next line.
    My overtime is record in infotype 2002 and subtypes 1010 while the attendance is in infotype 2002 and subtype 1000. I just want the overtime to check against the absences (e.g. leave) but not the attendance. This attendance is just for display only.
    Any idea how to configure?
    Thanks
    Regards,
    Bryan

    Hi Aditya,
    My constraint class for infotype 2002 subtype 1000 (attandance) is 1 and infotype 2002 subtype 1010 (overtime) is 2.
    I already specify any class of infotype 2002 that crash with 2002 (any class) to N at V_554Y_B. But it is still giving me the same error message.
    Any idea?
    Thanks
    Regards,
    Bryan
    My constraint class for infotype 2002 subtype 1000 (attandance) is 1 and infotype 2002 subtype 1010 (overtime) is 2.
    I already specify infotype 2002 crash with 2002 (any class) to N at V_554Y_B. But it is still giving me the same error message.
    Any idea?
    Thanks
    Regards,
    Bryan

  • Integrate project open (third party tool for time sheet management) in EP

    Hello Experts,
    I have third party tool for time sheet management (Project Open) and EP7.0 SP17. I tried to integrate third party tool with portal by using the App integrator. But it is not working properly. Again and again its asking authentication. I followed same steps to integrate this tool by using App integrator in portal.
    we filled the system properties Server name is projects.company.local and Web Application URL is /intranet/.
    What i made mistakes in this, please help me.
    Regards
    Kumar

    If anyone knows how to contact Sacha Emery, ATE Systems Engineer @ NI, he may have more information regarding this.  (He may even have the DLL wrapper source code.)  His name is in the ITrax2 Readme.txt file as the creator.
    ~ Jay

  • Time sheet issues

    Here is the scenario-
    I have integrated project server with TFS. Assume a project test has a task/user story. In project server, i have assigned a user X with 50% availability to user story1 and this user story runs for 2 days. So the estimated effort is 8 hours, with 4 hours
    each day. Now i publish this  project and go to TFS and find the same user story assigned to the same user. Great!
    I now go ahead and enter the estimated hours as 8 and the remaining hours as 8. The user X goes in on day1, and in TFS enters Completed hours as 5, remaining 1 and saves the work item. Now, here is the issue. The user goes into project server, goes to his
    time sheet, finds the user story1 assigned to him on day1, clicks the check box and selects import task progress. Miraculously, project server assumes that the resource X has spent 4 hours on day1 for user story1 and 1 hour on day 2. While in reality, he has
    spent 5 hours on user story1 and nothing on day 2!!!!
    How do we solve this problem!! Any help urgently would be appreciated!!

    Any help from microsoft on this one????!!!

  • 1 sheet with multiple pages will not show various page numbers

    I'm having a difficult time differentiating between pages and sheets in Numbers. For example, I have 1 sheet with 5 pages. I am inserting page numbers (done, re-done several times after looking through the forum), but each page will not print with a sequential number (ie. 1, 2, 3, 4, 5). Instead, each page is 1. When I scroll over the number "1" on, say, page 3, the number 3 shows up. But unfortunately t will not print with anything but page number 1.

    I am having a problem that is close to this, when I try and preview my site in browser some of the pages show up as a white and gray blocks only.  I can not seem to find any reason or connection to what pages are doing this.  The only page that has a video seems to work fine.  Its almost acting like the links are broken or something.  Any help would be welcomed.
    Thanks
    Mike

  • Creation of Time sheet

    I have to create a time sheet as shown below,
                                         2011-10-03      2011-10-04    2011-10-05     2011-10-06    2011-10-07      2011-10-08     2011-10-09
                                           Time                  Time               Time                 TIme               Time                   Time               Time
                                         In    Out  Sign   In   out   Sign  In  Out   Sign    In  Out   Sign   In  Out   Sign    In  Out   Sign   In  Out   Sign
    SNO  Employee Name
    The above format will be taken as print weekly & the users will manually sign the sheet.
    Second & fourth Saturdays column back color should be changed to different color.
    Employee Names will be filled form the database & user input will be week No. The above output is fro week number 40, this year
    Can anyone please help me out who to start this report?

    Well, you do not say if you have a database to work from, so if not, start with excel.
    You can create a fairly simple table  in the example below  DATE is at A1, in A2, Out A3
    first date at B1, Sign in at B2, and Sign Out at B3, etc...
    DATE     IN     OUT
    10/3/2011     Sign In     Sign Out
    10/4/2011     Sign In     Sign Out
    10/5/2011     Sign In     Sign Out
    10/6/2011     Sign In     Sign Out
    10/7/2011     Sign In     Sign Out
    10/8/2011     Sign In     Sign Out
    10/9/2011     Sign In     Sign Out
    10/10/2011     Sign In     Sign Out
    When you build the report in crystal
    go to your data area and add
    DATE
    IN
    OUT
    I below the other.  ( My area is about 1 inch Tall, by 1 inch wide "more on that later )  I am using CR XI, so I hope your instructions will be like these
    Right click in the details section, and select  Format with multiple columns.   At the top right you should see a layout tab now.
    click on the layout tab, select a detail size of 1 inch (or whatever fits on your paper)   also select a printing direction of
    across then down.
    Preview your report,   You can add other columns as needed...   Hope this gives you a good start.

  • Dropdown Custom Field in CATS Time Sheet in ESS

    I have added a custom field in CAT2 transaction with drop down values from the custom table.  When I log on to ESS I was not able to see the dropdown in timesheet for that field. I am able to configure the field to have a search help dialog box.
    Let me know how can I configure the field to show dropdown values in time sheet in ESS? Appreciate your replies.
    Thank you,
    Rohit

    check CL_XSS_CAT_VALUE_HELP*
    or
    use implicit enhancement of CL_Xss_cat_value_help_general for the purpose
    build_f4_help Method in the class CL_XSS_CAT_RFC_COMMAND_TOOLS.
    or note 914125 on how to get different helps
    The table TCATS_SHLP_ITS also can be explored

  • Time sheet uploading from Non SAp to SAP R/3.

    Hi,
              I am trying to upload the time sheets from Non SAp to SAP with the datails like the sales oreder for which the employee worked, time spent ect.
              While uploading this from Excel to R/3 using se38, I am gettig an error saying "Enter sender activty also".
              I have checked if the activity type is checked in the CATS data entry profile, it is selected in the defaults.
             I have cheked in KP26, for the year we have given the planned activity also.
             In KSPI, I have run the price alculation for all the cost center with the activity type.
             I have seen the validity periods of the cost centers, activity typs are in line with 2010.
              I am able to upload the time sheets for a few employees and for a few it asks for the "Sender activity type".
              Please assist me, its very urent.
    Regards,
    Shilpa.

    For employees where you are facing this error, please check if Time Sheet defaults - IT0315 is maintained, and if not maintain it.
    Hope this helps.

Maybe you are looking for

  • HT2736 I want to buy a movie with a iTunes card?

    How I can buy movies with a iTunes card?

  • Posting  with document splitting

    What is posting with document splitting ?  Transaction code for document splitting.. <b>Helpful posts will be rewarded</b>

  • Objective Setting and Assessments

    Hello, I am working in Objective Setting and Assessments HR Project, I need some Appraiser & Appraiser Type Which is available in 0PAH_DS01,My all the reporting requirment is based on Infoset 0PAH_IS01, But 0PAH_DS01 is not availabe in that infoset,

  • Can XI process the sold-to IDOC before the processing the ship-to IDOC

    Hi Experts, Can XI process the sold-to IDOC before the processing the ship-to IDOC? For example if I have 10 IDOCs for both sold-to and ship-to, Can XI process all Sold-To IDOCs first, then process the ship-to IDOCs right after? I know that this can

  • Change pointers for HR master data

    Hi I am trying to setup change pointers for HR Master data , in relation to HRMD_A06 idoc , I did all the steps for setting up change pointers. Transaction bd52 for my reduced IDOC shows 0 entries, When i did the same for customer master data , BD52