Inter and Intra Company Stock Transport Orders

Hi All,
has anyone set up the following scenarios?
1. Intra Company Stock Transport Orders between 2 plants in the same company code and same Sales Org
i.e Plant 0001 (Supplying Plant) exists for Company Code 0001 and Sales Org 0001
Plant 0002 (Receiving Plant) exists for Company Code 0001 and Sales Org 0001
2. Inter Company Stock Transport Orders between 2 plants in different company codes and different Sales Orgs
i.e. Plant 0003 (Supplying Plant) exists for Company Code 0002 and Sales Org 0002
Plant 0002 (Receiving Plant) exists for Company Code 0001 and Sales Org 0001
We are unable to get both scenarios to work at the same time due to the fact that only one Sales organization for intercompany billing can be assigned to a plant.
Regards
Chris

Hi chris,
Followings steps are involved for configuring intra stock transport order.
Intra Company STO Scenario: Plant B receives material from Supplying plant A.
1.create combination of Shipping condition, Loading Group and Supplying plant.
2.Create Customer master with sales org, Distribution channel and Division.
3.Assign customer master to receiving plant with same Sales area.
4.Assign Delivery Type and Checking Rule.
5.Assign Document Type, One-Step Procedure, under delivery Tolerance.
6.Make Sure Assignment of  sales organization - distribution channel - plant
7.Create material master with purchasing view in plant B.
8.Extend material master with sales view to plant A.
9.In Plant A create STO (UB), with supplying plant. Check for shipping point XXXX.
10.In Plant B create STO (UB), with supplying plant.Check for shipping point XXXX.
11.Create delivery for XXXX shipping points.
12. Post Goods issue.
Thanks,
Muth's

Similar Messages

  • Vendor determination for Intra company stock transport order

    Team,
    We need the vendor and the partner function to be determined for intra company stock transport order.
    I have create Vendor and assigned the vendor to the plant code. When i create scheduling agreement with LU , the vendor filed is not getting updated as the agreement is with supplying plant.
    Is there any possibility that the vendor code and the partner functions can be populated to the Intra company stock transport order.
    Regards
    Gobinthan G

    Hi,
    To plant, you have to assign customer. Create a cutsomer and assign it to the plant through following path.
    SPRO-> Materials Management -> Purchasing -> Purchase order - > Setup stock transport order - > Define shipping data for plants.
    Then you assign delivery type and checking rule as per following path.
    SPRO-> Materials Management -> Purchasing -> Purchase order - > Setup stock transport order - > Assign delivery types and checking rules.  Here you can create the assignment of po document type with delivery doc type and checking rule.
    The last step is to maintain the all sales views of the material you tranfer, both of the receiving and sending plant.
    Now you will get the tab 'shipping' in the purchase order item details section.
    For intra company transaction as you said, in the vendor master, relevent customer code has to be updated.  This will make suitable updation in sales process in line with your scheduling agreement / purchase order.
    Thanks,
    Hari.

  • Intra company stock transport order with delivery to subcontracting vendor

    Hi Friends,
    We have an issue with Intra company stock transport scheduling agreement with delivery to subcontracting vendor.
    We have a scenario where the component is provided by another plant (Plant A -Intra company) directly to subcontracting vendor and the subcontracting vendor processes the component and sends us(
    Plant B) the finished good.
    We have a subcontracting scheduling agreement created with the subcontracting vendor with Item category u201CLu201D for plant B .(Document type LPA)
    And we created the stock transport scheduling agreement with document type LU (Between Plant A to Plant B) by entering the subcontracting vendor number to the "EMLIF- Vendor to be supplied/who is to receive delivery" field but the check box "LBLKZ-Subcontracting vendor" is hidden in the delivery address tab.
    Field selection with document type (LU) and Field selection with transaction code (ME37) did not help to bring the field to the delivery address tab.
    As a result, when we do PGI from the supplying plant, the stock is posted to "in transit" (Movement type 641) instead of "Component provided to vendor" (Movement type 641 u2013 O)
    The same behavior for purchase order with document type UB as well/
    Is the movement type u201C641-O u201C supported by standard SAP or do we have any other workaround to address the requirement. ?
    Now we are in ECC 6.0 EHP3.
    Your inputs will be highly appreciated.
    Regards
    Gobinathan G

    Hello,
    This EhP4 feature addresses only the one step Stock Transport Order to subcontracting vendor for intra company.
    Does anybody know how to do a two steps Stock Transport Order to subcontracting vendor for intra company?
    By "two steps" I mean:
    1- Goods Issue from supplying plant A to in-transit stock of the subcontracting vendor at receiving plant B.
    2- Inbound Delivery Notification (IDN) at receiving plant B + Goods receipt against this IDN into the subcontracting stock at receiving plant B.
    Thanks and regards,
    Stéphane

  • Overdelivery in intra-company stock transport order

    Hello,
    I have the following scenario - I have two plants, 1000 and 2000, both under the same company code.
    I transfer 450KG of material 123456 from plant 1000 using STO with SD (mvt. type 641), material is packed in HUs. In the receiving plant, the HUs are being place on a weight to check their actual weight. It;s possible for the actual weight be greater than the GI weight of 450KG (for example, due to weight scale accuracy issues) . When doing GR, I need to be able to receive quantity greater than the GI quantity. That is not allowed in stock transport order (per note 212387). For the same scenario with intercompany STO (GI mvt type 643) I'm able to post GR quantity which is greater than GI qty.
    Any suggestion on how to solve this? Can I create a customer order type that is both intra-company and allows for overdelivery?
    Thanks,
    Yossi

    a overdelivery does not make any sense in stock transfers, you would solve the problem of the stock accuracy in the receiving plant, but at the same time you create another problem with a negative stock in transit, that never gets cleared.
    a STO having stock left in transit is never considered as closed. even intercompany stock transfers are not considered as closed, even you can receive more than issued.
    Latest when archiving purchasing documents then you will see all your error in the process design, because only closed business cases can be archived.
    in stock transfer business you always have to care about both sides, you cannot just care about the receiving plant and ignore the problems of the sending plant.

  • Intra Company Stock Transport Order

    Hi,
    This is a scenario of Intra Company Stock Transfer (using Stock Transport Order with document type UB) from one manufacturing plant to another manufacturing plant within the same company code.
    I have created STO, prepared Outbound Delivery with T-Code VL10B and did PGI. Billing was done with T-code VF01 and Outbound Excise Invoice was created with T-Code J1IIN
    While doing Goods Receipt in the Receiving plant with the T-code MIGO, when I referred the outbound excise invoice that was created in the previous step with the T-code J1IIN (put Excise Invoice No. and Date), I got the following error message "Excise invoice doesn't exist in the supplying plant" and not any Excise Value is flowing from the Excise Invoice in the screen of MIGO.
    The CIN configuration and master data in J1ID seems to be ok.
    Please provide the expert opinions to overcome the issue.
    Thanks in advance
    Rajesh Praveen

    I did Goods Receipt with reference to Outbound Delivery in the Receiving Plant without referring any Excise Invoice Number (as our system has been designed now like this). I updated part RG23A part 1 using the material document number (generated as a result of Goods Receipt) in J1I5.
    Now I am trying to post RG23A part 2 in J1IEX with reference to the material document number (generated as a result of Goods Receipt) and putting the Excise Number created in J1IIN earlier. The system is picking BED, ECS and SECess values but the value of Base Value is not being picked up as a result of which I am not able to post the Excise Invoice.
    Please provide some idea to resolve this
    Thanks in advance

  • Inter - Company Stock Transport Order Issue

    MM SAP Gurus,
    When I try working on "inter company stock transport order between two company codes."
    I found the errors while creating PO(using document type UB)
    ie.
    *1st Error -Material 1 not maintained in Plant 2.
    2nd Error - Customer 1 does not exist (please check entry in plant 1)
    3rd Error - Not possible to determine shipping data for material1)*
    i couldnt find out the error................................
    Here is the configuration done by me......
    Company codes:c1,c2
    Plant for c1:p1
    Plant for c2:p2
    I m going to create and transfer stock from p2 to p1.
    Here i m using stock transport order with billing(SD)
    Purchase org for c1:porg1
    Vendor for c1,porg1:v1
    I assigned plant p2 in additional purchase data of vendor v1.
    Sales area for c2:sorg2,ds2,d2
    Customer for sales area(sorg1,ds1,d1):cust1
    Now i go to mm->purchasing->purchase order->setup for stock transport order
    > for receiving plant p1 i assign cust1,sales area(sorg1,ds1,d1)
    > delivery type for supplying plant:NLCC
    >checking rule RP.
    i assigned doc.type UB into receiving plant p1 and supplying plant p2.
    Then, in ME21N used doc type UB, these r the errors::::::::::::::::::::::::::::::
    *1st Error -Material 1 not maintained in Plant 2.
    2nd Error - Customer 1 does not exist (please check entry in plant 1)
    3rd Error - Not possible to determine shipping data for material1)*
    I already maintained all this.
    The doc type NB also I tried ,,,,,,,but same errors r being shown.
    Also where to create the inter company a/cs for billing?
    Please check the attached file for the error and let me know.
    Thanks & Regards
    Keerthi ...

    Business partner
    ●     Vendor master u2013 supplying plant
    Create the vendor for the purchasing organization of the receiving plant.
    Assign the vendor to the supplying plant in the vendor master record.
    From the menu, choose Logistics ® Materials Management ® Purchasing ® Master Data ® Vendor ® Purchasing ® Change (Current). Go to the Purchasing View and choose Extras ® Additional Purchasing Data.
    ●     Customer master u2013 receiving plant
    Create a customer master record for the receiving plant. From this, both the address and the data that is relevant for shipping point determination, such as transportation zone and shipping condition are taken.
    From the menu, choose Logistics ® Sales and Distribution ® Master Data ® Business Partner ® Customer ® Create.
    The above is from help.SAP:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/4d/2b90dc43ad11d189410000e829fbbd/frameset.htm
    Plz check this link for tht information.
    So, basing on this: I have customer 1 and vendor 1 for CC1......
    --> Customer 1 is assigned to the receiving plant with sales area1 in setup STO configuration.
    --> Vendor 1 is assigned to the supplying plant in the vendor master.
    --> My question for u is:
      1)  In ME21N, in the vendor field u assign the vendor from CC1 or CC2 (Because it says the vendor - external supplier if u read in F1 in tht vendor filed)
      Company code , Purc Org, plant all this will be from CC1 in ME21N, right?????????
    Material exists in both the plants P1 and P2.......right?????
    2) How to configure the inter - company accounts for the billing in sd for this STO scenario.???
    Please clarify these things.....
    You will be appreciated and rewarded too.
    Thanks
    Keerthi

  • Project Systems - Inter company stock transport orders

    We are implementing SAP Project Systems module for our client as part of ECC 6.0 global roll out and we are looking for a solution to meet the with following business scenario:
    The sales company (CC : US01)  receives a purchase order for large project from an external customer. The sales company creates a sales order in SAP with delivering plant  that belongs to another legal entity ( CC : US02 and plant : USP2) that has the main engg.facility . Two projects ( WBS elements ) are created for the sales company and engg.company . WBS element 1 element is used to drive milestone billing for the external customer and WBS2 element is created to post revenues and costs for the main engg.company
    ( CC :US02). The main engg.company plant ( USP2) has to procure sub structures from another legal entity in the company ( CC :US03 and plant :USP3) . We are creating an inter company stock transport order from USP2 ( main engg.company ) on plant USP3. In standard SAP , the stock transport order carries WBS2 that belongs to purchasing plant. But the business requirement is to have their own WBS element for USP3 plant to capture costs and revenues. What's the best of way of meeting the above business requirement either through standard SAP configuraion or some user exists with manual process.
    I'd appreciate any suggestions or ideas from the experts !
    Thanks

    Hi,
    Please check if the below link helps.
    [Project with Intercompany Billing|http://help.sap.com/bp_bblibrary/500/html/D48_ProjInterBill_EN_US.htm]
    Regards,
    P Gomatheeswaran

  • Excise Duty handling for Inter company Stock Transport Orders in SAP 4.6C

    I want to handle Excise Duty handling for Inter company Stock Transport Orders in SAP 4.6C. I know that SAP has provided standard solutions in 4.7C by giving one standard table OIH09 which can be maintained through Customisation.
    In 4.6C, even the Goods issue & Goods receipt button in item details of Stock Transport order is not available.
    Is there any work around for the same.

    In IS-OIL, cross company postings were stopped with Note #  623910 & would
    require a core modification to achieve this functionality.

  • Inter company Stock transport order

    Hi all we are using stock transport order for inter company postings,when we are trying to post purchase order through me 21n for material type FERT(finished)it is throwing erro "material xxxxx not maintained by purchasing".
    As for this type of materials we are running sucessfully in live environment,we are getting this error in  quality environment.
    for all other material types this will work fine,but for only finished it will through error.

    Hi,
    Kindly check the following views in Material Master.
    Purchasing
    MRP2
    In the MRP2 view, check the following field values:
    Procurement type
    Special procurement
    Kindly check the following links:
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b919243ad11d189410000e829fbbd/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/6f/28322ac77911d4b57d006094b9b9dd/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/75/ee0ccb55c811d189900000e8322d00/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b8ec943ad11d189410000e829fbbd/frameset.htm
    kindly reward points for all helpful answers!
    Kind regards,
    Thangesh

  • Plant as Vendor Defination and Assignment, for Stock Transport Order.

    Hallow All,
    Can anybody explain the procedure of  Plant as Vendor defination and their assignment for the Stock transfer with Stock Transport Order.
    Thanks in advance !!!!!!

    hi
    Following are the steps:
    1.Create a vendor for the company code of receiving plant, using account group :0007 using T-Code XK01.
    2 Assign this vendor to Delivering plant
    Go to XK02 >Purchasing view>Extras>Add. Purchasing data>Plant
    3. Create internal customer with the sales area of the vendor. Go To XD01
    4.In Pricing procedure determination relevant to STO, assign document Pricing Procedure and customer pricing procedure appropriate for STO to get the pricing in the invoice.
    5.Maintain condition records for the relevant pricing condition.
    6. Some more setting for STO: Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Receiving plant >assign customer here & Supplying SA (for billing) to Receiving plant here
    7. Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Supplying plant and assign the sales area of receiving plant.
    8. Go to MM> Purchasing > Purchase Order > Set up STO> assign delivery Type & Checking rule
    Assign the delivery type to document type. In this case, Delivery type NLCC is assigned to Document type NB
    9. Go to MM> Purchasing > Purchase Order > Set up STO>Assign document Type, One step Procedure, Under delivery tolerance
    Assign the document type NB to supplying plant and receiving plant
    10. After all settings , Create the STO using T-Code:ME21n and Save.
    11. Create Delivery :VL10G
    Click on the Background Button after selecting line item
    A message is flashed : See log for information> next Click on Log for delivery creation Button >click on line item>click on document button to get Delivery document No
    12. Picking, PGI:[VL02n
    13. Billing:VF01n
    Save the document and its done
    try this
    reward points if heilpful

  • What is Purpose and Usage of "Stock Transport Order" in Purchase Order.

    Sap Masters,
                       I have Created One PO Order with type <u><b>UD-Stock Transport Order</b></u>.
                       But I didn't know, How to Process in T_Code <b>VL10B</b>.
                       Kindly, Describe What is the Usage of VL10B Transaction ? And How to Proceed
                       it ?

    Hi,
    A number of procedures are available to enable you to transfer materials from one plant to another:
    -> Stock Transfer Between Plants in One Step
    -> Stock Transfer Between Plants in Two Steps
    -> Stock Transport Order Without Delivery
    -> Stock Transport Order with Delivery via Shipping
    -> Stock Transport Order with Delivery and Billing Document/Invoice
    In Purchasing, you can request and monitor a stock transfer with a:
    -> Stock transfer order
    -> Purchase requisition
    -> Scheduling agreement
    When a stock transfer involves two company codes and the issuing of a bill, you do not create a stock transport order but a standard purchase order
    (see also Cross-Company Stock Transfer).
    Where to find information about this?: See SAP-Library
    -> MM
    -> IM (inventory mgt)
    -> managing special stocks
    -> stock transfer in purchasing
    Best regards
    FSA

  • Inter Company Stock transport order - invoice posting

    Hello,
    I have a group of materials getting delivered from one plant to another plant and both the plants are in different company codes. Both the plants are in different company codes and so we adopted inter company STO process.
    The STO process works fine with out failure. But during goods issue and invoicing some of the materials stock and amount values are getting posted differently than what is listed in PO.
    Our end user complains that goods receipt is OK but sap goods issue and invoiced too much.
    I tried looking at the purchase order history and every thing looks fine. When I look at the pricing conditions, I see one of the pricing condition is displayed with a red radio tab ( indicating a failure) but this pricing condition is not adding any amount to PO.
    The end user runs the customized MM report  to correct these issues.
    Can some one explain why their is difference showing up during invoice and goods issue time.
    Thanks
    Rakesh

    This could you be material price diffrent in both companey codes.Check the VL03N post goods issue material document accounting doument and check th Billing document in vf03 transaction accounting document.It seems in invoice some extra conditions added in your case.Chack MM invoice through MIR4 invoice.
    Normally when inter companey sto you have to do sales invoice and it will generate Miro invoice background.Check these things you will get some clue.

  • Intra company stock transfer without delivery

    Hi,
    Can anyone give me the configuration steps for the intra company stock transport order by using UB type (Between two plants with in same company code) with out delivery.

    Hi,
    While I am doing Stock transport order I am getting the following error:
    "Not possible to determine shipping data for material 4500012"
    I have maintained the material 4500012 in both the plants.
    I am not quite sure to what you are trying to say but the cross company Stock Transport Orders can be done by:
    - Configure using transaction OMGN.
    - Depending upon the sending and receiving plants, maintain sales organization and customer data in customizing.
    - Maintain the supplying plant as a vendor and attach the plant to the vendor in the Vendor Master.
    - Material type has to be HALB or HAWA.
    - Ensure that the company with sales Organization has a plant to take care of stocking.
    - The PO used is NB and not Stock Transfer PO.
    Configure SD for inter-company billing to enable picking up the pricing procedure for billing.
    - Carry Out delivery through process delivery due list and billing through process billing due list.
    Otherwise, You need to configure your Stock Transport Order settings for your Cross-Company:
    Business Transaction to work.
    1. Customer No. for the Goods Receiving Plant - OMGN
    2. Availability Check- Checking Rule (if necessary) - OMGN
    3. Assign a Delivery Type for the Delivering Plant - OMGN (for Stock Transport Orders, NLCC)
    4. PO type (which i belive you have done) - OMGN
    5. Assign Vendor No. to the Supplying Plant (done) - VK02
    6. Assign Customer No. to the Purchasing Plant for the Inter-Compnay Invoice (but you need to assign this to the Sales Organization pre-assigned to the Purchasing Plant),
    IMG-SD-Billing-InterCompany Billing-Define Internal Customer No. by Sales Org
    ***and by the way for the Invoice to work between Cross-Compnay Plants, you need also to have a Sales Org for the Supplying Plant and a Pricing Determination Procedure.
    pherasath

  • Stock Transport Order - Partners not Determined

    Hi Colleagues,
    We have a simple Intra company Stock Transport Order and want to get the partner function 'VN' into the purchase order and then into the Inbound Delivery
    We have configured the partner schemas and assigned to the vendor account group 0007. Partners are created in the plant vendor record
    We have configured the purchase document schema and assigned this to document type 'UB'. However, the partners are not defaulted into the STO. We can assign them manually
    However, when we create the Inbound Delivery for the STO the vendor is not defaulted into the delivery and gives an incompletion error. We can manually enter vendor in the inbound delivery and then save the document.
    Any Ideas what is wrong or missing?
    Thanks
    Steve

    have a look into OSS note 863541 - Standard vendor for inbound delivery w/ purchase order refer

  • Inter company and intra company billing

    Hi Dina,
    Can you please explain the difference between inter and intra company billing and under what condition which one can be used?
    Thank you.
    Deborah
    Edited by: user4461879 on Mar 2, 2011 7:16 AM

    Hi
    Intercompany billing is done when both organizations, the provider and receiver organizations, are within the same operating unit.
    If organizations are in different operating units, you would be using intercompany billing.
    Oracle Projects cross charge functionality is quite different with those two scenarios.
    Cross charge within the same operating unit is called Borrow-and-Lent. This process generates journal entries for both organizations, sent to the same SOB. There are no AP and AR internal invoices involved with that.
    When you need to cross operating units, there are additional setup steps, like creating an inter-company projects for each one of the parties.
    Dina